In: Finance
Let’s compute IRR of the security using trial and error method.
Computation of NPV at discount rate of 8 %.
Year |
Cash Flow (C) |
Computation of PV Factor |
PV Factor @ 8 % (F) |
PV (C x F) |
0 |
-$ 8,000 |
1/ (1+0.08)0 |
1 |
-$ 8,000.00 |
1 |
$ 1,000 |
1/ (1+0.08)1 |
0.92592592592593 |
$ 925.925926 |
2 |
$ 1,000 |
1/ (1+0.08)2 |
0.85733882030178 |
$ 857.338820 |
3 |
$ 1,000 |
1/ (1+0.08)3 |
0.79383224102017 |
$ 793.832241 |
4 |
$ 1,000 |
1/ (1+0.08)4 |
0.73502985279645 |
$ 735.029853 |
5 |
$ 1,000 |
1/ (1+0.08)5 |
0.68058319703375 |
$ 680.583197 |
6 |
$ 1,000 |
1/ (1+0.08)6 |
0.63016962688311 |
$ 630.169627 |
7 |
$ 1,000 |
1/ (1+0.08)7 |
0.58349039526213 |
$ 583.490395 |
8 |
$ 1,000 |
1/ (1+0.08)8 |
0.54026888450198 |
$ 540.268885 |
9 |
$ 1,000 |
1/ (1+0.08)9 |
0.50024896713146 |
$ 500.248967 |
10 |
$ 1,500 |
1/ (1+0.08)10 |
0.46319348808468 |
$ 694.790232 |
11 |
$ 1,500 |
1/ (1+0.08)11 |
0.42888285933767 |
$ 643.324289 |
12 |
$ 1,500 |
1/ (1+0.08)12 |
0.39711375864599 |
$ 595.670638 |
NPV1 |
$ 180.67307 |
As NPV is negative let’s compute NPV at discount rate of 9 %.
Year |
Cash Flow (C) |
Computation of PV Factor |
PV Factor @ 9 % (F) |
PV (C x F) |
0 |
-$ 8,000 |
1/ (1+0.09)0 |
1 |
-$ 8,000.0000 |
1 |
$ 1,000 |
1/ (1+0.09)1 |
0.91743119266055 |
$ 917.431193 |
2 |
$ 1,000 |
1/ (1+0.09)2 |
0.84167999326656 |
$ 841.679993 |
3 |
$ 1,000 |
1/ (1+0.09)3 |
0.77218348006106 |
$ 772.183480 |
4 |
$ 1,000 |
1/ (1+0.09)4 |
0.70842521106520 |
$ 708.425211 |
5 |
$ 1,000 |
1/ (1+0.09)5 |
0.64993138629835 |
$ 649.931386 |
6 |
$ 1,000 |
1/ (1+0.09)6 |
0.59626732687922 |
$ 596.267327 |
7 |
$ 1,000 |
1/ (1+0.09)7 |
0.54703424484332 |
$ 547.034245 |
8 |
$ 1,000 |
1/ (1+0.09)8 |
0.50186627967277 |
$ 501.866280 |
9 |
$ 1,000 |
1/ (1+0.09)9 |
0.46042777951630 |
$ 460.427780 |
10 |
$ 1,500 |
1/ (1+0.09)10 |
0.42241080689569 |
$ 633.616210 |
11 |
$ 1,500 |
1/ (1+0.09)11 |
0.38753285036302 |
$ 581.299276 |
12 |
$ 1,500 |
1/ (1+0.09)12 |
0.35553472510369 |
$ 533.302088 |
NPV2 |
-$ 256.535531 |
IRR = R1 + [NPV1 x (R2 – R1)/ (NPV1 – NPV2)]
= 8 % + [$ 180.67307 x (9 % - 8 %)/ ($ 180.67307– (-$ 256.535531))]
= 8 % + [($ 180.67307 x 1 %)/ ($ 180.67307 + $ 256.535531)]
= 8 % + ($ 1.8067307/ $ 437.208601)
= 8 % + 0.004132423
= 8 % + 0.41 % = 8.41 %
Security should be purchased as the rate of return, 8.41 % is higher than required rate of return.
Option “Yes, because the return is greater than 7 %” is correct answer.