In: Accounting
Assume the following set of facts for questions 5-6.
Puig corp. has developed some standard costs for the year based on a capacity of 180,000 direct labor hours as follows (Puig uses direct labor hours as a base for overhead):
Cost per unit:
direct materials 4 pounds @ $7 = $28
fixed overhead 2 hours @ $4 = 8
During the year, 90,000 units were scheduled for production; however, only 80,000 units were actually produced. The following data relate to the year:
Direct labor efficiency variance $20,000 u.
Actual direct labor hours were 165,000.
The denominator level of volume was 180,000 direct labor hours.
____ 5. The standard wage per hour for direct labor is:
(a) $ 6
(b) $ 5
(c) $ 4
(d) $ 3
(e) none of the above, the correct answer is ________.
___ 6. The production volume variance for the year is:
(a) $60,000 f
(b) $60,000 u
(c) $30,000 u
(d) $30,000 f
(e) none of the above, the correct answer is _________.
| Sol 5) | D.Labor efficiency variance = | (Standard Hours - Actual Hours) x Standard Rate | ||||||
| $ (20,000.00) | = | ($ 160000 - $ 165000) x Standard Rate | ||||||
| $ (20,000.00) | = | $ (5,000.00) | x Standard Rate | |||||
| $ 4.00 | = | Standard Rate | ||||||
Workings:
| Standard Hours Computation: | |||||||
| For 90,000 units, standard D.Labor hours = | 180000 | ||||||
| Therefore, | For 80,000 units, standard D.Labor hours = | (180000/90000) x 80000 | |||||
| = | 160000 | hours | |||||
| 6) | Data for Production Volume Variance | |||||
| a) | Budgeted Hour for Budgeted Unit | 180000 | hrs | |||
| b) | Actual Hour | 165000 | hrs | |||
| c) | Budgeted Hour for Actual unit | (Standard) | 160000 | hrs | ||
| d) | Recovery Rate | (Fixed OH) | $ 4.00 | per hour | ||
| e) | Budgeted Overhead | (a x d) | $ 720,000.00 | |||
| f) | Recovered Overhead | (c x d) | $ 640,000.00 | |||
| Production volume Variance = | Recovered OH - Budgeted OH | ||||
| = | $ 720000 - $ 640000 | ||||
| = | $ 80000 | (F) | |||