In: Operations Management
Heather Adams, production manager for a Newfoundland exercise equipment manufacturer needs to schedule an order of 50 items of A which are to be shipped in week 8 and 40 items of B which are to be shipped in week 6. In parenthesis are indicated quantity required for each component. The inventory on hand is for week 1 only. Below is the information about the products.
| 
 Item  | 
 Lead Time  | 
 On Hand Inventory  | 
 Components  | 
| 
 A  | 
 1  | 
 10  | 
 D(1); F(2)  | 
| 
 B  | 
 2  | 
 20  | 
 E(1); F(3)  | 
| 
 C  | 
 3  | 
 10  | 
 D(2); E(3)  | 
| 
 D  | 
 1  | 
 15  | 
|
| 
 E  | 
 2  | 
 5  | 
|
| 
 F  | 
 2  | 
 20  | 
Develop a net MRP (Material Requirements Plan) for F. show your work.
Net MRP plan for F
| Item = F; OH = 20, LT = 2 | ||||||||
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 
| Gross requirements | 0 | 0 | 0 | 60 | 0 | 0 | 80 | 0 | 
| Scheduled receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
| Projected on hand inventory | 20 | 20 | 20 | 0 | 0 | 0 | 0 | 0 | 
| Net requirement | 0 | 0 | 0 | 40 | 0 | 0 | 80 | 0 | 
| Planned order receipts | 0 | 0 | 0 | 40 | 0 | 0 | 80 | 0 | 
| Planned order releases | 0 | 40 | 0 | 0 | 80 | 0 | 0 | 0 | 
Net MRP plan for parent Items A and B
| Item = A; OH = 10, LT = 1 | ||||||||
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 
| Gross requirements | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 50 | 
| Scheduled receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 
| Projected on hand inventory | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 0 | 
| Net requirement | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 40 | 
| Planned order receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 40 | 
| Planned order releases | 0 | 0 | 0 | 0 | 0 | 0 | 40 | 0 | 
| Item = B; OH = 20, LT = 2 | ||||||||
| Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 
| Gross requirements | 0 | 0 | 0 | 0 | 0 | 40 | 0 | 0 | 
| Scheduled receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 
| Projected on hand inventory | 20 | 20 | 20 | 20 | 20 | 0 | 0 | 0 | 
| Net requirement | 0 | 0 | 0 | 0 | 0 | 20 | 0 | 0 | 
| Planned order receipts | 0 | 0 | 0 | 0 | 0 | 20 | 0 | 0 | 
| Planned order releases | 0 | 0 | 0 | 20 | 0 | 0 | 0 | 0 |