In: Finance
Robbins Inc. is considering a project that has the following
cash flow and cost of capital (r) data. What is the project's NPV?
Note that if a project's expected NPV is negative, it should be
rejected.
r. | 10.25% | |||||
Year |
0 |
1 |
2 |
3 |
4 |
5 |
Cash flows |
−$1,000 |
$300 |
$300 |
$300 |
$300 |
$300 |
|
|||
|
|||
|
|||
|
|||
|
Reed Enterprises is considering a project that has the following
cash flow and cost of capital (r) data. What is the project's NPV?
Note that a project's expected NPV can be negative, in which case
it will be rejected.
r. | 10.00% | |||
Year |
0 |
1 |
2 |
3 |
Cash flows |
−$1,050 |
$450 |
$460 |
$470 |
|
|||
|
|||
|
|||
|
|||
|
Spence Company is considering a project that has the following
cash flow data. What is the project's IRR? Note that a project's
IRR can be less than the cost of capital or negative, in both cases
it will be rejected.
Year |
0 |
1 |
2 |
3 |
4 |
Cash flows |
−$1,050 |
$400 |
$400 |
$400 |
$400 |
|
|||
|
|||
|
|||
|
|||
|
Calculating NPV for Project of Robbins Inc
Discount rate = Cost of capital = r = 10.25%
We have the following cash flows
Cash Flow | ||||||
Year | 0 | 1 | 2 | 3 | 4 | 5 |
Cash Flow | -1000 | 300 | 300 | 300 | 300 | 300 |
We know that, present value of a cash flow = Cash flow / (1+discount rate)n where n = year of cash flow
NPV of the project = Cash flow in year 0 + Sum of present value of cash flows for year 1 to year 5 discounted at 10.25%
NPV of the project = -1000 + 300 / (1+10.25%)1 + 300 / (1+10.25%)2 + 300 / (1+10.25%)3 + 300 / (1+10.25%)4 + 300/(1+10.25%)5 = -1000 + 272.1088 + 246.8107 + 223.8646 + 203.0518 + 184.1739 = 130.0098 = 130.01 (rounded to two decimal places)
Since NPV is positive, hence project should be accepted
Answer. e. $130.01
Calculating NPV of Project of Reed Enterprises
Discount rate = Cost of capital = r = 10%
We have following cash flows
Year | 0 | 1 | 2 | 3 |
Cash Flow | -1050 | 450 | 460 | 470 |
We know that, present value of a cash flow = Cash flow / (1+discount rate)n where n = year of cash flow
NPV of the project = Cash flow in year 0 + Sum of present values of cash flows for year 1 to year 3 discounted at 10%
NPV of the project = -1050 + 450 / (1+10%)1 + 460 / (1+10%)2 + 470 / (1+10%)3
NPV of the project = -1050 + 409.0909 + 380.1652 + 353.1179 = 92.3740 = 92.37 (rounded to two decimal places)
Since NPV of the project is positive, hence project should be accepted
Answer. b. $92.37
Calculating IRR for project of Spence Company
We have following cash flows for the project
Year |
0 |
1 |
2 |
3 |
4 |
Cash flows |
−$1,050 |
$400 |
$400 |
$400 |
$400 |
IRR of the project is the rate of return earned by the project such that NPV of the project is zero. At discount rate equal to IRR, sum of present values of cash inflows is equal to sum of present values of cash outflows
0 = -1050 + 400 / (1+IRR)1 + 400 / (1+IRR)2 + 400 / (1+IRR)3 + 400 / (1+IRR)4
We have find the IRR of the project using IRR function in excel
Formula to be used in excel: = IRR(Values)
where values are cash flows of the project
Using IRR fuction in excel, we get IRR of the project = 19.27%
Answer. c.19.27%