In: Operations Management
Heather Adams, production manager for a Newfoundland exercise equipment manufacturer needs to schedule an order of 50 items of A which are to be shipped in week 8 and 40 items of B which are to be shipped in week 6. In parenthesis are indicated quantity required for each component. The inventory on hand is for week 1 only. Below is the information about the products.
Item |
Lead Time |
On Hand Inventory |
Components |
A |
1 |
10 |
D(1); F(2) |
B |
2 |
20 |
E(1); F(3) |
C |
3 |
10 |
D(2); E(3) |
D |
1 |
15 |
|
E |
2 |
5 |
|
F |
2 |
20 |
Develop a net MRP (Material Requirements Plan) for F. show your work.
Net MRP plan for F
Item = F; OH = 20, LT = 2 | ||||||||
Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 0 | 0 | 0 | 60 | 0 | 0 | 80 | 0 |
Scheduled receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 | |
Projected on hand inventory | 20 | 20 | 20 | 0 | 0 | 0 | 0 | 0 |
Net requirement | 0 | 0 | 0 | 40 | 0 | 0 | 80 | 0 |
Planned order receipts | 0 | 0 | 0 | 40 | 0 | 0 | 80 | 0 |
Planned order releases | 0 | 40 | 0 | 0 | 80 | 0 | 0 | 0 |
Net MRP plan for parent Items A and B
Item = A; OH = 10, LT = 1 | ||||||||
Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 50 |
Scheduled receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Projected on hand inventory | 10 | 10 | 10 | 10 | 10 | 10 | 10 | 0 |
Net requirement | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 40 |
Planned order receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 40 |
Planned order releases | 0 | 0 | 0 | 0 | 0 | 0 | 40 | 0 |
Item = B; OH = 20, LT = 2 | ||||||||
Week | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 |
Gross requirements | 0 | 0 | 0 | 0 | 0 | 40 | 0 | 0 |
Scheduled receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Projected on hand inventory | 20 | 20 | 20 | 20 | 20 | 0 | 0 | 0 |
Net requirement | 0 | 0 | 0 | 0 | 0 | 20 | 0 | 0 |
Planned order receipts | 0 | 0 | 0 | 0 | 0 | 20 | 0 | 0 |
Planned order releases | 0 | 0 | 0 | 20 | 0 | 0 | 0 | 0 |