In: Finance
Louis is analyzing a project and has determined that the initial cost will be $1,380,000 and the required rate of return needs to be 16 percent. The project has a 60 percent chance of success and a 40 percent chance of failure. If the project fails, it will generate an annual after-tax cash flow of $242,000. If the project succeeds, the annual after-tax cash flow will be $666,000. He has further determined that if the project fails, he will shut it down after the first year and sell the equipment for the after-tax salvage value of $420,000. If however, the project is a success, he can expand it with no additional investment and increase the after-tax cash flow to $697,000 a year for Years 2-5. At the end of Year 5, the project would be terminated and have no salvage value. What is the expected net present value of this project at Time 0?
$171,480.74
$183,667.21
$201,500.99
$227,615.75
$239,518.20
Please provide rating..
NPV if project success | |||||||||
Year | Cash flow | PVIF @ 16% | Present value | ||||||
0 | -1,380,000 | 1.0000 | (1,380,000.00) | ||||||
1 | 666000 | 0.8621 | 574,137.93 | ||||||
2 | 697000 | 0.7432 | 517,984.54 | ||||||
3 | 697000 | 0.6407 | 446,538.40 | ||||||
4 | 697000 | 0.5523 | 384,946.90 | ||||||
5 | 697000 | 0.4761 | 331,850.77 | ||||||
875,458.54 | |||||||||
NPV (Success) = | 875,458.54 | ||||||||
NPV if project fail | |||||||||
Year | Cash flow | Salvage value | Total cash flow | PVIF @ 16% | Present value | ||||
0 | -1,380,000 | -1,380,000 | 1.0000 | (1,380,000.00) | |||||
1 | 242000 | 242,000 | 0.8621 | 208,620.69 | |||||
1 | 420000 | 420,000 | 0.8621 | 362,068.97 | |||||
(809,310.34) | |||||||||
NPV (Failure) = | (809,310.34) | ||||||||
Therefore NPV of the project = Probability of success*NPV of success + probability of failure * NPV of failure | |||||||||
NPV = | =875458.54*.6-809310.34*.4 | ||||||||
201,550.99 | |||||||||
Therefore correct answer = | 201,550.99 |