Question

In: Finance

Robbins Inc. is considering a project that has the following cash flow and cost of capital...

Robbins Inc. is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that if a project's expected NPV is negative, it should be rejected.

r. 10.25%
Year

0

1

2

3

4

5

Cash flows

−$1,000

$300

$300

$300

$300

$300

a. $105.89
b. $111.47
c. $117.33
d. $123.51
e. $130.01

Reed Enterprises is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that a project's expected NPV can be negative, in which case it will be rejected.

r. 10.00%
Year

0

1

2

3

Cash flows

−$1,050

$450

$460

$470

a. $112.28
b. $92.37
c. $101.84
d. $106.93
e. $96.99

Spence Company is considering a project that has the following cash flow data. What is the project's IRR? Note that a project's IRR can be less than the cost of capital or negative, in both cases it will be rejected.

Year

0

1

2

3

4

Cash flows

−$1,050

$400

$400

$400

$400

a. 21.20%
b. 15.61%
c. 19.27%
d. 17.34%
e. 14.05%

Solutions

Expert Solution

Calculating NPV for Project of Robbins Inc

Discount rate = Cost of capital = r = 10.25%

We have the following cash flows

Cash Flow
Year 0 1 2 3 4 5
Cash Flow -1000 300 300 300 300 300

We know that, present value of a cash flow = Cash flow / (1+discount rate)n where n = year of cash flow

NPV of the project = Cash flow in year 0 + Sum of present value of cash flows for year 1 to year 5 discounted at 10.25%

NPV of the project = -1000 + 300 / (1+10.25%)1 + 300 / (1+10.25%)2 + 300 / (1+10.25%)3 + 300 / (1+10.25%)4 + 300/(1+10.25%)5 = -1000 + 272.1088 + 246.8107 + 223.8646 + 203.0518 + 184.1739 = 130.0098 = 130.01 (rounded to two decimal places)

Since NPV is positive, hence project should be accepted

Answer. e. $130.01

Calculating NPV of Project of Reed Enterprises

Discount rate = Cost of capital = r = 10%

We have following cash flows

Year 0 1 2 3
Cash Flow -1050 450 460 470

We know that, present value of a cash flow = Cash flow / (1+discount rate)n where n = year of cash flow

NPV of the project = Cash flow in year 0 + Sum of present values of cash flows for year 1 to year 3 discounted at 10%

NPV of the project = -1050 + 450 / (1+10%)1 + 460 / (1+10%)2 + 470 / (1+10%)3

NPV of the project = -1050 + 409.0909 + 380.1652 + 353.1179 = 92.3740 = 92.37 (rounded to two decimal places)

Since NPV of the project is positive, hence project should be accepted

Answer. b. $92.37

Calculating IRR for project of Spence Company

We have following cash flows for the project

Year

0

1

2

3

4

Cash flows

−$1,050

$400

$400

$400

$400

IRR of the project is the rate of return earned by the project such that NPV of the project is zero. At discount rate equal to IRR, sum of present values of cash inflows is equal to sum of present values of cash outflows

0 = -1050 + 400 / (1+IRR)1 + 400 / (1+IRR)2 + 400 / (1+IRR)3 + 400 / (1+IRR)4

We have find the IRR of the project using IRR function in excel

Formula to be used in excel: = IRR(Values)

where values are cash flows of the project

Using IRR fuction in excel, we get IRR of the project = 19.27%

Answer. c.19.27%


Related Solutions

Robbins Inc. is considering a project that has the following cash flow and cost of capital...
Robbins Inc. is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that if a project's expected NPV is negative, it should be rejected. r. 10.25% Year 0 1 2 3 4 5 Cash flows −$1,000 $300 $300 $300 $300 $300 a. $117.33 b. $105.89 c. $123.51 d. $130.01 e. $111.47 Reed Enterprises is considering a project that has the following cash flow and cost of capital (r)...
Scott Enterprises is considering a project that has the following cash flow and cost of capital...
Scott Enterprises is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that if a project's expected NPV is negative, it should be rejected. r: 11.00% Year 0 1 2 3 4 Cash flows −$1,000 $350 $350 $350 $350 Reed Enterprises is considering a project that has the following cash flow and cost of capital (r) data. What is the project's NPV? Note that a project's expected NPV...
shannon co. is considering a project that has the following cash flow and cost of capital...
shannon co. is considering a project that has the following cash flow and cost of capital (r) data. What is the project discount paycheck? R+ 12.00% Year 0 1 2 3 CF -$1000 $450 $425 $400 $410 $400
reed enterprises is considering a project that has the following cash flow and cost of capital...
reed enterprises is considering a project that has the following cash flow and cost of capital (r) data. What is the project NPV? note that a projects expected NPV can be negative, in which case it will be rejected. R: 11.00% Year 0 1 2 3 CF -1,065 $500 $475 $450
Craig's Car Wash Inc. is considering a project that has the following cash flow and cost...
Craig's Car Wash Inc. is considering a project that has the following cash flow and cost of capital (r) data. What is the project's discountedpayback? r. 10.00% Year 0 1 2 3 Cash flows −$900 $500 $500 $500 a. 2.09 years b. 1.88 years c. 2.52 years d. 2.78 years e. 2.29 years You have just landed an internship in the CFO's office of Hawkesworth Inc. Your first task is to estimate the Year 1 cash flow for a project...
Redesign Inc. is considering a project that has the following cash flow data. (a) What is...
Redesign Inc. is considering a project that has the following cash flow data. (a) What is the project's payback period? (b) What is the project's discounted payback period? Assume the cost of capital is 12%. Year 0 1 2 3 Cash flows -$500 $200 $200 $200
Susmel Inc. is considering a project that has the following cash flow data. What is the...
Susmel Inc. is considering a project that has the following cash flow data. What is the project's payback? No original investment given Year 0 1 2 3 Cash flows -$500 $150 $200 $300 Group of answer choices 1.90 years 2.63 years 2.50 years 1.93 years
Nichols Inc. is considering a project that has the following cash flow data. What is the...
Nichols Inc. is considering a project that has the following cash flow data. What is the project's IRR? Note that a project's IRR can be less than the cost of capital or negative, in both cases it will be rejected. Year 0 1 2 3 4 5 Cash flows −$1,250 $325 $325 $325 $325 $325 a. 11.47% b. 10.40% c. 9.43% d. 10.92% e. 9.91% Westwood Painting Co. is considering a project that has the following cash flow and cost...
Masulis Inc. is considering a project that has the following cash flow and WACC data.  What is...
Masulis Inc. is considering a project that has the following cash flow and WACC data.  What is the project's discounted payback? WACC:  15.00% Year                            0                1                2                3                4     Cash flows              -$750         $525          $485          $445          $405 Hint: Discounted Payback period: The number of years required to recover a project’s cost. Cumulative cash flow computation takes into account the time value of money by using discounted cash flows. Group of answer choices 1.68 years 1.99 years 1.80 years 2.22 years 2.44 years
XYZ Inc. is considering a new project that has the following cash flow data. What is...
XYZ Inc. is considering a new project that has the following cash flow data. What is the project's IRR? Year 0 1 2 3 4 5 Cash Flows -1043 340 340 340 340 340
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT