Product Costs using Activity Rates Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products...

Product Costs using Activity Rates

Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows:

Activity Activity Rate
Fabrication $23 per machine hour
Assembly $13 per direct labor hour
Setup $58 per setup
Inspecting $24 per inspection
Production scheduling $14 per production order
Purchasing $11 per purchase order

The activity-base usage quantities and units produced for each product were as follows:

Activity Base Elliptical Machines Treadmill
Machine hours 1,665 982
Direct labor hours 392 153
Setups 61 19
Inspections 627 376
Production orders 64 13
Purchase orders 173 106
Units produced 261 175

Use the activity rate and usage information to calculate the total activity cost and activity cost per unit for each product. If required, round the per unit answers to the nearest cent.

Total Activity Cost Activity Cost Per Unit
Elliptical Machines $ $
Treadmill $ $

Solutions

Expert Solution

The correct answer is :

Total Activity Cost Activity Cost Per Unit
Elliptical Machines $ 64,776 $ 248.18
Treadmill $ 36,049 $ 205.99

Notes:

Activity Activity Rate Elliptical Machines Activity Activity * Activity Rate
Fabrication 23 per machine hour 1665 Machine Hours 38,295
Assembly 13 per direct labor hour 392 Direct Labor Hours 5,096
Setup 58 per setup 61 Setups 3,538
Inspecting 24 per inspection 627 Inspections 15,048
Production scheduling 14 per production order 64 Production Order 896
Purchasing 11 per purchase order 173 Purchase Orders 1,903
Total Activity Cost 64,776
Total Units 261
Activity Cost Per Unit (Total Activity Cost / Total Units) 248.18

`

Activity Activity Rate TreadMill Activity Activity * Activity Rate
Fabrication 23 per machine hour 982 Machine Hours 22,586
Assembly 13 per direct labor hour 153 Direct Labor Hours 1,989
Setup 58 per setup 19 Setups 1,102
Inspecting 24 per inspection 376 Inspections 9,024
Production scheduling 14 per production order 13 Production Order 182
Purchasing 11 per purchase order 106 Purchase Orders 1,166
Total Activity Cost 36,049
Total Units 175
Activity Cost Per Unit (Total Activity Cost / Total Units) 205.99

Related Solutions

Product Costs using Activity Rates Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products...
Product Costs using Activity Rates Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $25 per machine hour Assembly $15 per direct labor hour Setup $51 per setup Inspecting $26 per inspection Production scheduling $16 per production order Purchasing $13...
Product Costs using Activity Rates Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products...
Product Costs using Activity Rates Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $21 per machine hour Assembly $9 per direct labor hour Setup $52 per setup Inspecting $20 per inspection Production scheduling $10 per production order Purchasing $7...
A. Product Costs using Activity Rates Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The...
A. Product Costs using Activity Rates Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $22 per machine hour Assembly $8 per direct labor hour Setup $49 per setup Inspecting $29 per inspection Production scheduling $9 per production order Purchasing...
Product Costs using Activity Rates Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are...
Product Costs using Activity Rates Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: ActivityActivity Rate Fabrication$20per machine hour Assembly$10per direct labor hour Setup$50per setup Inspecting$23per inspection Production scheduling$11per production order Purchasing$8per purchase order The activity-base usage quantities and units produced for each product were...
Product Costs using Activity Rates Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are...
Product Costs using Activity Rates Hercules Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $27 per machine hour Assembly $9 per direct labor hour Setup $58 per setup Inspecting $20 per inspection Production scheduling $10 per production order Purchasing $7 per...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $27 per machine hour Assembly $9 per direct labor hour Setup $45 per setup Inspecting $23 per inspection Production scheduling $10 per production order Purchasing $7 per purchase order The activity-base...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $22 per machine hour Assembly $17 per direct labor hour Setup $53 per setup Inspecting $31 per inspection Production scheduling $18 per production order Purchasing $15 per purchase order The activity-base...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $27 per machine hour Assembly $9 per direct labor hour Setup $51 per setup Inspecting $31 per inspection Production scheduling $10 per production order Purchasing $7 per purchase order The activity-base...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $28 per machine hour Assembly $20 per direct labor hour Setup $75 per setup Inspecting $30 per inspection Production scheduling $12 per production order Purchasing $ 8 per purchase order The...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication...
Atlas Enterprises Inc. manufactures elliptical exercise machines and treadmills. The products are produced in its Fabrication and Assembly production departments. In addition to production activities, several other activities are required to produce the two products. These activities and their associated activity rates are as follows: Activity Activity Rate Fabrication $20 per machine hour Assembly $10 per direct labor hour Setup $55 per setup Inspecting $24 per inspection Production scheduling $11 per production order Purchasing $8 per purchase order The activity-base...