Question

In: Operations Management

Heather Adams, production manager for a Newfoundland exercise equipment manufacturer needs to schedule an order of...

Heather Adams, production manager for a Newfoundland exercise equipment manufacturer needs to schedule an order of 50 items of A which are to be shipped in week 8 and 40 items of B which are to be shipped in week 6. In parenthesis are indicated quantity required for each component. The inventory on hand is for week 1 only. Below is the information about the products.

Item

Lead Time

On Hand Inventory

Components

A

1

10

D(1); F(2)

B

2

20

E(1); F(3)

C

3

10

D(2); E(3)

D

1

15

E

2

5

F

2

20

Develop a net MRP (Material Requirements Plan) for F. show your work.

Solutions

Expert Solution

Net MRP plan for F

Item = F; OH = 20, LT = 2
Week 1 2 3 4 5 6 7 8
Gross requirements 0 0 0 60 0 0 80 0
Scheduled receipts 0 0 0 0 0 0 0
Projected on hand inventory 20 20 20 0 0 0 0 0
Net requirement 0 0 0 40 0 0 80 0
Planned order receipts 0 0 0 40 0 0 80 0
Planned order releases 0 40 0 0 80 0 0 0

Net MRP plan for parent Items A and B

Item = A; OH = 10, LT = 1
Week 1 2 3 4 5 6 7 8
Gross requirements 0 0 0 0 0 0 0 50
Scheduled receipts 0 0 0 0 0 0 0 0
Projected on hand inventory 10 10 10 10 10 10 10 0
Net requirement 0 0 0 0 0 0 0 40
Planned order receipts 0 0 0 0 0 0 0 40
Planned order releases 0 0 0 0 0 0 40 0
Item = B; OH = 20, LT = 2
Week 1 2 3 4 5 6 7 8
Gross requirements 0 0 0 0 0 40 0 0
Scheduled receipts 0 0 0 0 0 0 0 0
Projected on hand inventory 20 20 20 20 20 0 0 0
Net requirement 0 0 0 0 0 20 0 0
Planned order receipts 0 0 0 0 0 20 0 0
Planned order releases 0 0 0 20 0 0 0 0

Related Solutions

A production manager needs to develop a production schedule to meet the following demand: Period 1...
A production manager needs to develop a production schedule to meet the following demand: Period 1 2 3 4 5 6 Demand 600 600 800 1000 1200 600 Productions costs are as follows: (a) regular time: $3 per unit. (b) over-time: $5 per unit. (c) subcontract: $7 per unit. (d) Inventory carrying cost = $2 per unit per period (e) Back-order costs = $5 per unit per period. Suppose some workers have retired, and the regular production rate can be...
Scott Logan Equipment produces exercise equipment. The following schedule reveals anticipated monthly production of bicycles for...
Scott Logan Equipment produces exercise equipment. The following schedule reveals anticipated monthly production of bicycles for the first three months of the year: January 8,000 February 11,500 March 15,000 Scott budgets for 1.75 direct labor hours per bicycle, at an average cost of $20.00 per hour. Variable factory overhead is applied at the rate of $8.00 per direct labor hour. Fixed overhead is expected to run $80,000 per month, which includes $8,500 per month of noncash expenses related to depreciation....
In order to meet the specifications of a client, a manufacturer of widgets needs to make...
In order to meet the specifications of a client, a manufacturer of widgets needs to make their widgets 1200 mm long. A quality assurance expert randomly selects 159 widgets and calculates the mean length to be 1202 mm. If it is known that the population standard deviation is1.24 mm.... construct the 95% confidence interval about the population mean. does it seem as though the client's specifications have been met? if we constructed a 99% confidence interval, would the range between...
The manufacturer of a type of exercise equipment wants to study the relationship between the number...
The manufacturer of a type of exercise equipment wants to study the relationship between the number of months (Months) since the type of equipment was purchased and the length of time (Hours) the equipment was used last week. The data is below. Person Fred Bob Joe Tina Lisa Jen Karl Hank Leah Anna Months 12 2 6 9 7 2 8 4 10 5 Hours 4 10 8 5 5 8 3 8 2 5 Following the style of the...
David Wong, the product manager of KiKi Company, was reviewing the production schedule for the last...
David Wong, the product manager of KiKi Company, was reviewing the production schedule for the last quarter of 2020. He noted that the company planned to sell 4,000 units during the year and keep a minimum closing inventory level at 100 units on 31 December 2020. As at 30 September 2020, the following data was reported. Units Inventory, 1 January 2020 0 Production 3,000 Sales 2,700 Inventory, 30 September 2020 300 At the beginning of the year, the company rented...
A manager needs to hire short-term employees to meet production demands. The manager would like to...
A manager needs to hire short-term employees to meet production demands. The manager would like to hire one of three possible short-term workers. Ten hours are demanded with 50% probability, 20 hours are demanded with 30% probability, and 30 hours are demanded with 20% probability. The table below represents the alternatives and possible states of nature. States of Nature (Worker hours demanded) Alternatives 10 hr total pay 20 hr total pay 30 hr total pay Worker 1 $1,000 $1,800 $2,400...
A manufacturer of the famous swimwear line needs help planning production for next year.
A manufacturer of the famous swimwear line needs help planning production for next year. Demand for swimwear follows a seasonal pattern, as shown below. Given the following costs and demand forecasts Beginning workforce: 12 workersBeginning inventory: 0Subcontracting capacity: unlimitedOvertime capacity: 2000 units/monthProduction rate per worker: 200 units/monthRegular wage rate : $10 per unitOvertime wage rate: $20 per unitSubcontracting cost: $25 per unitHiring cost: $150 per worker Firing cost: $250 per workerHolding cost: $0.75 per unit/monthBackordering cost: $5 per unit/montha. Level...
Carlos Cavalas, the manager of Echo Products’ Brazilian Division, is trying to set the production schedule...
Carlos Cavalas, the manager of Echo Products’ Brazilian Division, is trying to set the production schedule for the last quarter of the year. The Brazilian Division had planned to sell 68,090 units during the year, but by September 30 only the following activity had been reported: Units Inventory, January 1 0 Production 73,700 Sales 61,900 Inventory, September 30 11,800 The division can rent warehouse space to store up to 29,100 units. The minimum inventory level that the division should carry...
Carlos Cavalas, the manager of Echo Products’ Brazilian Division, is trying to set the production schedule...
Carlos Cavalas, the manager of Echo Products’ Brazilian Division, is trying to set the production schedule for the last quarter of the year. The Brazilian Division had planned to sell 68,420 units during the year, but by September 30 only the following activity had been reported: Units Inventory, January 1 0 Production 73,400 Sales 62,200 Inventory, September 30 11,200 The division can rent warehouse space to store up to 30,200 units. The minimum inventory level that the division should carry...
Carlos Cavalas, the manager of Echo Products’ Brazilian Division, is trying to set the production schedule...
Carlos Cavalas, the manager of Echo Products’ Brazilian Division, is trying to set the production schedule for the last quarter of the year. The Brazilian Division had planned to sell 3,600 units during the year, but by September 30 only the following activity had been reported: Units Inventory, January 1    0 Production 2,400 Sales 2,000 Inventory, September 30 400 The division can rent warehouse space to store up to 1,000 units. The minimum inventory level that the division should carry...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT