Question

In: Operations Management

The normal scrap loss for four successive operations is 5%, 3%, 15% and 10% respectively. How...

The normal scrap loss for four successive operations is 5%, 3%, 15% and 10% respectively. How many units should be started through in order to finish with 1,200 pieces? Find:


a) The total machine time needed if the operation times are 3, 6, 4, and 5 minutes, respectively.


b) The total cost if the cost per unit for each successive operation is $2, $5, $3, and $1, respectively.

Solutions

Expert Solution

operations

normal scrap loss

1-loss %

1

5%

95%

2

3%

97%

3

15%

85%

4

10%

90%

required output

         1,200

pieces

Output Required=Input Given *(1-Loss1%)*(1-Loss2%)*(1-Loss3%)*(1-Loss4%)

1200 = input *(1-0.05)*(1-0.03)*(1-0.15)*(1-0.10)

solve for input:

input = 1200/(95%*97%*85%*90%)

input

1702

pieces

(rounding off)

a)

operations

time/unit (min)

time

1

3

5107

2

6

9703

3

4

6275

4

5

6667

total time

27751

min

b)

operations

cost/unit

cost

1

$              2

$    3,404.51

2

$              5

$    8,085.71

3

$              3

$    4,705.88

4

$              1

$    1,333.33

total cost

$ 17,529.43

formulae used:


Related Solutions

1. Consider the following data set: D= (5, 10, 15, 15, 5, 10, 15, 15, 5,...
1. Consider the following data set: D= (5, 10, 15, 15, 5, 10, 15, 15, 5, 10, 15, 15) SD= 4.33 How would you add a number to this set while keeping the SD the same? 2. tossing a coin 50 times A. from the 50 flips compute the proportion of heads from your 50 flips. B. For a 95% confidence level find the z critical value C. compute the 95% confidence interval for p, the margin of error from...
1. Suppose X is normal with ?=10 and ?=5. Find x0 such that P(X?x0)=0.0643 10.8 15...
1. Suppose X is normal with ?=10 and ?=5. Find x0 such that P(X?x0)=0.0643 10.8 15 10.32 17.6 2.4 2. A survey was conducted to measure the number of hours per week adults in the United States spend on home computers. In the survey, the number of hours was normally distributed, with a mean of 7 hours and a standard deviation of 1 hour. A survey participant is randomly selected. Which of the following statements is true? The probability that...
Week 1 2 3 4 5 6 Value 18 14 15 10 17 15 Using the...
Week 1 2 3 4 5 6 Value 18 14 15 10 17 15 Using the naïve method (most recent value) as the forecast for the next week, compute the following measures of forecast accuracy. (a) Mean absolute error If required, round your answer to one decimal place. (b) Mean squared error If required, round your answer to one decimal place. (c) Mean absolute percentage error If required, round your intermediate calculations and final answer to two decimal places. (d)...
15. How is the standard normal distribution used to compute normal probabilities?
15. How is the standard normal distribution used to compute normal probabilities?
Given that the set X = 1, 2, 3, 5, 6, 10, 15, 30) and Poset...
Given that the set X = 1, 2, 3, 5, 6, 10, 15, 30) and Poset (X, ≼). The relation ≼ is defined as follows: (x, y X) x ≼ y ↔ x factor of y Question i). Draw a Hasse diagram of the Poset. ii). Specify maximum, Maximum, Minimum, Minimum (if any) elements iii). Is the relation "≼" a Lattice? Explain !
year X Y 1 10% 15% 2 24% 25% 3 10% 14% 4 -17% -22% 5...
year X Y 1 10% 15% 2 24% 25% 3 10% 14% 4 -17% -22% 5 105 16% calculate the arithmetic average returns variance and standard deviation
Question 3 The Operations Manager of a construction company wants to assign four contractors to four...
Question 3 The Operations Manager of a construction company wants to assign four contractors to four jobs in such a way as to minimize the time taken to complete four buildings of a special kind and size. Based on experience, the times taken (in months) for each contractor to complete each job are given in the table below. . Jobs Contractor 1 2 3 4 1 15 15 16 14 2 20 18 16 19 3 24 26 20 23...
Question 3 The Operations Manager of a construction company wants to assign four contractors to four...
Question 3 The Operations Manager of a construction company wants to assign four contractors to four jobs in such a way as to minimize the time taken to complete four buildings of a special kind and size. Based on experience, the times taken (in months) for each contractor to complete each job are given in the table below. . Jobs Contractor 1 2 3 4 1 15 15 16 14 2 20 18 16 19 3 24 26 20 23...
10? + 50? + 20? + 10? = 100 5? + 15? + 75? − 25?...
10? + 50? + 20? + 10? = 100 5? + 15? + 75? − 25? = 200 25a − 15? − 5? = 300 10? + 20? − 30? + 100? = 400 how to do flowchart using gauss elimination and lu decomposition method
10? + 50? + 20? + 10? = 100 5? + 15? + 75? − 25?...
10? + 50? + 20? + 10? = 100 5? + 15? + 75? − 25? = 200 25a − 15? − 5? = 300 10? + 20? − 30? + 100? = 400 how to write coding in matlab using lu decomposition
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT