1. As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:
Task |
Duration (minutes) |
Immediate Predecessor |
A |
0.3 |
- |
B |
0.5 |
A |
C |
0.4 |
B |
D |
0.5 |
- |
E |
1.9 |
D |
F |
0.8 |
C |
G |
1.2 |
E, F |
A) The precedence diagram as follows :
A |
D |
B |
|
C |
|
F |
E |
G |
a) Minimum cycle time =0.3 minutes
Maximum cycle time = Sum of all activities = 5.6 minutes
Calculated cycle time = 8 hour of 480minutes/240 units = 2 minutes per item
b) Minimum number of stations needed
= Sum of duration of all tasks /calculated cycle time
= 5.6 /2
= 2.8 ( 3 stations rounded to nearest whole number )
c) Assignment of tasks against workstations will be done in such a way so that sum of tasks allocated to a workstation does not exceed calculated cycle time of 2 minutes
Workstation |
Tasks |
Total time |
Idle time = calculated cycle time of 2 minutes – total time |
1 |
A,B,C,D |
03+0.5 +0.4+0.5 = 1.7 |
0.3 |
2 |
E |
1.9 |
0.1 |
3 |
F,G |
0.8 + 1.2 = 2 |
0 |
Percentage of idle time
= Total idle time in all workstations / ( actual number of workstations x calculated cycle time) x 100
= 0.4 /( 3 x 2) x 100
= ( 0.4/6) x 100
= 6.67%