In: Finance
The Engler Oil Company is deciding whether to drill for oil on a tract of land that the company owns. The company estimates that the project will cost $8 million today. Engler estimates that once drilled, the oil will generate positive cash flows of $4.5 million a year at the end of each of the next 4 years. Although the company is fairly confident about its cash flow forecast, it recognizes that if it waits 2 years, it will have more information about the local geology as well as the price of oil. Engler estimates that if it waits 2 years, the project will cost $11 million, and cash flows will continue for 4 years after the initial investment is made. Moreover, if it waits 2 years, there is a 95% chance that the cash flows will be $4.6 million a year for 4 years, and there is a 5% chance that the cash flows will be $2.6 million a year for 4 years. Assume that all cash flows are discounted at 11%.
Answer: Initial Investment: $8 million
Cash flow: $4.5 million
Life of project: 4 years
Discount rate: 11% (1+0.11)=1.11
Solution a:If the company chooses to drill today, what is the project’s expected net present value?
NPV = R × | 1 − (1 + i)-n | − Initial Investment |
i |
In the above formula,
R is the net cash inflow expected to be received in each
period;
i is the required rate of return per period (i.e. the
hurdle rate, discount rate);
n are the number of periods during which the project is
expected to operate and generate cash inflows.
Net Present Value
= $4.5million × (1 − (1 + 11%)^-4) ÷ 11% − $8million
= $4.5 million × (1 − 1.11^-4) ÷ 0.11 − $8 million
≈ $4.5 million × (1 − 0.6587309741) ÷ 0.11 − $8 million
≈ $4.5 million × 0.3412690259÷ 0.11 − $8 million
≈ $4.5 million × 3.10244569 − $8 million
≈ $13.961005605 million − $8 million
≈ $5.9610 million
Solution b: Would it make sense to wait 2 years before deciding whether to drill?
WAIT TWO YEARS:
Low 5% prob | High 95% prob | |||||
Year | NPV | Year | NPV | |||
0 | 0 | - | 0 | 0 | - | |
1 | 0 | - | 1 | 0 | - | |
2 | ‘-11 million | 2 | ‘-11 million | |||
3 | ‘2.6/(1.11)^1 | 2.3423 | 3 | 4.6/(1.11)^1 | 4.1441 | |
4 | 2.6/(1.11)^2 | 2.1102 | 4 | 4.6/(1.11)^2 | 3.7334 | |
5 | 2.6/(1.11)^3 | 1.9011 | 5 | 4.6/(1.11)^3 | 3.3635 | |
6 | 2.6/(1.11)^4 | 1.7127 | 6 | 4.6/(1.11)^4 | 3.0303 | |
Total | 4.6409 | Total | 14.2713 |
Low CF Scenario: NPV= (-11+4.6409)/(1.11)^2=$-5.1611 million
High CF Scenario: NPV= (-11+14.2713)/(1.11)*2= $ 2.6550 million
Expected NPV= 0.05(-5.1611)+ 0.95(26550)=$25222.7580 million
if the cash flows are only 2.6 million, the NPV of the project is negative and thus would not be undertaken. The value of the option of waiting two years is evaluated as 0.05($0)+0.95(26550)=$25222.5million
Since the NPV of waiting two years is less than going ahead and proceeding with the project today it makes sense to drill today.