In: Finance
|
Solve the problems described below, and present your solutions
in the Excel template provided; no memo is required with this
assignment. Also, the excel spreadsheet specifies monthly billable
hour data. Set March, 2013, as month zero. Ignore taxes. The due
date is SATURDAY at 11:55 PM Eastern. No late work is
accepted.
|
|||||
| % or Unit | Start | End | |||
| Price | 3 Year | 2013 | 2014 | 2015 | |
| ($ / Hr) | Total | Sub-Tot | Sub-Tot | Sub-Tot | |
| Data For Both Track Hoes | |||||
| Billable Hours of Operation | 3600 | 1200 | 1200 | 1200 | |
| MARR and Monthly Discount Factors | |||||
| Annual effective rate | 12.5% | ||||
| Monthly effective rate | |||||
| Monthly discount factors | |||||
| Track Hoe #1 | |||||
| Capital Values | |||||
| Track Hoe Investment | $100,000 | ||||
| Track Hoe Salvage | $35,000 | ||||
| Revenues | |||||
| Track Hoe Operation | $95.00 | ||||
| Costs | |||||
| Track Hoe Operation | $31.00 | ||||
| Operator | $29.00 | ||||
| Total Costs | |||||
| NCF | |||||
| Cumulative Cash | |||||
| Present Values | |||||
| PVs of Monthly NCFs | |||||
| Project Net -- NPV | |||||
| IRR | |||||
| Track Hoe #2 | |||||
| Capital Values | |||||
| Track Hoe Investment | $65,000 | ||||
| Track Hoe Salvage | $0 | ||||
| Revenues | |||||
| Track Hoe Operation | $95.00 | ||||
| Costs | |||||
| Track Hoe Operation | $36.00 | ||||
| Operator | $29.00 | ||||
| Total Costs | |||||
| NCF | |||||
| Cumulative Cash | |||||
| Present Values | |||||
| PVs of Monthly NCFs | |||||
| Project Net -- NPV | |||||
| IRR | |||||
| Requested Valuation Methods | |||||
| 1. Net Present Value | |||||
| TH1 | TH2 | ||||
| 2. Future Value | |||||
| TH1 | TH2 | ||||
| 3. Monthly Rate of Return or Internal Rate of Return (IRR) | |||||
| TH1 | TH2 | ||||
| 4. Payback without interest (number of months) | |||||
| TH1 | TH2 | ||||
| 5. Payback with interest (number of months) | |||||
| TH1 | TH2 | ||||
| Final recommendation | |||||
| TH1 or TH2? | |||||
| Financial Comparison of Track Hoe #1 with Track Hoe #2 | |||||
| % or Unit | Start | End | |||
| Price | 3 Year | 2013 | 2014 | 2015 | |
| ($ / Hr) | Total | Sub-Tot | Sub-Tot | Sub-Tot | |
| Data For Both Track Hoes | |||||
| Billable Hours of Operation | 3600 | 1200 | 1200 | 1200 | |
| MARR and Monthly Discount Factors | |||||
| Annual effective rate | 12.50% | ||||
| Monthly effective rate | 1.04% | ||||
| Monthly discount factors | 0.99 | ||||
| Track Hoe #1 | |||||
| Capital Values | |||||
| Track Hoe Investment | $100,000 | $100,000 | |||
| Track Hoe Salvage | $35,000 | $35,000 | |||
| Revenues | |||||
| Track Hoe Operation | $95.00 | $342,000.00 | $114,000.00 | $114,000.00 | $114,000.00 |
| Costs | |||||
| Track Hoe Operation | $31.00 | $111,600.00 | $37,200.00 | $37,200.00 | $37,200.00 |
| Operator | $29.00 | $104,400.00 | $34,800.00 | $34,800.00 | $34,800.00 |
| Total Costs | $60.00 | $216,000.00 | $72,000.00 | $72,000.00 | $72,000.00 |
| NCF | $35.00 | $126,000.00 | $42,000.00 | $42,000.00 | $42,000.00 |
| Cumulative Cash | |||||
| Present Values | |||||
| PVs of Monthly NCFs | $34.64 | $100,016.46 | $37,333.33 | $33,185.19 | $29,497.94 |
| Project Net -- NPV | $24,598.08 | ||||
| IRR | |||||
| PV | $1,571.78 | ||||
| PV | $0.000000 | ||||
| PV | ($96.00) | ||||
| IRR | 24.942% | ||||
| Track Hoe #2 | |||||
| Capital Values | |||||
| Track Hoe Investment | $65,000 | ||||
| Track Hoe Salvage | $0 | ||||
| Revenues | |||||
| Track Hoe Operation | $95.00 | $342,000.00 | $114,000.00 | $114,000.00 | $114,000.00 |
| Costs | |||||
| Track Hoe Operation | $36.00 | $129,600.00 | $43,200.00 | $43,200.00 | $43,200.00 |
| Operator | $29.00 | $104,400.00 | $34,800.00 | $34,800.00 | $34,800.00 |
| Total Costs | $65.00 | $234,000.00 | $78,000.00 | $78,000.00 | $78,000.00 |
| NCF | $30.00 | $108,000.00 | $36,000.00 | $36,000.00 | $36,000.00 |
| Cumulative Cash | |||||
| Present Values | |||||
| PVs of Monthly NCFs | $29.69 | $85,728.40 | $32,000.00 | $28,444.44 | $25,283.95 |
| Project Net -- NPV | $20,728.40 | ||||
| IRR | |||||
| PV | $380.06 | ||||
| PV | ($0.0000) | ||||
| PV | ($527.70) | ||||
| IRR | 30.416% | ||||
| Requested Valuation Methods | |||||
| 1. Net Present Value | |||||
| TH1 | TH2 | ||||
| $24,598.08 | $20,728.40 | ||||
| 2. Future Value | |||||
| TH1 | TH2 | ||||
| 3. Monthly Rate of Return or Internal Rate of Return (IRR) | |||||
| TH1 | TH2 | ||||
| 24.94% | 30.42% | ||||
| 4. Payback without interest (number of months) | |||||
| TH1 | TH2 | ||||
| 5. Payback with interest (number of months) | |||||
| TH1 | TH2 | ||||
| Final recommendation | |||||
| TH1 or TH2? | TH2 | Because IRR is more | |||