In: Finance
Let’s compute IRR of the security using trial and error method.
Computation of NPV at discount rate of 8 %.
| 
 Year  | 
 Cash Flow (C)  | 
 Computation of PV Factor  | 
 PV Factor @ 8 % (F)  | 
 PV (C x F)  | 
| 
 0  | 
 -$ 8,000  | 
 1/ (1+0.08)0  | 
 1  | 
 -$ 8,000.00  | 
| 
 1  | 
 $ 1,000  | 
 1/ (1+0.08)1  | 
 0.92592592592593  | 
 $ 925.925926  | 
| 
 2  | 
 $ 1,000  | 
 1/ (1+0.08)2  | 
 0.85733882030178  | 
 $ 857.338820  | 
| 
 3  | 
 $ 1,000  | 
 1/ (1+0.08)3  | 
 0.79383224102017  | 
 $ 793.832241  | 
| 
 4  | 
 $ 1,000  | 
 1/ (1+0.08)4  | 
 0.73502985279645  | 
 $ 735.029853  | 
| 
 5  | 
 $ 1,000  | 
 1/ (1+0.08)5  | 
 0.68058319703375  | 
 $ 680.583197  | 
| 
 6  | 
 $ 1,000  | 
 1/ (1+0.08)6  | 
 0.63016962688311  | 
 $ 630.169627  | 
| 
 7  | 
 $ 1,000  | 
 1/ (1+0.08)7  | 
 0.58349039526213  | 
 $ 583.490395  | 
| 
 8  | 
 $ 1,000  | 
 1/ (1+0.08)8  | 
 0.54026888450198  | 
 $ 540.268885  | 
| 
 9  | 
 $ 1,000  | 
 1/ (1+0.08)9  | 
 0.50024896713146  | 
 $ 500.248967  | 
| 
 10  | 
 $ 1,500  | 
 1/ (1+0.08)10  | 
 0.46319348808468  | 
 $ 694.790232  | 
| 
 11  | 
 $ 1,500  | 
 1/ (1+0.08)11  | 
 0.42888285933767  | 
 $ 643.324289  | 
| 
 12  | 
 $ 1,500  | 
 1/ (1+0.08)12  | 
 0.39711375864599  | 
 $ 595.670638  | 
| 
 NPV1  | 
 $ 180.67307  | 
As NPV is negative let’s compute NPV at discount rate of 9 %.
| 
 Year  | 
 Cash Flow (C)  | 
 Computation of PV Factor  | 
 PV Factor @ 9 % (F)  | 
 PV (C x F)  | 
| 
 0  | 
 -$ 8,000  | 
 1/ (1+0.09)0  | 
 1  | 
 -$ 8,000.0000  | 
| 
 1  | 
 $ 1,000  | 
 1/ (1+0.09)1  | 
 0.91743119266055  | 
 $ 917.431193  | 
| 
 2  | 
 $ 1,000  | 
 1/ (1+0.09)2  | 
 0.84167999326656  | 
 $ 841.679993  | 
| 
 3  | 
 $ 1,000  | 
 1/ (1+0.09)3  | 
 0.77218348006106  | 
 $ 772.183480  | 
| 
 4  | 
 $ 1,000  | 
 1/ (1+0.09)4  | 
 0.70842521106520  | 
 $ 708.425211  | 
| 
 5  | 
 $ 1,000  | 
 1/ (1+0.09)5  | 
 0.64993138629835  | 
 $ 649.931386  | 
| 
 6  | 
 $ 1,000  | 
 1/ (1+0.09)6  | 
 0.59626732687922  | 
 $ 596.267327  | 
| 
 7  | 
 $ 1,000  | 
 1/ (1+0.09)7  | 
 0.54703424484332  | 
 $ 547.034245  | 
| 
 8  | 
 $ 1,000  | 
 1/ (1+0.09)8  | 
 0.50186627967277  | 
 $ 501.866280  | 
| 
 9  | 
 $ 1,000  | 
 1/ (1+0.09)9  | 
 0.46042777951630  | 
 $ 460.427780  | 
| 
 10  | 
 $ 1,500  | 
 1/ (1+0.09)10  | 
 0.42241080689569  | 
 $ 633.616210  | 
| 
 11  | 
 $ 1,500  | 
 1/ (1+0.09)11  | 
 0.38753285036302  | 
 $ 581.299276  | 
| 
 12  | 
 $ 1,500  | 
 1/ (1+0.09)12  | 
 0.35553472510369  | 
 $ 533.302088  | 
| 
 NPV2  | 
 -$ 256.535531  | 
IRR = R1 + [NPV1 x (R2 – R1)/ (NPV1 – NPV2)]
= 8 % + [$ 180.67307 x (9 % - 8 %)/ ($ 180.67307– (-$ 256.535531))]
= 8 % + [($ 180.67307 x 1 %)/ ($ 180.67307 + $ 256.535531)]
= 8 % + ($ 1.8067307/ $ 437.208601)
= 8 % + 0.004132423
= 8 % + 0.41 % = 8.41 %
Security should be purchased as the rate of return, 8.41 % is higher than required rate of return.
Option “Yes, because the return is greater than 7 %” is correct answer.