In: Finance
Part B: New Location
If Rhonda expects profits from the new location in Part B to be $7,250 annually, should she open the new location? First, if the discount rate is 4.5%? Then, if the discount rate is 7.75%?
Please show your work so I can understand how you get to the answers.
Thank you!
Rhonda aims at recovering the initial investment of $ 30000 in 5 years time. This implies that the present value of the annual profits over the 5 years of the project should sum up to equal the initial investment, thereby giving an NPV of zero.
Discount Rate = 4.5 % and let the annual profits be $ P
Therefore, 30000 = P x (1/0.045) x [1-{1/(1.045)^(5)}] = P x 4.3899767
P = 30000 / 4.3899767 = $ 6833.7492 ~ $ 6833.75
New Discount rate = 7.75 % and the new required profit be P'
Therefore, 30000 = P' x (1/0.0775) x [1-{1/(1.0775)^(5)}] = P' x 4.0191572
P' = 30000 / 4.0191572 = $ 7464.25
Now if Expected profit is $ 7250, then Rhonda should take up the project when the discount rate is 4.5 % as the required minimum profit in that case is lower at $ 6833.75 as compared to the expected profit of $ 7250
However, a discount rate of 7.75% requires a minimum profit of $ 7464.25, therby impliying that the expected profit of $ 7250 will not be sufficient to recoup Rhonda's initial investment of $ 30000 in 5 years. Hence, Rhonda should take up the project when the discount rate is 4.5 % but not when it is 7.75 %.