In: Accounting
At the beginning, the accountant for Limited industries estimated that total overhead would be $80,000. Overhead is allocated to jobs on the basis of direct labour cost. Direct labour was budgeted to cost $200,000 this period. During the period, only three jobs were worked on. The following summarizes the direct materials and labour costs for each:
Job 12 |
Job 123 |
Job 124 |
|
---|---|---|---|
Direct materials |
$45,000 |
$70,000 |
$30,000 |
Direct labour |
70,000 |
90,000 |
50,000 |
Job 12 was finished and sold, Job 123 was finished but is waiting to be sold, and Job 1234 is still in process. Actual overhead for the period was $82,000.
A. Calculate the cost of each job completed.
Job 12 - ?
Job 123 - ?
Job 1234 - ?
B. Calculate the cost of goods sold.
C. Calculate the amount of overapplied or underapplied overhead that will be prorated to the ending balances in work in process, finished goods, and cost of goods sold.
first let us know the predetermined overhead rate:
=>total overhead /total budgeted labor cost *100
=>80,000/200,000*100
=>40%.
a.cost of each job completed:
job 12 | job 123 | job 1234 | |
direct materials | 45,000 | 70,000 | 30,000 |
direct labor | 70,000 | 90,000 | 50,000 |
overhead applied (70,000...90,000...50,0000...*0.40) | 28,000 | 36,000 | 20,000 |
total cost | 143,000 | 196,000 | 100,000 |
b.cost of goods sold:
it is the cost of job 12 =>143,000.
c.
total applied overhead =28,000+36,000+20,000=>84,000.
actual overhead =82,000
over applied overhead = 2000.
prorating the ending balances.
balance | weight | overapplied overhead prorated | |
work in process (job 1234) | 100,000 | 0.23 | (2000*0.23)=>460 |
finished goods (job 123) | 196,000 | 0.45 | (2000*0.45)=>900 |
cost of goods sold (job 12) | 143,000 | 0.32 | (2000*0.32)=>640 |
total | 439,000 | 2000 |
the prorated amounts are to be reduced from work in process, finished goods, cost of goods sold amounts.