In: Finance
Reynolds Enterprises is attempting to evaluate the feasibility of investing $85,000, CF0, in a machine having a 5-year life. The firm has estimated the cash inflows associated with the proposal as shown below. The firm has a 12 percent cost of capital.
End of Year (t) | Cash Inflows (CFt) |
1 | $18,000 |
2 | $22,500 |
3 | $27,000 |
4 | $31,500 |
5 | $36,000 |
a. Calculate the payback period for the proposed investment.
b. Calculate the NPV for the proposed investment.
c. Calculate the IRR for the proposed investment.
d. Evaluate the acceptability of the proposed investment using NPV and IRR. What recommendation would you make relative to implementation of the project? Why?
a | ||||||
Project | ||||||
Year | Cash flow stream | Cumulative cash flow | ||||
0 | -85000 | -85000 | ||||
1 | 18000 | -67000 | ||||
2 | 22500 | -44500 | ||||
3 | 27000 | -17500 | ||||
4 | 31500 | 14000 | ||||
5 | 36000 | 50000 | ||||
Payback period is the time by which undiscounted cashflow cover the intial investment outlay | ||||||
this is happening between year 3 and 4 | ||||||
therefore by interpolation payback period = 3 + (0-(-17500))/(14000-(-17500)) | ||||||
3.56 Years | ||||||
b | ||||||
Project | ||||||
Discount rate | 0.12 | |||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
Cash flow stream | -85000 | 18000 | 22500 | 27000 | 31500 | 36000 |
Discounting factor | 1 | 1.12 | 1.2544 | 1.404928 | 1.5735194 | 1.762342 |
Discounted cash flows project | -85000 | 16071.43 | 17936.86 | 19218.07 | 20018.819 | 20427.37 |
NPV = Sum of discounted cash flows | ||||||
NPV Project = | 8672.54 | |||||
Where | ||||||
Discounting factor = | (1 + discount rate)^(Corresponding period in years) | |||||
Discounted Cashflow= | Cash flow stream/discounting factor | |||||
c | ||||||
Project | ||||||
IRR is the rate at which NPV =0 | ||||||
IRR | 0.155838927 | |||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
Cash flow stream | -8500000.00% | 18000 | 22500 | 27000 | 31500 | 36000 |
Discounting factor | 1 | 1.155839 | 1.335964 | 1.544159 | 1.7847988 | 2.06294 |
Discounted cash flows project | -85000 | 15573.1 | 16841.78 | 17485.25 | 17649.048 | 17450.82 |
NPV = Sum of discounted cash flows | ||||||
NPV Project = | 9.83164E-07 | |||||
Where | ||||||
Discounting factor = | (1 + IRR)^(Corresponding period in years) | |||||
Discounted Cashflow= | Cash flow stream/discounting factor | |||||
IRR= | 15.58% | |||||
d
Accept the project as NPV is positive and IRR is more than discount rate