In: Accounting
After reading an
article about activity-based costing in a trade journal for the
furniture industry, Santana Rey wondered if it was time to
critically analyze overhead costs at Business Solutions. In a
recent month, Santana found that setup costs, inspection costs, and
utility costs made up most of its overhead. Additional information
about overhead follows.
| Activity | Cost | Driver | |||
| Setting up machines | $ | 18,040 | 22 | batches | |
| Inspecting components | $ | 5,100 | 5,100 | parts | |
| Providing utilities | $ | 10,200 | 5,100 | machine hours | |
Overhead has been applied to output at a rate of 50% of direct
labor costs. The following data pertain to Job 615.
| Direct materials | $ | 2,700 | |
| Direct labor | $ | 3,100 | |
| Batches | 4 | batches | |
| Number of parts | 570 | parts | |
| Machine hours | 660 | machine hours | |
Required:
1. Classify each of its three overhead activities
as unit level, batch level, product level, or facility level.
|
2. What is the total cost of Job 615 if Business
Solutions applies overhead at 50% of direct labor cost?
|
3. What is the total cost of Job 615 if Business
Solutions uses activity-based costing?
|
| 1.) | ||||||
| Setting Up Machines | Batch Level | |||||
| Inspecting Components | Unit Level | |||||
| Providing Utilities | Facility Level | |||||
| 2.) Cost of Job 615 | ||||||
| Direct Materials | $2,700.00 | |||||
| Direct labour | $3,100.00 | |||||
| Overhead Costs | $1,550.00 | |||||
| (50% of Direct labour Hr.) | ||||||
| Total Cost | $7,350.00 | ANS | ||||
| 3.) | ||||||
| Under Activity Based Costing | ||||||
| Activity | Cost | Driver | Cost per Driver | |||
| Setting Up of Machines | $18,040.00 | 22 | $820.00 | |||
| Inspecting Compnents | $5,100.00 | 5100 | $1.00 | |||
| Providing utilities | $10,200.00 | 5100 | $2.00 | |||
| Cost of Job 615 | ||||||
| Direct Material | $2,700.00 | |||||
| Direct Labour | $3,100.00 | |||||
| Setting Up Machines | ||||||
| Batches * Cost driver Rate | (4 * 840) | $3,360.00 | ||||
| Inspecting Components | ||||||
| Parts * Cost Driver Rate | (1 * 570) | $570.00 | ||||
| Providing Utilities | ||||||
| Machine Hours * Cost Drver Rate | (660 * 2) | $1,320.00 | ||||
| TOTAL COST | $11,050.00 | ANS | ||||
THANK YOU
HOPING FOR A POSITIVE RESPONSE