Question

In: Finance

An investment requires an outlay of $20,000 and has an expected cash flow of $23,700 one...

An investment requires an outlay of $20,000 and has an expected cash flow of $23,700 one year later. What is the internal rate of return of the investment?

Solutions

Expert Solution

Let irr be x%
At irr,present value of inflows=present value of outflows.

20,000=23700/1.0x

1.0x=(23700/20,000)

1.0x=1.185

x=1.185-1

=18.5%=irr


Related Solutions

An investment requires an outlay of $20,000 and has an expected cash flow of $23,700 one...
An investment requires an outlay of $20,000 and has an expected cash flow of $23,700 one year later. What is the internal rate of return of the investment?
Project S requires an initial outlay at t = 0 of $20,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $20,000, and its expected cash flows would be $4,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $46,000, and its expected cash flows would be $13,450 per year for 5 years. If both projects have a WACC of 12%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects...
An investment project requires an initial outlay of $100,000, and is expected to generate annual cash...
An investment project requires an initial outlay of $100,000, and is expected to generate annual cash inflows of $28,000 for the next 5 years. The cost of capital is 12 percent. Determine the internal rate of return for the project (to the nearest tenth of one percent). a. 12.0% b. 12.6% c. 3.6% d. 12.4%
2. An investment requires an initial capital outlay of $12,000. The investment is expected to generate...
2. An investment requires an initial capital outlay of $12,000. The investment is expected to generate future cash flows of $1,000 one year hence, $2000 two years hence, $3,000 three years hence, $4,000 four years hence, $5,000 five years hence. Assume a 10% cost of capital. This is the homework question but I think its asking for net present value?
1. A new hog investment requires an initial outlay of $130,000 and is expected to increase...
1. A new hog investment requires an initial outlay of $130,000 and is expected to increase operating receipts by 87,000 but will also increase operating expenses by 23,000. The investment will be depreciated over 15 years and will have a $0 salvage value. The marginal tax rate is 30%. The investment will be analyzed over 7 years and the terminal value of the hog investment after 7 years will be $45,000. The pre-tax discount rate is 13.5%. What is the...
A new hog investment requires an initial outlay of $130,000 and is expected to increase operating...
A new hog investment requires an initial outlay of $130,000 and is expected to increase operating receipts by 87,000 but will also increase operating expenses by 23,000. The investment will be depreciated over 15 years and will have a $0 salvage value. The marginal tax rate is 30%. The investment will be analyzed over 7 years and the terminal value of the hog investment after 7 years will be $45,000. The pre-tax discount rate is 13.5%. What is the NPV...
Project S requires an initial outlay at t = 0 of $16,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $16,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $40,500, and its expected cash flows would be $12,100 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. a. Project L, since the NPVL > NPVS. b. Both Projects...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $18,000, and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $29,000, and its expected cash flows would be $14,900 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Both Projects S and L, since both projects have IRR's...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $11,000, and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $46,500, and its expected cash flows would be $14,500 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Project S, since the NPVS > NPVL. b. Both Projects...
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash...
Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $34,500, and its expected cash flows would be $14,200 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT