Question

In: Accounting

On January 1, Year 1, a contractor agrees to build on the customer’s land a bridge...

On January 1, Year 1, a contractor agrees to build on the customer’s land a bridge that is expected to be completed at the end of Year 3. The bridge is a single performance obligation to be satisfied over time. The contractor determines that the progress toward completion of the bridge is reasonably measurable using the input method based on costs incurred. The contract price is $4,000,000, and initial expected total costs of the project are $2,400,000.

Year 1

Year 2

Year 3

Costs incurred during each year

$   600,000

$1,200,000

$1,100,000

Costs expected in the future

1,800,000

1,200,000


^ this is the question form the professor and I did the answers for year 1-2-3 :

Year 1
By the end of Year 1, 25% [$600,000 ÷ ($600,000 + $1,800,000)] of the total expected costs have been incurred. Using the input method based on costs incurred, the contractor recognizes 25% of the total expected revenue ($4,000,000 contract price × 25% ) = $1,000,000 and cost of goods sold $2,400,000.× 25%) = $600,000. The difference between these amounts is the gross profit for Year 1.

Revenue $1,000,000, Cost of goods sold $600,000 , Gross profit (1,000,000 – 600,000) =$400,000. The gross profit in Year 1 of $400,000 also may be calculated as total expected gross profit from the project of $1,600,000 ($4,000,000 - $2,400,000) times the progress toward completion of the contract of 25%.

Year 2
By the end of Year 2, total costs incurred are $1,800,000 ($600,000+ $1,200,000). Given that $1,200,000 is expected to be incurred in the future, the total expected cost is $3,000,000 ($1,800,000 + $1,200,000). The change in the total cost of the contract must be accounted for prospectively. By the end of Year 2, 60% ($1,800,000 ÷ $3,000,000) of expected costs have been incurred.
Thus, $2,400,000 ($4,000,000 × 60%) of cumulative revenue and $1,800,000 ($ 3,000,000 × 60%) of cumulative cost of goods sold should be recognized for Years 1 and 2.
Because $1,000,000 of revenue and $600,000 of cost of goods sold were recognized in Year 1, revenue of $1,400,000 ($2,400,000 cumulative revenue - $1,000,000) and cost of goods sold of $1,200,000 ($1,800,000 cumulative cost of goods sold - $600,000) are recognized in Year 2.
Revenue
$1,400,000
Cost of goods sold
1,200,000
Gross profit -- Year 2
$200,000*
* The gross profit in Year 2 of $200,000 also may be calculated as the cumulative gross profit for Years 1 and 2 of $600,000 [($4,000,000 - $3,000,000) × 60%] minus the gross profit recognized in Year 1 of $400,000.

Year 3
At the end of Year 3, the project is completed, and the total costs incurred for the contract are $2,900,000 ($600,000 + $1,200,000 + $1,100,000). Given $2,400,000 of cumulative revenue and $1,800,000 of cumulative cost of goods sold for Years 1 and 2, $1,600,000 ($4,000,000 contract price - $2,400,000) of revenue and $1,100,000 ($2,900,000 total costs - $1,800,000) of cost of goods sold are recognized in Year 3.

Revenue
$1,600,000
Cost of goods sold
1,100,000
Gross profit -- Year 3
$500,000
NOTE: (1) The total gross profit from the project of $550,000 ($400,000 + $200,000 + $500,000) equals the contract price of $4,000,000 minus the total costs incurred of $2,900,000. (2) When progress toward completion is measured using the cost-to-cost method, as in the example above, the cost of goods sold recognized for the period equals the costs incurred during that period.

NOW : I need the answer for this question:

An entity may not be able to estimate the degree of completion of a project at the end of the first year, perhaps because this is the first time such a project has been undertaken by the firm. In that case, how much revenue would the firm recognize in that year if significant costs have been incurred in the construction process?

Solutions

Expert Solution

Hello there. I see that you have solved the answer and it is correct. However, I found one issue in it so thought to tell you that. I am not sure in what context you have written this, but just recheck if you want. In the last para of 'NOTE' you have written:

"NOTE: (1) The total gross profit from the project of $550,000 ($400,000 + $200,000 + $500,000) equals the contract price of $4,000,000 minus the total costs incurred of $2,900,000....."

The total gross profit is $1,100,000 for the whole contract.

Now, for the specific query you have, regarding how much revenue to recognise if degree of completion cannot be reliably estimated. This means that the 'outcome of the construction contract cannot be estimated reliably'.

The accounting standard says that if the outcome of the construction contract cannot be reliably estimated, then the revenue should be recognised to the extent of the contract costs incurred, but till the amount it is probable that the costs will be recovered.

In simple words, the contract cost which is incurred till the close of the period should be recognised as the cost. If the outcome of the contract cannot be reliably estimated, or in other words, the degree of completion cannot be calculated, then the revenue should be recognised till the costs incurred, if it is probable that the costs incurred can be recovered.

Example: $100 is cost incurred, then $100 worth of revenue should be recognised, if it is probable that $100 would be recovered from the party which gave the contract.


Related Solutions

On January 1, Year 1, Company ABC hired a general contractor to begin construction of a...
On January 1, Year 1, Company ABC hired a general contractor to begin construction of a new office building. ABC negotiated a $900,000, five-year, 10% loan on January 1, Year 1, to finance construction. Payments made to the general contractor for the building during Year 1 amount to $1,000,000. Payments were made evenly throughout the year. Construction is completed at the end of Year 1, and ABC moves in and begins using the building on January 1, Year 2. The...
1-A contractor decided to build homes that will include the middle 80% of the market. If...
1-A contractor decided to build homes that will include the middle 80% of the market. If the average size of homes built is 1750 square feet, find the maximum and minimum sizes of the homes the contractor should build. Assume that the standard deviation is 96 square feet and the variable is normally distributed. 2-Determine the indicated probability for a binomial experiment with the given number of trials n and the given success probability p. n = 13, p =...
AZRB is a road bridge construction company. The company plan to build a major road bridge...
AZRB is a road bridge construction company. The company plan to build a major road bridge for its new project. Table shows the process sequence and other related data for the major road bridge development. Table :Activities to construct the bridge, estimated time and crashing cost. Activity Predecessor Time Estimates (Days) Cost (RM per day) Crash cost (RM per day) Optimistic Most Likely Pessimistic Maximum crash time (days) a m b A - 65 73 90 100 150 6 B...
On January 8 of year 1 Javier purchased a building, including the land it was on,...
On January 8 of year 1 Javier purchased a building, including the land it was on, to assemble his new equipment. The total cost of the purchase was $1,399,500; $322,000 was allocated to the basis of the land and the remaining $1,077,500 was allocated to the basis of the building. (Use MACRS Table 1, Table 2, Table 3, Table 4 and Table 5.) (Do not round intermediate calculations. Round your answer to the nearest whole dollar amount.) d. Answer the...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project involving the construction of a multi-screen cinema and retail complex. You have had safety concerns in relation to the appointed scaffolding company, over a three weeks period. The issues raising concern include scaffolds being handed over in an unsafe state (missing toe boards, inadequate bracing and ties), scaffold workers operating at height not being tied-off, poor housekeeping and storage of materials on-site. Outline your...
The municipality of a major city in Quebec is planning to build a new bridge to...
The municipality of a major city in Quebec is planning to build a new bridge to decrease the traffic load on the existing bridges connecting both sides of the city across the river. Construction is to start in 2020 and is expected to take four years at a cost of $25 million per year. After construction is completed, the cost of operation and maintenance is expected to be $2.5 million for the first year and to increase by 2.8% per...
Part 1 On January 1, Year 1, Phillips Company made a basket purchase including land, a...
Part 1 On January 1, Year 1, Phillips Company made a basket purchase including land, a building and equipment for $800,000. The appraised values of the assets are $48,000 for the land, $760,000 for the building and $112,000 for equipment. Phillips uses the double-declining-balance method of depreciation for the equipment which is estimated to have a useful life of four years and a salvage value of $10,000. The depreciation expense for Year 1 for the equipment is: (Round your intermediate...
A bridge will cost (in the present) $280 million to build, will be completed by next year, and will start producing the benefits next year, $8 million per year.
8. A bridge will cost (in the present) $280 million to build, will be completed by next year, and will start producing the benefits next year, $8 million per year. It will cost $1 million a year to maintain (starting next year, too). It is expected that the bridge will last for long time. The market interest rate is 5%. Approximate (with the formula for a perpetuity) the present value of the bridge project (including the cost of construction, benefits,...
The UAE government is going to build a bridge between two of its islands in the...
The UAE government is going to build a bridge between two of its islands in the Arabian Gulf Sea to allow the residences of these two islands to communicate with each other’s and with the rest of the country. The government will sign a long time contract with the biggest international company in this field to be responsible for this project. The government will pay an initial cost of 100,000,000 Dhs, a major re-design to fix any bugs in the...
1. The Howell’s decided to build a resort hotel on land owned by Chief Ugundi. For...
1. The Howell’s decided to build a resort hotel on land owned by Chief Ugundi. For each of the following items, indicate whether the cost should be recorded as Land (L), Land Improvements (LI), Resort Hotel (RH), or Equipment (E) by placing the correct answer in the space provided. Answer Fences around the property site cost $50,000 Construction of the resort hotel cost $5,000,000 Demolition of existing huts on the land cost $80,000 Installation of wooden sidewalks between the resort...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT