Question

In: Finance

Q1 a) Given the following cashflows for Project Omega, what is the payback period in years...

Q1

a)

Given the following cashflows for Project Omega, what is the payback period in years assuming the cashflows occur annually?

Year Cashflows of Project Omega
0 -90,000
1 20,000
2 25,000
3 50,000
4 40,000
5 150,000

b)

Project X and Y. The following are the cash flows of two projects:

Year Project X Project Y
0 -100,000 -50,000
1 50,000 20,000
2 40,000 30,000
3 30,000 30,000
4 20,000
5 10,000

If the discount rate is 18% is the project with the highest profitability index also the one with the highest NPV?

Yes

No

c)

he cashflows for an investment in Factory X are listed below. Using the discounted payback method of capital budgeting, what is the payback period for this investment expressed in years, assuming that the cashflows occur annually and using a discount rate of 20%.  

Year Factory X
0 -       300,000
1            50,000
2            50,000
3          100,000
4          100,000
5          200,000
6          200,000

Solutions

Expert Solution

a. Payback period = 2 + (45000/50000) = 2.9 years

Year Cash flows Cumulative cash flows
1 20000 20000
2 25000 45000
3 50000 95000
4 40000 135000
5 150000 285000

b. Profitability index for Project X= Sum of discounted cash flows / Initial cash flow = 104046.0544/100,000 = 1.04

Profitability index for Project Y= Sum of discounted cash flows / Initial cash flow = 56753.6116/50,000 = 1.13

NPV of project X = 4046.0544

NPV of Project Y = 6753.6116

Year Cash flows PV factor @18% Discounted cash flows
0 -100000 1 -100000
1 50000 0.847457627 42372.881
2 40000 0.71818443 28727.377
3 30000 0.608630873 18258.926
4 20000 0.515788875 10315.778
5 10000 0.437109216 4371.0922
NPV 4046.0544
Year Cash flows PV factor @18% Discounted cash flows
0 -50000 1 -50000
1 20000 0.847457627 16949.153
2 30000 0.71818443 21545.533
3 30000 0.608630873 18258.926
NPV 6753.6116

c. Discounted payback = 5 years + (300,000 - 262860.0823) / 66979.595 = 5.554 years

Year Cash flows PV factor @20% Discounted cash flows
0 -300000 1 -300000
1 50000 0.833333333 41666.667
2 50000 0.694444444 34722.222
3 100000 0.578703704 57870.37
4 100000 0.482253086 48225.309
5 200000 0.401877572 80375.514
6 200000 0.334897977 66979.595
NPV 29839.678

Related Solutions

What is the payback period for a project with the following characteristics, given a minimum attractive...
What is the payback period for a project with the following characteristics, given a minimum attractive rate of return (MARR) of 12%? First Cost $20,000 Annual Benefits $8,000 Annual Maintenance $2,000 in year 1, then increases by $500 per year Salvage value $2,000 Useful Life 10 years
A project has the following cash flow's what is the payback period in years? A 2.48...
A project has the following cash flow's what is the payback period in years? A 2.48 B 2.74 C 2.80 D 3.63 E 3.11 Bingo Bowling is considering a project with an initial cost of $161,400 the project will not produce any cash flows for the first 3 years starting in year 4 the project will produce cash inflows of $94,000 a year for the next 5 years the project is risky so the firm has assigned it a discount...
Given the following cash flows for a capital project, calculate its payback period and discounted payback...
Given the following cash flows for a capital project, calculate its payback period and discounted payback period. The required rate of return is 8 percent. Year 0 1 2 3 4 5 Cash Flows $-37500 $11250 $11250 $15000 $6000 $6000 The discounted payback period is 0.16 year longer than the payback period. 0.80 year longer than the payback period. 1.27 years longer than the payback period. 1.85 years longer than the payback period.
Given the following cash flows for a capital project, calculate its payback period and discounted payback...
Given the following cash flows for a capital project, calculate its payback period and discounted payback period. The required rate of return is 8 percent. Year 0 1 2 3 4 5 Cash Flows $-56900 $13650 $18050 $25200 $10000 $5000 The discounted payback period is
Calculate the Payback Period and Discounted Payback Period for the following project: 1. An initial investment...
Calculate the Payback Period and Discounted Payback Period for the following project: 1. An initial investment of $20,000 with expected after-tax operating cash flows of $125,000 per year for each of the next 3 years. However, in preparation for its termination at the end of year 3, an additional investment of $350,000 must be made at the end of Year 2. Please show all work in excel.
What information does the payback period provide? Payback period essentially provides the number of years it...
What information does the payback period provide? Payback period essentially provides the number of years it would take for a project to recover the initial investment from its operating cash flows. As the model was criticized, the model evolved incorporating time value of money to create the discounted payback method. The models still reflected faulty ranking criteria but they provided important information about liquidity and risk. The   the payback, other things constant, the greater the project’s liquidity. Suppose Praxis Corporation’s...
Given the following cash flows for a proposed capital investment project, calculate the payback period. Year...
Given the following cash flows for a proposed capital investment project, calculate the payback period. Year Cash Flow 0 -$40,000 1 15,000 2 15,000 3 15,000 4 15,000 5 10,000 6 10,000 Question 4 options: 5.50 years 3.33 years 4.33 years 2.67 years
What is the payback period for the investment project that has the following cash flows? Year...
What is the payback period for the investment project that has the following cash flows? Year Cash Flows 0 -65,209 1 24,853 2 27,977 3 23,774 4 25,436
What is the discounted payback period for the investment project that has the following cash flows,...
What is the discounted payback period for the investment project that has the following cash flows, if the discount rate is 14 percent? (Do not round intermediate calculations and round your final answer to 2 decimal places. (e.g., 32.16)) Year Cash Flows 0 -13779 1 4470 2 5005 3 5877 4 6626
Project 1 Payback period = 2 years 9 months NPV = £2,041
 Project 1Payback period = 2 years 9 monthsNPV = £2,041APR = 22.08%Project 2Payback period = 2 years 10 monthsNPV = £3,995APR = 26.19% Based on the above, which project is best to invest in?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT