In: Finance
An MNC IT company based in Germany, named IT AG, has identified
two
mutually exclusive cost saving projects. However, the equipment
that will be
required to realize the cost savings need an upfront investment of
$250
million for both the projects. The annual cost savings expected
from project 1
is 15% of the annual revenues and from project 2 is 12% of the
annual
revenues. The equipment used in both the projects have a useful
life of 4
years. The firm has decided to employ a Straight Line Method (SLM)
of
depreciation and the ending period book value is zero for both
the
equipment. The firm expects to sell the equipment for projects 1
and 2 for $50
million and $100 million respectively at the end of 4 years. The
year 1 revenue
projected for this firm is $500 million, which is expected to grow
at an annual
growth rate of 5% for the subsequent years. The tax rate in Germany
is 15%.
Which project would you choose based on a discounting rate of
10%
The cashflows are calculated for 1st project as follows :
Project 1 (Amounts in Million $) | |||||
Year | 0 | 1 | 2 | 3 | 4 |
Revenues | 500.00 | 525.00 | 551.25 | 578.81 | |
Cost Savings | 75.00 | 78.75 | 82.69 | 86.82 | |
Depreciation | -62.50 | -62.50 | -62.50 | -62.50 | |
Inremental EBT | 12.50 | 16.25 | 20.19 | 24.32 | |
Less Tax @15% | 1.88 | 2.44 | 3.03 | 3.65 | |
PAT | 10.63 | 13.81 | 17.16 | 20.67 | |
Add Depreciation | 62.50 | 62.50 | 62.50 | 62.50 | |
Capital Cost | -250 | ||||
Post taxSalvage value | 42.50 | ||||
Cashflows | -250 | 73.13 | 76.31 | 79.66 | 125.67 |
NPV of project 1 = -250+ 73.13/1.1+76.31/1.1^2+79.66/1.1^3+125.67/1.1^4
=$25.23 million
The cashflows are calculated for 2nd Project as follows :
Project 2 (Amounts in Million $) | |||||
Year | 0 | 1 | 2 | 3 | 4 |
Revenues | 500.00 | 525.00 | 551.25 | 578.81 | |
Cost Savings | 60.00 | 63.00 | 66.15 | 69.46 | |
Depreciation | -62.50 | -62.50 | -62.50 | -62.50 | |
Inremental EBT | -2.50 | 0.50 | 3.65 | 6.96 | |
Less Tax @15% | -0.38 | 0.08 | 0.55 | 1.04 | |
PAT | -2.13 | 0.43 | 3.10 | 5.91 | |
Add Depreciation | 62.50 | 62.50 | 62.50 | 62.50 | |
Capital Cost | -250 | ||||
Post taxSalvage value | 85.00 | ||||
Cashflows | -250 | 60.38 | 62.93 | 65.60 | 153.41 |
NPV of project 2 = -250+ 60.38/1.1+62.93/1.1^2+65.60/1.1^3+153.41/1.1^4
=$10.96 million
As the NPV of 1st Project is more than project 2, Project 1 should be selected.