1. As part of a major plant renovation project, the industrial engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationships are as follows:

Task

Duration (minutes)

Immediate Predecessor

A

0.3

-

B

0.5

A

C

0.4

B

D

0.5

-

E

1.9

D

F

0.8

C

G

1.2

E, F

  1. Draw the precedence diagram.
  2. Determine the minimum cycle time, the maximum cycle time, and the calculated cycle time.
  3. Determine the minimum number of stations needed.
  4. Assign tasks to workstations on the basis of most following tasks. Use longest processing time as a tiebreaker. If ties still exist, assume indifference in choice.
  5. Compute the percentage of idle time for the assignment in part d.

Solutions

Expert Solution

A) The precedence diagram as follows :

                                                     A

                      

                                                          D

                                                     B

                                                      C

                                                         F

                                                             E

                                                                                                             G

a) Minimum cycle time =0.3 minutes

Maximum cycle time = Sum of all activities = 5.6 minutes

Calculated cycle time = 8 hour of 480minutes/240 units = 2 minutes per item

b) Minimum number of stations needed

= Sum of duration of all tasks /calculated cycle time

= 5.6 /2

= 2.8 ( 3 stations rounded to nearest whole number )

c) Assignment of tasks against workstations will be done in such a way so that sum of tasks allocated to a workstation does not exceed calculated cycle time of 2 minutes

Workstation

Tasks

Total time

Idle time = calculated cycle time of 2 minutes – total time

1

A,B,C,D

03+0.5 +0.4+0.5 = 1.7

0.3

2

E

1.9

0.1

3

F,G

0.8 + 1.2 = 2

0

Percentage of idle time

= Total idle time in all workstations / ( actual number of workstations x calculated cycle time) x 100

= 0.4 /( 3 x 2) x 100

= ( 0.4/6) x 100

= 6.67%


Related Solutions

The biomedical engineering department in the hospital has been asked to calibrate the pulmonary function equipment....
The biomedical engineering department in the hospital has been asked to calibrate the pulmonary function equipment. It helps to understand the major tests that will be conducted. Correctly match these pulmonary function tests with their description. Place letter from column B that best fits the description Column A Column B 1.         Total Lung Capacity (TLC) A. The amount of air that the lungs can expel after having been filled completely representing the change in volume from completely emptied lungs to...
As part of a major renovation at the beginning of the year, Atiase Pharmaceuticals, Inc. sold...
As part of a major renovation at the beginning of the year, Atiase Pharmaceuticals, Inc. sold shelving units (recorded as Equipment) that were 10 years old for $920 cash. The shelves originally cost $6,880 and had been depreciated on a straight-line basis over an estimated useful life of 10 years with an estimated residual value of $480. Complete the table below, indicating the account, amount, and direction of the effect on disposal. Assume that depreciation has been recorded to the...
You are the head of the engineering department in a certain company. your department has been...
You are the head of the engineering department in a certain company. your department has been allocated an annual budget of R2.6 million for this year. it is now towards the endof the financial year and your department has overspent by 25%. your senior manager wants you to justify why this is so. YOur task is to present a report showing all the expense of your department for the year and analyse them in a form of a Pareto analysis...
You are the head of the engineering department in a certain company. your department has been...
You are the head of the engineering department in a certain company. your department has been allocated an annual budget of R2.6 million for this year. it is now towards the endof the financial year and your department has overspent by 25%. your senior manager wants you to justify why this is so. YOur task is to present a report showing all the expense of your department for the year and analyse them in a form of a Pareto analysis...
You have been asked to work, as an adviser, on a major infrastructure project. It involves...
You have been asked to work, as an adviser, on a major infrastructure project. It involves a response to the prospect of coastal flooding. The investment suggested is to build a seawall. Critically assess this suggestion. [We are particularly interested in how your advice would be structured, based on whether the situation we are dealing with (the prospect of coastal flooding) represents a “risky”, “uncertain”, or “fundamentally uncertain” situation.]
You have been asked to engage in one final project for the chain of department stores...
You have been asked to engage in one final project for the chain of department stores for which you have been working concerning the sales of a type of shirt that they carry. Specifically, this time you wish to study the nature of the relationship between the average daily number of hours the stores are open and monthly sales for the month you have been studying. You wish to utilize the average daily number of hours the stores are open...
You have been asked to engage in one final project for the chain of department stores...
You have been asked to engage in one final project for the chain of department stores for which you have been working concerning the sales of a type of shirt that they carry. Specifically, this time you wish to study the nature of the relationship between the average daily number of hours the stores are open and monthly sales for the month you have been studying. You wish to utilize the average daily number of hours the stores are open...
You have been asked to engage in one final project for the chain of department stores...
You have been asked to engage in one final project for the chain of department stores for which you have been working concerning the sales of a type of shirt that they carry. Specifically, this time you wish to study the nature of the relationship between the average daily number of hours the stores are open and monthly sales for the month you have been studying. You wish to utilize the average daily number of hours the stores are open...
The head of the accounting department at a major software manufacturer has asked you to put...
The head of the accounting department at a major software manufacturer has asked you to put together a pro forma statement of the company's value under several possible growth scenarios and the assumption that the company’s many divisions will remain a single entity forever. The manager is concerned that, despite the fact that the firm’s competitors are comparatively small, collectively their annual revenue growth has exceeded 50 percent over each of the last five years. She has requested that the...
The head of the accounting department at a major software manufacturer has asked you to put...
The head of the accounting department at a major software manufacturer has asked you to put together a pro forma statement of the company's value under several possible growth scenarios and the assumption that the company’s many divisions will remain a single entity forever. The manager is concerned that, despite the fact that the firm’s competitors are comparatively small, collectively their annual revenue growth has exceeded 50 percent over each of the last five years. She has requested that the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT