Question

In: Operations Management

Multiple Production Department Factory Overhead Rates The total factory overhead for Urban Styles, Inc. is budgeted...

Multiple Production Department Factory Overhead Rates

The total factory overhead for Urban Styles, Inc. is budgeted for the year at $1,356,250, divided into two departments: Cutting, $1,102,500, and Sewing, $253,750. Urban Styles manufactures two types of men's pants: jeans and khakis. The jeans require three direct labor hours in Cutting and three direct labor hours in Sewing. The khakis require four direct labor hours in Cutting and two direct labor hours in Sewing. Each product is budgeted for 7,000 units of production for the year.

When required, round all per unit answers to the nearest cent.

a. Determine the total number of budgeted direct labor hours for the year in each department.

Cutting direct labor hours
Sewing direct labor hours

b. Determine the departmental factory overhead rates for both departments.

Cutting $ per dlh
Sewing $ per dlh

c. Determine the factory overhead allocated per unit for each product using the department factory overhead allocation rates.

Jeans $ per pair of jeans
Khakis $ per pair of khakis

Solutions

Expert Solution

a) Total number of budgeted direct labor hours= (Direct labour hour required for each product) * (Production per year)

Cutting-

Jeans = (3 hours)* ( 7000 units) = 21000 hours

khakis= (4 hours) * (7000 units) = 28000 hours

Total direct labour hours for cutting = 21000 hours + 28000 hours = 49000 hours

Sewing-

Jeans = 3 hours * 7000 units = 21000 hours

sewing= 2 hours * 7000 units = 14000 hours

Total direct labour hours for sewing = 21000 hours + 14000 hours = 35000 hours

b) Factory overhead rate = Factory overheads / total direct labour hours

Cutting = $1102500 / 49000 hours = $22.5

Sewing = $253750 / 35000 hours = $7.25

.

c) Factory overheads allocated per unit for each product = Direct labour hours * factory overhead rate

Jeans-

Cutting - 3 hours * $22.5 = $ 67.5

Sewing - 3 hours * $7.25 = $ 21.75

Total factory overheads per pair of jeans = $67.5 + $21.75 = $89.25

Khakis-

Cutting - 4 hours * $22.5 = $90

Sewing - 2 hours * $21.75 = $43.5

Total factpry overheads per pair of khadis = $90 + $43.5 = $133.5


Related Solutions

Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $519,000, divided into two departments: Fabrication, $451,500, and Assembly, $67,500. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require four direct labor hours in Fabrication and one direct labor hour in Assembly. The bass boats require three direct labor hours in Fabrication and one direct labor hour in Assembly. Each product is budgeted for 3,000...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $576,000, divided into two departments: Fabrication, $423,000, and Assembly, $153,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require one direct labor hour in Fabrication and two direct labor hours in Assembly. The bass boats require two direct labor hours in Fabrication and one direct labor hour in Assembly. Each product is budgeted for 6,000...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $966,000, divided into two departments: Fabrication, $768,000, and Assembly, $198,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require four direct labor hours in Fabrication and two direct labor hours in Assembly. The bass boats require four direct labor hours in Fabrication and four direct labor hours in Assembly. Each product is budgeted for 4,000...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $1,345,500, divided into two departments: Fabrication, $1,069,250, and Assembly, $276,250. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require four direct labor hours in Fabrication and one direct labor hours in Assembly. The bass boats require three direct labor hours in Fabrication and four direct labor hours in Assembly. Each product is budgeted for 6,500...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $411,750, divided into two departments: Fabrication, $276,750, and Assembly, $135,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require one direct labor hour in Fabrication and three direct labor hours in Assembly. The bass boats require two direct labor hours in Fabrication and one direct labor hour in Assembly. Each product is budgeted for 4,500...
Single Plantwide Factory Overhead Rate The total factory overhead for Bardot Marine Company is budgeted for...
Single Plantwide Factory Overhead Rate The total factory overhead for Bardot Marine Company is budgeted for the year at $1,305,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboat and bass boat each require six direct labor hours for manufacture. Each product is budgeted for 7,500 units of production for the year. When required, round all per unit answers to the nearest cent. a. Determine the total number of budgeted direct labor hours for the year....
Single Plantwide Factory Overhead Rate The total factory overhead for Bardot Marine Company is budgeted for...
Single Plantwide Factory Overhead Rate The total factory overhead for Bardot Marine Company is budgeted for the year at $1,100,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboat and bass boat each require five direct labor hours for manufacture. Each product is budgeted for 8,000 units of production for the year. When required, round all per unit answers to the nearest cent. a. Determine the total number of budgeted direct labor hours for the year....
Single Plantwide Factory Overhead Rate The total factory overhead for Bardot Marine Company is budgeted for...
Single Plantwide Factory Overhead Rate The total factory overhead for Bardot Marine Company is budgeted for the year at $1,710,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboat and bass boat each require four direct labor hours for manufacture. Each product is budgeted for 9,000 units of production for the year. When required, round all per unit answers to the nearest cent. a. Determine the total number of budgeted direct labor hours for the year....
Multiple Production Department Factory Overhead Rate Method Performance Gloves, Inc. produces three sizes of sports gloves:...
Multiple Production Department Factory Overhead Rate Method Performance Gloves, Inc. produces three sizes of sports gloves: small, medium, and large. A glove pattern is first stenciled onto leather in the Pattern Department. The stenciled patterns are then sent to the Cut and Sew Department, where the glove is cut and sewed together. Performance Gloves uses the multiple production department factory overhead rate method of allocating factory overhead costs. Its factory overhead costs were budgeted as follows: Pattern Department overhead $216,000...
Multiple Production Department Factory Overhead Rate Method Performance Gloves, Inc. produces three sizes of sports gloves:...
Multiple Production Department Factory Overhead Rate Method Performance Gloves, Inc. produces three sizes of sports gloves: small, medium, and large. A glove pattern is first stenciled onto leather in the Pattern Department. The stenciled patterns are then sent to the Cut and Sew Department, where the glove is cut and sewed together. Performance Gloves uses the multiple production department factory overhead rate method of allocating factory overhead costs. Its factory overhead costs were budgeted as follows: Pattern Department overhead $104,000...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT