In: Operations Management
follow the questions based on ABC or D Thank YOU .
1.With respect to the five S's, cleaning plant and equipment to eliminate dirtiness that can hide or obscure problems is called ________. *
seiso- shine
seiton- set in order
seiketsu- standrdize
seiri- sort
2.What is the first step in process mapping? *
developing a map of the process
settling on a standard set of process mapping symbols to be used
reviewing a draft copy of the process map with the employees
observing the work being performed by shadowing the workers performing the work
3.What is the most important and most difficult step of the ISO process? *
contracting with the client
certification audit
selecting a registrar
phase 1 audit
4.______can be tabular, computer-based, or schematic. *
Pareto charts
Check sheets
Histograms
Control charts
5.The ________ is used to examine the relationships between variables. *
scatter diagram
process map
Pareto chart
cause-and-effect diagram
6.Which of the following Baldrige criteria examines key aspects such as customer focus in design, work system, design for services and products, support processes, and processes relating to partners? *
measurement, analysis, and knowledge management
operations focus
strategic planning
workforce focus
7.Which of the following Baldrige criteria is used to evaluate the extent to which top management is personally involved in creating and reinforcing goals, values, directions, and customer involvement? *
workforce focus
operations focus
leadership
strategic planning
8.With ________ inspection, all work is inspected at each stage of the manufacturing process, and the workers inspect their own work. *
multilevel
in-process
continuous
dynamic
9.A ________ determines the parameters for process improvement. *
process map
cause-and-effect diagram
control chart
check sheet
10.In a scatter plot, the data is plotted on a ______dimensional plane. *
Three
One
Four
Two
11.In process map, the ________represent the progression from one step to the next. *
Circles
Parallelograms
Arcs
Diamonds
12.With reference to the language of process maps, a ________ is used whenever processing takes place. *
diamond
triangle
circle
rectangle
13.In the ________ approach, the scores required to win the state awards are lower than those for the national awards. *
multilevel
full-Baldrige
Baldrige-lite
Baldrige quality
14.In cause and effect diagram, the problem is clearly stated in the _____of the fish. *
Skeleton
Ribs
Bone
Head
15.What is the first step in the registration process for ISO 9000:2015? *
inquiry
phase 1 audit
client contract
certification audit
16.___________ are spreadsheets that are communicated to management on a regular basis. *
Process map
Balanced scorecards
Histograms
Affinity diagrams
17.With respect to the five S's, ________involves color coding and labeling areas. *
seiketsu- standardize
seiso- shine
seiri- sort
seiton- set in order
18.Pareto charts is aided by the __________ rule. *
70/20
80/20
20/40
80/30
19.Which of the following is not a quality management principle underlying ISO 9000:2015? *
involvement of people
dedication
improvement
leadership
20.The ________ is used to move to lower levels of abstraction in solving problems. *
control chart
Pareto chart
histogram
cause-and-effect diagram
21.The model for the Baldrige consists of ________ interrelated categories that compose the organizational system for performance. *
seven
six
four
five
22.In the multilevel approach, the top level includes the ________ approach. *
consensus
strategic
full-Baldrige
Baldrige quality
23.The first view of lean manufacturing is a philosophical view of ________. *
inventory control
waste reduction
strategic planning
product development
24.The Deming Prize is awarded to individuals and groups who have contributed to the field of ________. *
sales management
just-in-time production
lean manufacturing
quality control
25.________ means that all departments are involved in quality. *
Multilevel deployment
Horizontal deployment
Cross-functional deployment
Vertical deployment
1st question
Correct answer is Seiso-shine
Cleaning plant and equipment to eliminate dirtiness that can hide or obscure problems is called seiso
2nd question
Correct answer is settling on a standard set of process mapping symbols to be used
3rd question
Correct answer is selecting a registrar
selecting a registrar is the most important and most difficult step of the ISO process
4th question
Correct answer is Check sheets
Check sheets are data collectings tools that provide data to Histogram and can be tabular, computer-based, or schematic
5th question
Correct answer is Scatter diagram
scatter diagram is used to examine the relationships between variables.
6th question
Correct answer is operations focus
7th question
Correct answer is leadership
leadership is used to evaluate the extent to which top management is personally involved in creating and reinforcing goals, values, directions, and customer involvement
8th question
Correct answer is in-process
With in-process inspection, all work is inspected at each stage of the manufacturing process, and the workers inspect their own work.
9th question
Correct answer is process map
A process map determines the parameters for process improvement.