Question

In: Operations Management

Discussion: Managing Risks Associated with Compressing the Project Schedule What are the options for the project...

Discussion: Managing Risks Associated with Compressing the Project Schedule

What are the options for the project team when it becomes clear from the network/PERT diagram and critical path that the project is scheduled to take longer than the sponsor and senior stakeholders expect? This is a common situation and it is important for project managers to prepare themselves to address this situation and systematically consider the options.

We will start our schedule compression analysis with the assumption that all the work packages and associated activities currently in the schedule should remain as part of the project scope. Project managers can consider two techniques; fast-tracking and crashing. You began your study of these techniques in Week 3. We continue to focus on them this week, and you will be applying them to your project schedules in Week 5.

How can you decide, which, if either, technique to use? What are the strengths and limitations of each technique? What are the risks associated with each technique?

Solutions

Expert Solution

Fast tracking and crashing are the schedule compression techniques used by the project manager to shorten the duration of the project. These techniques are employed if the project is running behind schedule but the team wants to finish in the pre-stipulated time. These techniques can also be employed if overall project cost needs to be lowered.

  • Fast tracking: In this method, the critical path of the project is considered and the parallel processes in the project are identified. Then the parallel processes are executed parallel rather than sequentially as was in the previous schedule.
    • Reduces the duration of the project
    • Does not require any additional cost for implementation
    • Does increase the overall risk of the project as the sequential processes are implemented in parallel.

           This method does not require any additional resource, just a consideration is needed to rearrange the overall processes in the project. This method must be used if the project duration needs to be shortened without incurring any additional cost.

  • Crashing: This technique of schedule compression is employed when the project manager adds some extra resources to the project to shorten its duration. This technique is usually employed when the fast tracking has not been able to save enough time on the schedule of the project. Resources are added at least extra cost. This method requires the project manager and the team to analyze the project activities based on the lowest incremental cost. The activities are then implemented in increasing order of their incremental costs with addition of resources.
    • Reduces the duration of the project by adding extra resources
    • Increases the overall project cost as additional resources are added
    • There is no change in the overall estimate of project risk

          This method must be employed if fast tracking technique was not effective or the project manager does not want to increase potential risks of the project.


Related Solutions

Explain the risks associated with leveling resources, compressing or crashing projects, and imposed durations or “catch-up”...
Explain the risks associated with leveling resources, compressing or crashing projects, and imposed durations or “catch-up” as the project is being implemented.
DISCUSSION QUESTION: There are several techniques available for managing risk. For each of the following risks,...
DISCUSSION QUESTION: There are several techniques available for managing risk. For each of the following risks, identify an appropriate technique or combination of techniques, that would be appropriate for dealing with risks. a. A family head may die prematurely because of a heart attack. b. An individual’s home may be totally destroyed in a hurricane. c. A new car may be severely damaged in an auto accident d. A negligent motorist may be ordered to pay a substantial liability judgment...
Describe some risks associated with car showroom project? in project management subject
Describe some risks associated with car showroom project? in project management subject
Discussion Topic: Discuss the health benefits and health risks associated with alcohol consumption.
Discussion Topic: Discuss the health benefits and health risks associated with alcohol consumption.
      Employees who are compensated with restricted stock or stock options face financial risks not associated...
      Employees who are compensated with restricted stock or stock options face financial risks not associated with cash compensation. Describe and compare the financial risks of these two types of equity-based compensation.
Capital budgeting decisions are risky. For this discussion question:  Research the risks associated with capital budgeting...
Capital budgeting decisions are risky. For this discussion question:  Research the risks associated with capital budgeting and identify the three that you believe are the most significant risks. Describe these risks and support your assertion with specific reasons. 
what are the main Risks associated with Trading Derivatives ?
what are the main Risks associated with Trading Derivatives ?
What are Articulate organizational risks associated with cybersecurity attacks.
What are Articulate organizational risks associated with cybersecurity attacks.
What are some of the most important risks associated with bonds?
What are some of the most important risks associated with bonds?
(Software Project Management) A project has following risks (R), associated likelihood (L) and impact (I), and...
(Software Project Management) A project has following risks (R), associated likelihood (L) and impact (I), and the risk reduction cost (C) and resulting reduced risk likelihood (L') of some planned risk reduction measures: (R) (L) (I) (C) (L') R1 20% $75,000 $5,000 5% R2 1% $1,000,000 $20,000 0.5% R3 8% $200,000 $8,000 6% a) Calculate the risk reduction leverage for each of the above risks. b) Based on your analysis in a) above, for which risk(s) would it be worth...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT