Sime Cooperation. is a ship building company. Recently, the company was appointed by the government to build a brand new ship. Table 1.1 shows the process sequence data for the ship development. As an industrial engineer, you need to provide the top management with certain information below:
Activity |
Predecessor |
Time Estimates (Days) |
Cost per day |
Crash cost per day |
||
Optimistic |
Most Likely |
Pessimistic |
||||
a |
m |
b |
||||
A |
- |
50 |
55 |
60 |
50 |
75 |
B |
A |
32 |
34 |
36 |
50 |
75 |
C |
A |
68 |
72 |
76 |
80 |
120 |
D |
B |
30 |
34 |
38 |
40 |
60 |
E |
B, C |
56 |
60 |
64 |
60 |
90 |
F |
E |
68 |
70 |
78 |
70 |
105 |
G |
D, F |
100 |
110 |
120 |
60 |
90 |
a)
b)
The critical time for this project is 258 days, hence the probability that the project can be completed in less than 380 days is 100 % as the expected time for project completion i.e 380 days is more than the critical time i.e 258 days.
c)
The minimum crash cost per day on the critical activity path i.e 1-2-4-6-7 i.e A-C-E-F is of A i.e 75 days. Hence the additional crash cost for the entire project will be: 75*3 = 225