Question

In: Finance

Novell, Inc., has the following mutually exclusive projects.    Year Project A Project B   0 –$25,000...

Novell, Inc., has the following mutually exclusive projects.

  

Year Project A Project B
  0 –$25,000    –$28,000   
  1 14,500    15,500   
  2 11,000    12,000   
  3 3,400    11,000   

  

a-1.

Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.)


      

a-2.

If the company's payback period is two years, which, if either, of these projects should be chosen?

  • Project A

  • Project B

  • Both projects

  • Neither project

  

b-1.

What is the NPV for each project if the appropriate discount rate is 17 percent? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.)


      

b-2.

Which, if either, of these projects should be chosen if the appropriate discount rate is 17 percent?

  • Project A

  • Project B

  • Both projects

  • Neither project

Solutions

Expert Solution

a.1. Payback period of project A is computed as follows:

Year Project A Cash Flows Cumulative Project A Cash Flows
0 - $ 25,000 - $ 25,000
1 $ 14,500 - $ 10,500 ( - $ 25,000 + $ 14,500 )
2 $ 11,000 $ 500 ( - $ 10,500 + $ 11,000 )

Payback period is the period in which the project initial investment is recovered.

So the project A payback period is lying between year 1 and year 2 and is computed as shown below:

1 year + Balance cost to be recovered after year 1 / Year 2 cash flows

1 year + $ 10,500 / $ 11,000

= 1.955 years approximately.

Payback period of project B is computed as follows:

Year Project B Cash Flows Cumulative Project B Cash Flows
0 - $ 28,000 - $ 28,000
1 $ 15,500 - $ 12,500 ( - $ 28,000 + $ 15,500 )
2 $ 12,000 - $ 500 ( - $ 12,500 + $ 12,000 )
3 $ 11,000 $ 10,500 ( - $ 500 + $ 11,000 )

Payback period is the period in which the project initial investment is recovered.

So the project B payback period is lying between year 2 and year 3 and is computed as shown below:

2 years  + Balance cost to be recovered after year 2 / Year 3 cash flows

2 years + $ 500 / $ 11,000

= 2.045 years approximately.

a-2. If the company's payback period is two years, Project A should be chosen, since project A payback period is less than 2 years.

b-1. NPV of project A at discount rate of 17% is computed as follows:

= - $ 25,000 + $ 14,500 / ( 1 + 0.17 )1 + $ 11,000 / ( 1 + 0.17 )2 + $ 3,400 / ( 1 + 0.17 )3

= - $ 2,448.33 Approximately.

NPV of project B at discount rate of 17% is computed as follows:

= - $ 28,000 + $ 15,500 / ( 1 + 0.17 )1 + $ 12,000 / ( 1 + 0.17 )2 + $ 11,000 / ( 1 + 0.17 )3

= $ 882.10 Approximately.

b-2. Since the NPV of project B is positive, hence project B should be accepted.

Feel free to ask in case of any query relating to this question


Related Solutions

Novell, Inc., has the following mutually exclusive projects. Year Project A. Project B __ __ 0...
Novell, Inc., has the following mutually exclusive projects. Year Project A. Project B __ __ 0 22, 000 25,000 1 13,000 14,000 2 9,500 10,500    3 3,100 9,500 a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g. 32.161.) Project A. _____ years Project B ______ years a-2. If the company's payback period is two years, which, if either, of these projects should be chosen? (Choose the...
Novell, Inc., has the following mutually exclusive projects.    Year Project A Project B   0 –$27,000...
Novell, Inc., has the following mutually exclusive projects.    Year Project A Project B   0 –$27,000    –$30,000      1 15,500    16,500      2 12,000    10,500      3 3,600    12,000    a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.) Project A: Years Project B: Years a-2. If the company's payback period is two years, which, if either, of these projects should be...
Novell, Inc., has the following mutually exclusive projects.    Year Project A Project B   0 –$21,000...
Novell, Inc., has the following mutually exclusive projects.    Year Project A Project B   0 –$21,000    –$24,000      1 12,500    13,500      2 9,000    10,000      3 3,000    9,000       a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.) Project A: _____ years Project B: _____ years b-1. What is the NPV for each project if the appropriate discount rate is...
Novell, inc. has the following mutually exclusive projects. year Project A Project B 0 18,000 21,000...
Novell, inc. has the following mutually exclusive projects. year Project A Project B 0 18,000 21,000 1 11,000 12,000 2 7,500 8,500 3 2,700 7,500 a.1 calculate the payback period for each project. Project A Years Project B Years a.2. If the company's payback period is two years, which, if either, of these projects, should be chosen? ( Project A, Project B, Both projects, Neither project) b.1 what is the NPV for each project if the appropriate discount rate is...
Novell, Inc., Has the following mutually exclusive project Year Project A Project B 0 $20,000 $23,000...
Novell, Inc., Has the following mutually exclusive project Year Project A Project B 0 $20,000 $23,000 1 12,000 13,000 2 8,500 9,500 3 2,900 8,500 a.1. Calculate the payback period for each period ( do not round intermediate calculations and round your answers to decimal places) Project A Years Project B    Years a.2 If the company's payback period is two years, which, if either, of these projects, should be chosen? b.1. What is the NPV for each project if...
ri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$...
ri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$ 13,300 –$ 8,700 1 7,500 3,400 2 6,500 2,900 3 2,100 5,300 Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback Period Project A years Project B years Based on the payback period, which project should the company accept? Project A Project B If the appropriate discount rate is 12...
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$...
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$ 13,800 –$ 9,200 1 8,400 3,900 2 7,000 3,400 3 2,100 5,800 Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback Period Project A years Project B years Based on the payback period, which project should the company accept? Project B Project A If the appropriate discount rate is 10...
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$...
Tri Star, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$ 15,000 –$ 10,300 1 9,500 5,000 2 8,100 4,500 3 2,100 6,900 Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) Payback Period Project A ___ years Project B ___ years Based on the payback period, which project should the company accept? Project B or A? Project B Project A If...
Greystone, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$ 13,600...
Greystone, Inc., has the following mutually exclusive projects: Year Project A Project B 0 –$ 13,600 –$ 9,000 1 8,200 3,700 2 6,800 3,200 3 2,100 5,600 a. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) b. Based on the payback period, which project should the company accept? c. If the appropriate discount rate is 15 percent, what is the NPV for each project? (Do not...
Maxwell Software, Inc., has the following mutually exclusive projects.    Year Project A Project B   0...
Maxwell Software, Inc., has the following mutually exclusive projects.    Year Project A Project B   0 –$26,000    –$29,000      1 15,000    16,000      2 11,500    10,000      3 3,500    11,500       a-1. Calculate the payback period for each project. (Do not round intermediate calculations and round your answers to 3 decimal places, e.g., 32.161.)    Payback period   Project A years     Project B years    a-2. Which, if either, of these projects should be chosen? Project...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT