Question

In: Operations Management

Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would...

Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin:

Immediate Time
Activity Description Predecessor (weeks)
A Survey building site 11
B Develop initial design 10
C Obtain board approval A, B 16
D Select architect C 10
E Establish budget C 9
F Finalize design D 10
G Obtain financing D, E 11
H Hire contractor F, G 12
  1. Which project network is correct?
    (i) (ii)
    (iii) (iv)


  2. Identify the critical path.

    B-C-D-G-H
  3. Develop the activity schedule for the project. If your answer is zero, enter “0”.

    Earliest Latest Earliest Latest Critical
    Activity Start Start Finish Finish Slack Activity
    A
    B
    C
    D
    E
    F
    G
    H
  4. Does it appear reasonable that construction of the athletic complex could begin one year after the decision to begin the project with the site survey and initial design plans? What is the expected completion time for the project?



    Project Completion Time is  weeks.

Solutions

Expert Solution

a.

Project network

Below is the project network (Options are not shown in the Question)

b.

Critical path is A-C-D-G-H

(detailed approach and calculation is given under point c.)

c.

We will use below approach:

Earliest Start Time (ES) = the earliest time that an activity can begin

Earliest Finish Time (EF) = the earliest time that an activity can be completed

EF = ES + duration of activity        

Latest Start Time (LS) = the latest time that an activity can begin without lengthening the minimum project duration

Latest Finish Time (LF) = the earliest time than an activity can be completed without lengthening the minimum project duration

LF = LS + duration of activity   

Duration of the project = the difference between the maximum value of the "lastest finish time" of projects and the minimum value of the "earliest start time" of projects

Project duration = max(LF) - min(ES)     

Slack = the amount of time that a project can be delayed without increasing the duration of the project

Slack = LF- LS or EF - ES

Critical path is the path with Slack = 0

Activity Description Immediate Predecessor Time (weeks) Early Start (ES) Early Finish (EF) Latest Start (LS) Latest Finish (LF) Slack Critical Activity
A Survey building site 11 0 0+11=11 11-11=0 11 11-11=0 Y
B Develop initial design 10 0 0+10=10 11-10=1 11 11-10=1
C Obtain board approval A, B 16 11 11+16=27 27-16=11 27 11-11=0 Y
D Select architect C 10 27 27+10=37 37-10=27 37 27-27=0 Y
E Establish budget C 9 27 27+9=36 37-9=28 37 28-27=1
F Finalize design D 10 37 37+10=47 48-10=38 48 38-37=1
G Obtain financing D, E 11 37 37+11=48 48-11=37 48 37-37=0 Y
H Hire contractor F, G 12 48 48+12=60 48 60 48-48=0 Y

d.

Project Completion time in weeks = 60 weeks

It does not appear reasonable that construction would begin in one year (~52 weeks) considering total completion time for assessment is much higher at 60 weeks.

Please give thumbs up/ likes if the answer is helpful. Thank you!

  


Related Solutions

List 3 goals in SMART Format for the new campus building project at HMC Sheridan College...
List 3 goals in SMART Format for the new campus building project at HMC Sheridan College List 3 assumptions for the new campus building project at HMC Sheridan List 3 constraints for the new campus building project at HMC Sheridan
ABC Company is considering the possibility of building an additional factory that would produce a new...
ABC Company is considering the possibility of building an additional factory that would produce a new addition to their product line. The company is currently considering two options. The first is a small facility that it could build at a cost of $6 million. If demand for new products is low, the company expects to receive $10 million in discounted revenues (present value of future revenues) with the small facility. On the other hand, if demand is high, it expects...
Expando, Inc., is considering the possibility of building an additional factory that would produce a new...
Expando, Inc., is considering the possibility of building an additional factory that would produce a new addition to their product line. The company is currently considering two options. The first is a small facility that it could build at a cost of $6 million. If demand for new products is low, the company expects to receive $10 million in discounted revenues (present value of future revenues) with the small facility. On the other hand, if demand is high, it expects...
Expando, Inc., is considering the possibility of building an additional factory that would produce a new...
Expando, Inc., is considering the possibility of building an additional factory that would produce a new addition to their product line. The company is currently considering two options. The first is a small facility that it could build at a cost of $6 million. If demand for new products is low, the company expects to receive $10 million in discounted revenues (present value of future revenues) with the small facility. On the other hand, if demand is high, it expects...
1. A survey reflects the views of 1,000 undergraduate students on the new building on campus....
1. A survey reflects the views of 1,000 undergraduate students on the new building on campus. The table below shows their points (like, dislike or not care) and which year they are. (write out all the probabilities in formal notion) Like Dislike Not care Total Freshman 100 98 22 220 Sophomore 152 85 23 260 Junior 80 178 12 270 Senior 143 76 31 250 Total 475 437 88 1000 Form the proportions table. Are disliking the building and being...
Gubanich Sportswear is considering building a new factory to produce aluminum baseball bats. This project would...
Gubanich Sportswear is considering building a new factory to produce aluminum baseball bats. This project would require an initial cash outlay of ​$5,000,000 and would generate annual free cash inflows of ​$1,100,000 per year for 6 years. Calculate the​ project's NPV ​given: a. A required rate of return of 9 percent b. A required rate of return of 11 percent c. A required rate of return of 13 percent d. A required rate of return of 18 percent
Emily’s Soccer Mania is considering building a new plant. This project would acquire an initial cash...
Emily’s Soccer Mania is considering building a new plant. This project would acquire an initial cash outlay of $10 million and would generate annual cash inflows of $3million per year for Years 1 through 4.In year 5 the project will acquire an investment outlay of $5,000,000. During Years 6 through 10 the project will provide cash inflows of $5million per year. Calculate the Project’s MIRR given a discount rate of 14 percent I want the answer in details not on...
Artie's Wrestling Stuff is considering building a new plant. This plant would require an initial cash...
Artie's Wrestling Stuff is considering building a new plant. This plant would require an initial cash outlay of ​$ 8 million and would generate annual free cash inflows of ​$ 1 million per year for 8 years. Calculate the​ project's MIRR ​given: a. A required rate of return of 9 percent b. A required rate of return of 12 percent c. A required rate of return of 15 percent
Gubanich Sportswear is considering building a new factory to produce aluminum baseball bats. This project would...
Gubanich Sportswear is considering building a new factory to produce aluminum baseball bats. This project would require an initial cash outlay of ​$5,000,000 and would generate annual free cash inflows of ​$1,100,000 per year for 7 years. Calculate the​ project's NPV ​given needs 7% needs 8% needs 13% needs 10% percentages need to be calculated with problem..
Your local community college is opening a new campus in a different city and has asked...
Your local community college is opening a new campus in a different city and has asked your software firm to create a student roster program. You first have to develop a class that represents the roster of students who are currently studying in this local community college. What components and attributes will need to be included in the Student class? Why?  Please include a Python code sample.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT