In: Operations Management
Why is scheduling overtime a popular choice for getting projects
back on schedule? (You may select more than one answer.
Single click the box with the question mark to produce a check mark
for a correct answer and double click the box with the question
mark to empty the box for a wrong answer.)
Scheduling overtime is a popular choice for getting projects back on schedule because
True- Even if it involves additional costs, you minimize additional coordination and training costs.
New appointment and on the job training is a time-consuming and relatively expensive procedure for any company. So it is better to implement overtime works for those experienced staff who are on current projects.
True- If it involves salaried workers, no direct costs are added to the project.
For those salaried people who come under the exempt employee category, as per labor law, a company need not pay them for overtime. This statement is right.
False- It tends to avoid accidents, inferior performance and turnover.
Inferior performance can still happen with current employees if you attribute them overtime job regularly. Hence, this is a false statement.
False- If it involves hourly workers no direct costs are added to the project.
Hourly workers come under the non-exempt category and are eligible for overtime pay. So this is also a delusive statement as per law.