Question

In: Operations Management

Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days...

Below are the data for a Time-Cost CPM Scheduling model analysis. The time is in days and the costs include both direct and indirect costs. If you crash this project to reduce the total time by two days what is the total time of the project and total cost? Explain. (Note: Cut and paste your Precedence diagram.)

Activity

Immediate

Predecessor

Normal Time

Crash Time

Normal Cost

Crash Cost

A

None

3

2

200

400

B

A

4

3

300

600

C

A

1

---

400

---

D

B and C

3

2

200

250

E

D

2

1

500

600

F

E

2

---

600

---

G

E

3

1

300

450

H

G

1

---

400

---

Solutions

Expert Solution

Based on the given data, we find the crash cost per day as shown below:

The formula for calculating crash cost per day is shown in the table.

Total Normal Cost of the project = $2900

Based on the predecessor relationship, we prepare project network diagram as shown below:

The above network diagram in the form of formulas is shown below for better understanding and reference:

The above project diagram is prepared as per the legend shown in the top-left corner.

EST = Early start time

LST = Late start time

EFT = Early finish time

LFT = Late finish time

SLK = Slack = LST - EST or Slack = LFT - EFT

The EST of an activity = EFT of previous activity

EFT of an activity = EST + Duration - 1

Similarly, LFT & LST are calculated during the backward pass. The activity END is only a dummy activity that is introduced for backward pass calculations only. It will not be considered for any other purpose.

There are multiple paths in the diagram:

A-B-D-E-F

A-B-D-E-G-H

A-C-D-E-F

A-C-D-E-G-H

Out of the above paths, path A-C-D-E-G-H is the longest path and has 0 slack. Hence, this is the critical path.

To reduce project duration, we have to crash activities on the critical path first.

As seen from the above table, we start with crashing activities with minimum crash cost per day to have a minimum cost impact.

Step-1: We crash activity D as it has the lowest crash cost. We crash D by 1 day which is the maximum possible. Additional cost = No. of days crashed * crash cost per day = 1*50 = $50

Step-2: We crash activity G as it has the lowest crash cost. We crash G by 1 day which is required. Additional cost = No. of days crashed * crash cost per day = 1*75 = $75

Revised network diagram is shown below:

We have reduced the project duration from 16 days to 14 days.

Total cost for this crashing = Additional cost for Step-1 + Additional cost for Step-2 = 50 + 75 = $125

Total Project time = 14 days

Total Project cost = Total Normal cost + Additional cost = 2900 + 125 = $3125

_______________________________________________________________________________________

In case of any doubt, please ask through the comment section before Upvote/downvote.


Related Solutions

Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A...
Activity Normal Time (days) Normal Cost ($) Crash Time (days) Crash Cost ($) Immediate Predecessor(s) A 6 1,000 5 1,200 — B 4 800 2 2,000 — C 3 600 2 900 A, B D 2 1,500 1 2,000 B E 6 900 4 1,200 C, D F 2 1,300 1 1,400 E G 4 900 4 900 E H 4 500 2 900 G The Advanced Tech Company has a project to design an integrated information database for a...
Q: List the benefits of CPM scheduling in the construction project from the project engineer’s perspective.
Q: List the benefits of CPM scheduling in the construction project from the project engineer’s perspective.
passage require analysis and breakdown Workforce scheduling is huge in hospitals, especially at this time. An...
passage require analysis and breakdown Workforce scheduling is huge in hospitals, especially at this time. An influx of traveling nurses has sprouted from this pandemic due to the rates that hospitals are willing to pay for contracted employees to come in and help with the relief effort. With this, it is important to know the lengths of the contracts and the amount of capital it is going to take to secure each of the temporary employees. Form there, the needs...
Illustrate and explain your understanding from Time-Cost tradeoff Scheduling?
Illustrate and explain your understanding from Time-Cost tradeoff Scheduling?
Perform an analysis of the data below. A time-series plot. Comment on the underlying pattern in...
Perform an analysis of the data below. A time-series plot. Comment on the underlying pattern in the time series. Using the dummy variable approach, build the forecasting model. Show your final time series table and regression equation. Using your model, forecast sales for January through December of the fourth year. Assume that January sales for the fourth year turn out to be $295,000. What was your forecast error? What can you do to resolve the owner's uncertainty in the forecasting...
48. CPM uses constant time, rather than time-cost trade-off. True False 56. In the weighted moving...
48. CPM uses constant time, rather than time-cost trade-off. True False 56. In the weighted moving average time series only a portion of the demand series is needed. True False 57. Six Sigma is more important to a firm because it requires full-time project leaders; whereas Lean systems only rely on part-time project leaders. True False 58. Cost of capital is a carrying cost that entails obsolescence costs assigned to items with a high risk of becoming obsolete. True False
For Priority Scheduling, What is the arrival time, completion time, burst time, turnaround time, and the...
For Priority Scheduling, What is the arrival time, completion time, burst time, turnaround time, and the waiting time? discuss these terms further as they pertain to the efficiency of the algorithm as well as properties such as starvation. Pros and Cons of Priority Scheduling
What is a loglinear model in categorical data analysis?
What is a loglinear model in categorical data analysis?
What is the waiting time and Turnaround time of each process for each of the scheduling...
What is the waiting time and Turnaround time of each process for each of the scheduling algorithms? [12 Marks] Job Arrival Time Burst(msec) Priority A 0 6 3 (Silver) B 1 2 1 (Diamond) C 3 5 3 (Silver) D 5 3 4 (Bronze) E 7 2 2 (Gold) (a) First-Come-First-Served (FCFS) scheduling [2 Marks] (b) Preemptive PRIORITY scheduling [2 Marks] (c) Highest Response Ratio Next (HRRN) scheduling [2 Marks] (d) Round Robin (RR) (quantum = 4) scheduling [2 Marks]...
What is the waiting time and Turnaround time of each process for each of the scheduling...
What is the waiting time and Turnaround time of each process for each of the scheduling algorithms? [12 Marks] Job Arrival Time Burst(msec) Priority A 0 6 3 (Silver) B 1 2 1 (Diamond) C 3 5 3 (Silver) D 5 3 4 (Bronze) E 7 2 2 (Gold) (a) First-Come-First-Served (FCFS) scheduling [2 Marks] (b) Preemptive PRIORITY scheduling [2 Marks] (c) Highest Response Ratio Next (HRRN) scheduling [2 Marks] (d) Round Robin (RR) (quantum = 4) scheduling [2 Marks]...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT