Question

In: Economics

A large manufacturing company in Jubail is considering an electric power plant project in order to...

A large manufacturing company in Jubail is considering an electric power plant project in order to save on their electric power consumption by generating its own power supply. The company currently uses 552,000 kW of electric energy a year and pays an average of $3.05 per kwh. The construction of the power plant would require an initial cost of $1,600,000 now plus an additional $950,000 investment at the end of the first year. It is expected to be operational for 10 years with an estimated residual value of $160,000 at the end of the 11th year. Since the installation of the project would take about one year, the annual benefit (in terms of savings) as well as the annual costs would occur only starting at the end of the second year. At that time, the annual operation and maintenance cost is estimated at $750,000 and expected to increase by 5% annually until the end of its useful life. As the capacity of the power plant would be more than adequate what the company needed, the excess energy could be supplied to the neighboring establishments from the fifth year up to the end of the productive life of the project, thereby creating an additional income of $105,000 per year.
Suppose MARR=15%, evaluate this project proposal using all relevant and applicable project assessment tools and techniques. Based on the analysis results, write a detailed recommendation report explaining and justifying your decision whether the project proposal should be accepted or rejected.

Solutions

Expert Solution

Here,

Current Cost Per Year = 3.05*552000 = $1683600

Now,

Installation Cost 1600000
Additional Cost After 1 Year 950000
O&M 750000 increasing by 5%
Salvage value after 11 years 160000
Savings per year 1683600
Additional Income 105000 After 5 years
Cash Flow
08-04-2020 Year 0 -1600000
08-04-2021 Year 1 -950000 O&M Cost
08-04-2022 Year 2 933600 75000
08-04-2023 Year 3 896100 787500
08-04-2024 Year 4 856725 826875
08-04-2025 Year 5 920381.3 868218.75
08-04-2026 Year 6 876970.3 911629.6875
08-04-2027 Year 7 831388.8 957211.1719
08-04-2028 Year 8 783528.3 1005071.73
08-04-2029 Year 9 733274.7 1055325.317
08-04-2030 Year 10 680508.4 1108091.583
08-04-2031 Year 11 785103.8 1163496.162
IRR 26.49%

IRR is found by using XIRR function from excel

The cash flow is after taking care of O&M cost

Since IRR is higher than MARR, we should go ahead with the project


Related Solutions

An electric utility is considering a new power plant in northern Arizona. Power from the plant...
An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would cost $269.63 million,...
An electric utility is considering a new power plant in northern Arizona. Power from the plant...
An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would require an initial...
An electric utility is considering a new power plant in northern Arizona. Power from the plant...
An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would require an initial...
An electric utility is considering a new power plant in northern Arizona. Power from the plant...
An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would require an initial...
An electric utility is considering a new power plant in northern Arizona. Power from the plant...
An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would require an initial...
An electric utility is considering a new power plant in northern Arizona. Power from the plant...
An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would require an initial...
An electric utility is considering a new power plant in northern Arizona. Power from the plant...
An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would cost $270.11 million,...
An electric utility is considering a new power plant in northern Arizona. Power from the plant...
An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would cost $239.88 million,...
An electric utility is considering a new power plant in northern Arizona. Power from the plant...
An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would require an initial...
An electric utility is considering a new power plant in northern Arizona. Power from the plant...
An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would require an initial...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT