Question

In: Operations Management

Question 1 options: Below is a table of times for Taxis (A to H) to reach...

Question 1 options:

Below is a table of times for Taxis (A to H) to reach Customers (1 to 8) who need a ride home after a night on the town. The goal is to Minimize the time it takes for all of the Taxis to reach their Customers. Only one Taxi will be sent to each Customer and each Customer needs only one Taxi.

Taxi / Cust

1

2

3

4

5

6

7

8

A

15

6

19

15

17

15

8

17

B

4

7

9

17

3

17

3

12

C

5

17

18

3

15

5

13

11

D

14

2

10

13

11

16

11

2

E

19

17

18

11

8

11

13

16

F

11

19

2

14

9

17

3

8

G

16

10

4

7

2

10

19

3

H

10

19

4

7

15

10

18

15





The optimal solution to this problem requires the following:


Taxi A picks up Customer


Taxi B picks up Customer


Taxi C picks up Customer


Taxi D picks up Customer


Taxi E picks up Customer


Taxi F picks up Customer


Taxi G picks up Customer


Taxi H picks up Customer




Minimum Cost =

Hint: Your cost should be between 33 and 39

Solutions

Expert Solution

Answer:

Taxi A picks up Customer 2

Taxi B picks up Customer 1

Taxi C picks up Customer 4

Taxi D picks up Customer 8

Taxi E picks up Customer 6

Taxi F picks up Customer 7

Taxi G picks up Customer 5

Taxi H picks up Customer 3

Minimum Cost = 35

Explanation:

It is an assignment problem which we can solve it using solver.

Excel Solver Solution & Parameters:


Related Solutions

Solve the question below: The following table illustrates a sample of maintenance task times observations. Use...
Solve the question below: The following table illustrates a sample of maintenance task times observations. Use the information in the table to calculate your responses for each of the questions. 74.66 75.40 47.18 59.63 59.87 57.36 55.94 66.00 43.45 51.22 62.26 69.15 66.61 53.03 59.51 53.97 46.62 63.77 70.50 68.93 56.73 40.51 57.30 55.07 54.89 35.85 69.60 52.93 61.05 64.62 43.85 53.27 50.87 59.96 42.15 51.67 61.65 42.87 57.15 52.57 60.49 53.82 43.75 64.07 67.35 54.10 68.07 55.83 34.05 57.83...
Consider a taxi stand where inter-arrival times of the taxis and the customers are both exponential...
Consider a taxi stand where inter-arrival times of the taxis and the customers are both exponential with means of 0.5 and 1 minutes, respectively. Stand has 3 spots that taxis can park while waiting for the arriving customers. Arriving taxis leaves the stand when all the spots are occupied. Similarly, arriving customers are also lost when there is no taxi in the stand. a. Model this system as a birth and death process by defining the state and the state...
Consider a taxi stand where inter-arrival times of the taxis and the customers are both exponential...
Consider a taxi stand where inter-arrival times of the taxis and the customers are both exponential with means of 0.5 and 1 minutes, respectively. Stand has 3 spots that taxis can park while waiting for the arriving customers. Arriving taxis leaves the stand when all the spots are occupied. Similarly, arriving customers are also lost when there is no taxi in the stand. a. Model this system as a birth and death process by defining the state and the state...
if you could classify these with the options below listed A-H. will upvote if answer all...
if you could classify these with the options below listed A-H. will upvote if answer all Sales discounts Additional paid in capital treasury stock Premium on bonds long term Loss on sale Sales allowances Leasehold improvements! Accumulated depreciation Unrealized gain on sale Customer deposits current portion Sales tax payable Payroll tax expense Discount on bonds long term Allowance for doubtful accounts Income tax payable Unrealized loss on sale A. Balance Sheet - Current Asset B.Balance Sheet - Non Current Asset...
QUESTION 14 Table 24-1 The table below pertains to Pieway, an economy in which the typical...
QUESTION 14 Table 24-1 The table below pertains to Pieway, an economy in which the typical consumer’s basket consists of 10 bushels of peaches and 15 bushels of pecans. Year Price of Peaches Price of Pecans 2005 $11 per bushel $6 per bushel 2006 $9 per bushel $10 per bushel Refer to Table 24-1. If 2006 is the base year, then the CPI for 2006 was a. 100. b. 83.3. c. 120. d. 240. QUESTION 15 Table 24-1 The table...
Determine the best alternative among the options in the table below if the MARR is 6%....
Determine the best alternative among the options in the table below if the MARR is 6%. Option A B C Initial cost $2500 $4000 $5000 Annual net benefits $410 $639 $700 n= 20 years. NPV= IRR= NPV i A B C 0% 1% 2% 3% 4% 5% 6% 7% 8% 9% 10% 11% 12% 13% 14% 15% 16% 17% 18% 19% 20% 21% 22% 23% 24% 25% a) Using Excel, construct a choice table for interest rates from 0% to...
The table below shows the means and standard deviations of the survival times (in days) of...
The table below shows the means and standard deviations of the survival times (in days) of some cancer patients who were treated with the same medication. Use these statistics to answer the question below. Type of Cancer Patient Mean Standard Deviation Breast 1395.9 1239.0 Bronchial 211.6 209.9 Colon 457.4 427.2 Ovarian 884.3 1098.6 Stomach 286.0 346.3 Which type of cancer patients      (a) had the highest average survival time?        (b) had the lowest average survival time?        (c) had the most consistent...
A die is rolled 120 times to see if it is fair. The table below shows...
A die is rolled 120 times to see if it is fair. The table below shows the outcomes. Face Value 1 2 3 4 5 6 Observed Frequency 15 18 26 20 14 27 What can be concluded using a level of significance of 0.05? H0: The distribution is uniform. H1: The distribution is not uniform. p-Value = Conclusion: There is insufficient or There is evidence
The estimated times and immediate predecessors for activities in a project  are given below in the table....
The estimated times and immediate predecessors for activities in a project  are given below in the table. Assume that the activity time  are independent. Task                            Predecessor                   Optimistic   Most Likely   Pessemistic                                                                                Time (wks)    time (wks)     time (wks) Architectural design                           --           10                  30                    45 Software                      Architectural design     13                  15                    23 Compilg                      Software                          2                    3                      4 Hardware                    Architectural design     15                  20                    25 Integration                  Software & Hardware   20                  22                    24 Bug fixes                     Integration                    3                    4                      11              a)  Draw an activity-on-node network diagram for this project. b) Identify the critical path and estimate the expected time to complete the project. c)  What is the probability of finishing this project in 77 weeks?
Which situation below would you be considered a principal in an agency relationship? Question 1 options:...
Which situation below would you be considered a principal in an agency relationship? Question 1 options: As a mechanic, you provide maintenance on a car. As a manager you present an update on the company at the annual shareholders’ meeting. As a mutual fund manager, you buy and sell securities for the fund. You meet with an architect to see the design of your new house.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT