A project will produce an operating cash flow of $445,000 a year for four years. The initial cash outlay for equipment will be $1,195,000. The net aftertax salvage value of $61,000 will be received at the end of the project. The project requires 87,000 of net working capital up front that will be fully recovered. What is the net present value of the project if the required rate of return is 12 percent? $146,800.23 $181,219.28 $154,036.37 $172,811.69 $163,677.13
Solution :
The net present value of the project if the required rate of return is 12 percent = $163,677.13
Thus the solution is option 5 = $ 163,677.13
Please find the attached screenshot of the excel sheet containing the detailed calculation for the solution.