Question

In: Finance

what is this project’s irr? year 0- 1099.67 yr 1. 450 yr 2. 450 yr 3....

what is this project’s irr?

year 0- 1099.67
yr 1. 450
yr 2. 450
yr 3. 450

Solutions

Expert Solution

Solution:
The Project IRR is    11.00%
Working Notes:
IRR of the project is at NPV of the project becomes Zero, IRR is compare with cost of capital , to analysis of project acceptance. IRR can be computed two method 1st Excel or Financial calculator which will give exact IRR 2nd is manual formula based which will give IRR but not exact.
1st method
Excel method A B
1 Year Cash Flow
2 0                               -1,099.67
3 1                                     450.00
4 2                                     450.00
5 3                                     450.00
IRR 11.00%
=IRR(B2:B5)
IRR as per excel method (used in above cell)
formula =IRR(B2:B5)
IRR = 11.00%
Where B represent the column in which cash flows is entered and 2 and 5 represent the cash flows from rows from 2nd to 5th row in column B
2nd method
The project have equal annual cash flows
Formula will be this
Internal rate of returns (IRR)
= low rate +[ (sum of PVF at low rate - Sum of PVF at IRR)/(sum of PVF at low rate - Sum of PVF at high rate )]x (Difference in rates)
Sum of PVF at IRR = Initial outflows / annual equal inflows
=1099.67/450
=2.443711111
Now we will compare this SUM of PVF at IRR in table of PVA present value ordinary annuity
We can clearly see that in 3rd row of the table as project have 3 years of cash flow 2.44371 under 11% column . Means IRR of the project is 11%.
here We get exact Sum of PVF at IRR in the PVA table in column of 11% in 3rd row as project life is 3 , we do not have to go further for computation of IRR , if Sum of PVF at IRR does not match exactly then we will go with the above formula of IRR.
Hence IRR under manual method is also same 11.00%
Please feel free to ask if anything about above solution in comment section of the question.

Related Solutions

Year Cash flow 0 59000 1 -34000 2 -39000 a. What is the IRR for this...
Year Cash flow 0 59000 1 -34000 2 -39000 a. What is the IRR for this project? b. What is the NPV of this project if the required return is 12 percent? c. What is the NPV of the project if the required return is 0 percent? d. What is the NPV of the project if the required return is 24 percent?
​(1) In​ general, if NPV​ = 0, then what IRR would be equal​ to? ​(2) In​...
​(1) In​ general, if NPV​ = 0, then what IRR would be equal​ to? ​(2) In​ general, if NPV​ > 0, then what PI​ (Profitability Index) would be equal​ to?
3/26 1 mo 0.01 6 mo 0.04 1 yr 0.13 2 yr 0.3 3 yr 0.36...
3/26 1 mo 0.01 6 mo 0.04 1 yr 0.13 2 yr 0.3 3 yr 0.36 5 yr 0.51 3/27 1 mo 0.01 6 mo 0.02 1 yr 0.11 2 yr 0.25 3 yr 0.3 5 yr 0.41 1. It is March 26 and you hold a $1mm (market value) long position in the 1-yr zero-coupon bond. Using modied durations, determine how much of the 5-yr zero-coupon bond you need to short so that your portfolio remains approximately unchanged if...
exampleInput.txt 1 2 3 0 2 3 4 0 1 3 5 0 1 2 6...
exampleInput.txt 1 2 3 0 2 3 4 0 1 3 5 0 1 2 6 1 5 6 8 2 4 6 7 3 4 5 9 10 5 8 9 4 7 9 6 7 8 6 How can I detect when 'cin' starts reading from a new line. The amount of numbers in each row is unknown. I need them in type 'int' to use the data.
Project Wind Power Year 0 Year 1 Year 2 Year 3 Costs $6,000,000 $4,000,000 $0 $0...
Project Wind Power Year 0 Year 1 Year 2 Year 3 Costs $6,000,000 $4,000,000 $0 $0 Benefits $18,000,000 $15,000,000 $12,000,000 $12,000,000 Project Hydroelectric power Year 0 Year 1 Year 2 Year 3 Costs $4,000,000 $2,000,000 $1,000,000 $0 Benefits $10,000,000 $14,000,000 $15,000,000 $16,000,000 If the interest rate is 3%, which project would you choose and why? Show your work using excel (15 points) If the interest rate is 15%, which project would you choose and why? Show your work using excel...
0. 0. 0. 0.0. 0. 0. 0. 0. 1. 1. 1. 1. 1. 1. 2. 2. 2. 3. 4.
0. 0. 0. 0.0. 0. 0. 0. 0.   1. 1. 1. 1. 1. 1. 2. 2. 2. 3.   4. A.)MEAN – B.)MEDIAN - C.)MODE - D.)STANDARD DEVIATION – E.)5 NUMBER SUMMARY – F.)BOX AND WHISKERS PLOT – G.) OUTLIERS-
0. 0. 0. 0.0. 0. 0. 0. 0. 1. 1. 1. 1. 1. 1. 2. 2. 2. 3. 4.
0. 0. 0. 0.0. 0. 0. 0. 0.   1. 1. 1. 1. 1. 1. 2. 2. 2. 3.   4. A.)5 NUMBER SUMMARY – B.)BOX AND WHISKERS PLOT – C.) OUTLIERS-
2. a) Calculate the IRR of the following cash flows: -$550,000 in year 0; $430,000 in...
2. a) Calculate the IRR of the following cash flows: -$550,000 in year 0; $430,000 in year 1; $100,000 in year 2; and $200,000 in year 3. Is the project acceptable if the cost of capital is 10%? b) Now calculate the MIRR of the same cash flows assuming a reinvestment rate of 12%. Is the project acceptable or not acceptable under this methodology?
?" + 3?′ + 2? = ????, ?(0) = 0, ?′(0) = 2 1) Please solve...
?" + 3?′ + 2? = ????, ?(0) = 0, ?′(0) = 2 1) Please solve using an annihilator 2) Please solve using the Method of Variation of Parameters Thank you.
Consider the following function: (?) = ?(?3 + 1), ? = 0, 1, 2, 3 What...
Consider the following function: (?) = ?(?3 + 1), ? = 0, 1, 2, 3 What is the value of the constant ? so that (?) is a pmf? Plug-in the value of ? in the expression of (?) and show the pmf in a table. Draw a probability histogram of the pmf. Find the cdf (?) and write it explicitly defined over the entire real number line. Draw the cdf (?). Calculate the probabilities: (i). (0 < ? ≤...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT