Question

In: Finance

What is the appropriate cost of capital for the project?

Empress Inc. has issued a bond with a face value of $1,000 and an interest rate of 13% to fund a new project. The bond is secured by the cash flows from the project, which will be $950 with a probability of 60% and $1,200 otherwise. Assume risk neutrality.

What is the appropriate cost of capital for the project?

Solutions

Expert Solution

Expected cash flow of project = 950*60% + 1200*(1-60%)

= 1050

Cost of capital = (1050-1000)/1000 = 5%

Appropriate cost of capital is 5%


Related Solutions

Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent...
Compute the payback statistic for Project A if the appropriate cost of capital is 8 percent and the maximum allowable payback period is four years. (Round your answer to 2 decimal places.) Project A Time: 0 1 2 3 4 5 Cash flow: –$1,600 $590 $660 $640 $420 $220 Should the project be accepted or rejected?
What is the appropriate cost of capital to use for valuing the total capital structure of...
What is the appropriate cost of capital to use for valuing the total capital structure of a business with a complex capital structure?
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent....
Compute the NPV statistic for Project Y if the appropriate cost of capital is 12 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project Y Time: 0 1 2 3 4 Cash flow: –$9,200 $3,590 $4,420 $1,760 $540 NPV: Should the project be accepted or rejected? accepted rejected
Compute the NPV for Project K if the appropriate cost of capital is 7 percent. (Negative...
Compute the NPV for Project K if the appropriate cost of capital is 7 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.) Project K Time: 0 1 2 3 4 5 Cash flow: −$11,600 $5,800 $6,800 $6,800 $5,800 −$14,600 Should the project be accepted or rejected? rejected accepted
Compute the MIRR statistic for Project I if the appropriate cost of capital is 13 percent....
Compute the MIRR statistic for Project I if the appropriate cost of capital is 13 percent. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project I Time: 0 1 2 3 4 Cash flow –$11,500 $5,580 $4,430 $1,770 $2,250 MIRR % Should the project be accepted or rejected?
Compute the NPV for Project M if the appropriate cost of capital is 7 percent. (Negative...
Compute the NPV for Project M if the appropriate cost of capital is 7 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)       Project M   Time: 0 1 2 3 4 5   Cash flow –$2,000 $550 $680 $720 $800 $300         NPV $       Should the project be accepted or rejected? Accepted Rejected
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 6...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 6 percent and the maximum allowable discounted payback period is three years. (Do not round intermediate calculations. Round your final answer to 2 decimal places.) Project C Time: 0 1 2 3 4 5 Cash flow –$2,900 $1,240 $1,050 $1,090 $680 $480 Discounted payback period years Should the project be accepted or rejected? Rejected Accepted
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent....
Compute the NPV statistic for Project U if the appropriate cost of capital is 9 percent. (Negative amount should be indicated by a minus sign. Do not round intermediate calculations and round your final answer to 2 decimal places.)       Project U   Time: 0 1 2 3 4 5   Cash flow –$1,050 $370 $1,530 –$530 $320 –$110
Compute the PI statistic for Project Z if the appropriate cost of capital is 6 percent....
Compute the PI statistic for Project Z if the appropriate cost of capital is 6 percent. (Do not round intermediate calculations and round your final answer to 2 decimal places.)       Project Z   Time: 0 1 2 3 4 5   Cash flow –$3,300 $730 $860 $1,030 $680 $480
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8...
Compute the discounted payback statistic for Project C if the appropriate cost of capital is 8 percent and the maximum allowable discounted payback period is three years. Time: 0 1 2 3 4 5 Cash flow: –$1,000 $480 $480 $520 $300 $100 Calculate discounted payback period in years
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT