Question

In: Accounting

In 2016, Makkah Corporation bought land for as a site for its new factory facility that...

In 2016, Makkah Corporation bought land for as a site for its new factory facility that was planned to be built in 2016. The following information related to the land and the factory building:

  1. Purchase cost of the land                                                        $400,000
  2. Closing cost                                                                                30,000
  3. Assumption of lien on the land                                                 100,000
  4. Cleaning and draining cost for the land                                     60,000
  5. Demolition and removal of an old building on the land             70,000
  6. Sale of salvaged material from the old building                         18,000
  7. Land permanent improvements                                                  60,000
  8. Costs of walkways, fences, and parking lots                             80,000
  9. Building permit fees                                                                  24,000
  10. Architectural design costs                                                           58,000
  11. Excavation costs                                                                         72,000
  12. Construction costs of the new building                                    570,000

Requirements:

  1. What was the cost of the land that should be recognized on Makkah’s balance sheet on Dec 31, 2016?
  2. If the new building was completed in 2016, what was the cost of the building that should be recognized on Makkah’s book at the end of 2016 (ignore any depreciation)?

Solutions

Expert Solution

Since no information regarding the accounting policies followed by Makkah is given. It is assumed Makkah prepares its balance sheet under IFRS

As per IAS 16, The cost of an item of property, plant and equipment shall be recognised as an asset if, and only if:

(a) it is probable that future economic benefits associated with the item will flow to the entity; and

(b) the cost of the item can be measured reliably.

The accounting treatment of land and building is as follows:

a. Cost of land that should be recognized on Makkah's balance sheet on December 31, 2016 is $430,000

Particulars Whether to be considered in the cost of land Reasons

Purchase Cost of Land

Yes Costs incurred to purchase the land.
Closing cost Yes Costs incurred to make it ready for use, such as closing costs including legal, title fees, etc.
Assumption of lien on land No Since this will be for a period of time, the same should be depreciated over the time. (para 58)
Cleaning & draining cost of land No

If the cost of land includes the costs of site dismantlement, removal and restoration, that portion of the land asset is depreciated over the period of benefits obtained by incurring those costs(para 58)

Demolition and removal of an old building on the land No

If the cost of land includes the costs of site dismantlement, removal and restoration, that portion of the land asset is depreciated over the period of benefits obtained by incurring those costs. (para 58)

Sale of salvaged material from the old building No

If the cost of land includes the costs of site dismantlement, removal and restoration, that portion of the land asset is depreciated over the period of benefits obtained by incurring those costs however proceeds from sale of salvaged materials from the old building must be reduced from the cost of land. (para 58)

Land Permanent improvements No Land improvements that have a useful life and add to the functionality of the land should be booked in a separate asset account and depreciated under IFRS. (para 58)
Costs of walkways, fences No Land improvements that have a useful life and add to the functionality of the land should be booked in a separate asset account and depreciated under IFRS. (para 58)

b) The cost of building to be recognized on the balance sheet is $ 724,000.

The cost of the building should be accounted as follows:

Particulars Whether to be considered in the cost of land Reasons
Building permit fees Yes

any costs directly attributable to bringing the asset to the location and condition necessary for it to be capable of operating in the manner intended by management

Architectural Costs Yes

any costs directly attributable to bringing the asset to the location and condition necessary for it to be capable of operating in the manner intended by management

Excavation costs Yes

any costs directly attributable to bringing the asset to the location and condition necessary for it to be capable of operating in the manner intended by management

Construction Costs Yes

Cost is the amount of cash or cash equivalents paid or the fair value of the other consideration given to acquire an asset at the time of its acquisition or construction


Related Solutions

Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a...
Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a factory. Teradene made the following expenditures related to the acquisition of the land, building, and equipment for the factory: (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.): Purchase price of the land $ 1,280,000 Demolition and removal of old building 88,000 Clearing and grading the land...
Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a...
Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a factory. Teradene made the following expenditures related to the acquisition of the land, building, and equipment for the factory: (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.): Purchase price of the land $ 1,230,000 Demolition and removal of old building 83,000 Clearing and grading the land...
Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a...
Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a factory. Teradene made the following expenditures related to the acquisition of the land, building, and equipment for the factory: (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1) (Use appropriate factor(s) from the tables provided.): Purchase price of the land $ 1,320,000 Demolition and removal of old building 92,000 Clearing and grading the land...
Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a...
Teradene Corporation purchased land as a factory site and contracted with Maxtor Construction to construct a factory. Teradene made the following expenditures related to the acquisition of the land, building, and equipment for the factory: (FV of $1, PV of $1, FVA of $1, PVA of $1, FVAD of $1 and PVAD of $1 Purchase price of the land $ 1,390,000 Demolition and removal of old building 99,000 Clearing and grading the land before construction 245,000 Various closing costs in...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $72,000. An old...
On March 1, 2018, Beldon Corporation purchased land as a factory site for $72,000. An old building on the property was demolished, and construction began on a new building that was completed on December 15, 2018. Costs incurred during this period are listed below: Demolition of old building $ 5,000 Architect’s fees (for new building) 11,000 Legal fees for title investigation of land 8,000 Property taxes on land (for period beginning March 1, 2018) 4,200 Construction costs 620,000 Interest on...
On January 1, 2018, Fulton Corporation purchased land as a factory site for $80,000. Fulton paid...
On January 1, 2018, Fulton Corporation purchased land as a factory site for $80,000. Fulton paid $30,000 and signed a noninterest-bearing note requiring the company to pay the remaining $50,000 on January 1, 2021. An interest rate of 5% properly reflects the time value of money for this type of loan agreement. An old building on the property was demolished, and construction began on a new building that was completed on December 31, 2018. Costs incurred during this period are...
Question 2: On September 25, 2020, ATS Corporation purchased land as a factory site for 600,000...
Question 2: On September 25, 2020, ATS Corporation purchased land as a factory site for 600,000 TL. An old building on the property was demolished and removed and the construction of a new building which was completed on November 24, 2020. Costs incurred during this period are listed below: Demolition of old building 60,000TL Architect’s fees 15,000TL Legal fees for title investigation and purchase contract 8,000TL Construction costs 1,000,000TL (Salvaged materials resulting from demolition were sold for 120,000TL.) Required: How...
Sandhill Corp. purchased land with two old buildings on it as a factory site for $454,000....
Sandhill Corp. purchased land with two old buildings on it as a factory site for $454,000. The property tax assessment (that is, assessed value) on this property was $357,000: $255,000 for the land and the rest for the buildings. It took six months to tear down the old buildings and construct the factory. The company paid $62,200 to raze the old buildings and it sold salvaged copper, lumber, and brick for $6,500. Legal fees of $1,860 were paid for title...
Ivanhoe Corp. purchased land with two old buildings on it as a factory site for $454,000....
Ivanhoe Corp. purchased land with two old buildings on it as a factory site for $454,000. The property tax assessment (that is, assessed value) on this property was $356,000: $249,000 for the land and the rest for the buildings. It took six months to tear down the old buildings and construct the factory. The company paid $60,100 to raze the old buildings and sold salvaged copper, lumber, and brick for $6,700. Legal fees of $1,860 were paid for title search...
Mandarin Company bought land for $100,000 that it held for a possible future plant site. Mandarin...
Mandarin Company bought land for $100,000 that it held for a possible future plant site. Mandarin Company bought the property for $20,000 cash payment and by signing a note secured by a mortgage on the land in the amount of $80,000. Property values in the area increased significantly. When the land was worth, $300,000, Mandarin Company took out a new mortgage of $250,000 and paid off the $100,000 existing mortgage loan. Property values in the area then decreased a great...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT