Question

In: Accounting

Gotham Inc. has a total of $50,000 in production overhead costs. The company’s products and related...

Gotham Inc. has a total of $50,000 in production overhead costs. The company’s products and related statistics follow.

Product X

Product Y

Direct Material in Pounds

2,400

1,600

Direct labor hours

320

480

Machine Hours

720

280

Number of setups

54

96

Number of Units Produced

312

140

Additional data: The direct material was purchased for $8,000. One direct labor hour costs $20.

2A)      Assume that Gotham uses direct labor hours to apply the overhead costs to the products. Determine the unit cost for product X?

2B)      Assume that Gotham uses the following activity centers, cost drivers, and costs to apply overhead to products.

Cost Pool

Cost Driver

Overhead Cost

Utilities

# of machine hours

$15,500

Setup

# of setups

$9,500

Material Handling

# of pounds of material

$25,000

Determine the unit cost for product Y?

please show all work and equations

Solutions

Expert Solution


Related Solutions

Nova Company’s total overhead costs at various levels of activity follow: Month Machine-Hours Total Overhead Costs...
Nova Company’s total overhead costs at various levels of activity follow: Month Machine-Hours Total Overhead Costs April 78,000 $ 214,000 May 115,500 286,000 June 96,000 238,000 July 106,000 246,640 Assume that the total overhead costs consist of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 78,000 machine-hour level of activity is as follows: Utilities (V) $ 48,640 Supervisory salaries (F) 22,600 Maintenance (M) 142,760 Total overhead costs $ 214,000 V = variable; F = fixed; M...
Reynolds Manufacturers Inc, has estimated total factory overhead costs of $95,000
Reynolds Manufacturers Inc, has estimated total factory overhead costs of $95,000 and expected direct labor hours of 9,500 for the current fiscal year. If job number 117 incurs 2,300 direct labor hours, Work in Process will be debited and Factory Overhead will be credited for a. $21,850 b.$2,300 c. $95,000 d. $23,000
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost      April 49,000    $209,260        May 39,000    $182,860        June 59,000    $235,660        July 69,000    $262,060   Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000-machine-hour level of activity in May is as follows:   Utilities (variable) $ 58,500     Supervisory salaries (fixed) 65,000   Maintenance (mixed) 59,360   Total overhead cost $ 182,860 The...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost      April 49,000    $191,570        May 39,000    $166,270        June 59,000    $216,870        July 69,000    $242,170   Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000-machine-hour level of activity in May is as follows:   Utilities (variable) $ 54,600     Supervisory salaries (fixed) 53,000   Maintenance (mixed) 58,670   Total overhead cost $ 166,270 The...
Ball Bearings, Inc., faces costs of production as follows: QUANITY TOTAL FIXED COSTS (DOLLARS) TOTAL VARIABLE...
Ball Bearings, Inc., faces costs of production as follows: QUANITY TOTAL FIXED COSTS (DOLLARS) TOTAL VARIABLE COSTS (DOLLARS) 0 180 0 1 180 80 2 180 140 3 180 180 4 180 240 5 180 320 6 180 450 Complete the following table by calculating the company’s total cost, marginal cost, average fixed cost, average variable cost, and average total cost at each level of production. QUANITY TOTAL COST (DOLLARS) MARGINAL COST (DOLLARS) AVERAGE FIXED COST (DOLLARS) AVERAGE VARIABLE COST...
A company manufactures three products, Alpha, Beta, and Gama. Total overhead costs amount to $ 560,000....
A company manufactures three products, Alpha, Beta, and Gama. Total overhead costs amount to $ 560,000. The company allocates these costs to products based on a predetermined overhead rate, calculated by dividing $ 560,000 by the total number of budgeted direct labor hours. This number for the current year is 70,000 hours. • Alfa used 12,000 hours and 16,000 units were produced • Beta used 24,000 hours and 19,200 units were produced • Gama used 34,000 hours and 20,000 units...
Mattawa Manufacturing Inc. has four categories of overhead. The expected overhead costs for each of the...
Mattawa Manufacturing Inc. has four categories of overhead. The expected overhead costs for each of the categories for the next year are as follows: Expected Costs Cost Driver Activity Maintenance $510,000 Machine hours 60,000 Material handling 250,000 Material moves 20,000 Setups 60,000 Setups 3,000 Inspection 21,000 Inspections 12,000 Currently, the company applies overhead using a predetermined overhead rate based upon budgeted direct labour hours of 100,000. The company has been asked to submit a bid on a proposed job. Usually...
When preparing the manufacturing overhead budget, total overhead costs for the period does not equal total...
When preparing the manufacturing overhead budget, total overhead costs for the period does not equal total overhead cash payments for the period because:      a.overhead costs typically only require cash payments for indirect materials. b.overhead costs typically only require cash payments for factory rent. c.overhead costs typically do not require cash payments. d.overhead costs typically include depreciation costs, which does not require a cash payment.
High–Low Method; Predicting Cost Prince Company’s total overhead costs at various levels of activity are presented...
High–Low Method; Predicting Cost Prince Company’s total overhead costs at various levels of activity are presented below:    labour    overhead Month    Hours    Cost September . . . . . . . . . . . . . . . . . . 100,000 $388,000 October . . . . . . . . . . . . . . . . . . . . . 80,000    $340,400 November . . . . . . ....
Predetermined Overhead Rate, Applied Overhead, Unit Cost Ripley, Inc., costs products using a normal costing system....
Predetermined Overhead Rate, Applied Overhead, Unit Cost Ripley, Inc., costs products using a normal costing system. The following data are available for last year: Budgeted:       Overhead      $343,000       Machine hours      88,000       Direct labor hours      9,800 Actual:       Overhead      $342,200       Machine hours      85,800       Direct labor hours       9,580       Prime cost      $1,464,700       Number of units      180,000 Overhead is applied on the basis of direct labor hours. Required: 1. What was the predetermined overhead rate? $fill in the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT