In: Math
The traffic control system inside Riyadh city is not meeting the
expectations of the city traffic police. The system is to be
updated within a few weeks to incorporate the traffic intensity,
the weather conditions and the VIP movements etc. The entire
project is to be completed within 10 weeks as per the following
schedule:
| 
 Task ID  | 
 Task  | 
 Allocated Time (Weeks)  | 
 Budget (SAR)  | 
| 
 TID-10  | 
 Requirements elicitation  | 
 1  | 
 10,000  | 
| 
 TID-11  | 
 Use-case Development  | 
 1  | 
 10,000  | 
| 
 TID-12  | 
 Process Model Development  | 
 1  | 
 10,000  | 
| 
 TID-13  | 
 Data Model Development  | 
 1  | 
 10,000  | 
| 
 TID-20  | 
 Architecture-Level Design  | 
 1  | 
 10,000  | 
| 
 TID-21  | 
 User-Interface Design  | 
 1  | 
 10,000  | 
| 
 TID-22  | 
 Algorithm Design  | 
 1  | 
 10,000  | 
| 
 TID-23  | 
 Data Storage Design  | 
 1  | 
 10,000  | 
| 
 TID-30  | 
 Programming  | 
 1  | 
 10,000  | 
| 
 TID-31  | 
 Quality Assurance  | 
 1  | 
 10,000  | 
At the end of Week 7 of the project you have completed only first six tasks (i.e. you just finished, TID-21 i.e. Data Model Development) with a total of SAR 67,500 spent to date. The Interior Minister asks you to produce a report on the status of project work with the help of earned value method. In particular you are asked to include answers to the following questions in your report:
Use the earned value management (EVM) in the given scenario
answering each of the abovementioned question separately.
thank you for time and effort