In: Operations Management
Consider the following linear programming problem:
Maximize 10X + 8Y
Subject to: 40X + 24Y <= 600
20X + 30Y <= 480
all variables >= 0
Hi,
Please find answer as below.
If you like the answer, please up vote. It will encourage me to contribute more.
Answer
Maximize | 170 |
X value | Y value |
9 | 10 |
I have used excel solver to solve the problem. I have attached screen shot of Input data, Formulas and constraints used along with the optimal solution.
1. Snapshot of Input Data
2. Snapshot of Formulas used
3. Snapshot of Constraints used
4. Snapshot of Optimal solution