In: Finance
Consider the following two mutually exclusive projects: |
Year | Cash Flow (A) | Cash Flow (B) |
0 | –$350,000 | –$35,000 |
1 | 25,000 | 19,000 |
2 | 70,000 | 11,000 |
3 | 70,000 | 19,000 |
4 | 410,000 | 11,000 |
The required return on these investments is 12 percent. |
Required: | |
(a) |
What is the payback period for each project? (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g., 32.16).) |
Payback period | |
Project A | years |
Project B | years |
(b) |
What is the NPV for each project? (Do not round intermediate calculations. Round your answers to 2 decimal places (e.g.,32.16).) |
Net present value | |
Project A | $ |
Project B | $ |
(c) |
What is the IRR for each project? (Do not round intermediate calculations. Enter your answer as a percentage rounded to 2 decimal places (e.g., 32.16).) |
Internal rate of return | |
Project A | % |
Project B | % |
(d) |
What is the profitability index for each project? (Do not round intermediate calculations. Round your answers to 3 decimal places (e.g., 32.161).) |
Profitability index | |
Project A | |
Project B | |
(e) | Based only on the projects' NPV and IRR, which project should you finally choose? |
Answer a.
Project A:
Company will recover $165,000 in first 3 years and remaining $185,000 in year 4.
Payback Period = 3 + $185,000/$410,000
Payback Period = 3.45 years
Project B:
Company will recover $30,000 in 2 years and remaining $5,000 in year 3
Payback Period = 2 + $5,000/$19,000
Payback Period = 2.26 years
Answer b.
Project A:
Present Value of Cash Inflows = $25,000/1.12 + $70,000/1.12^2 +
$70,000/1.12^3 + $410,000/1.12^4
Present Value of Cash Inflows = $388,512.03
NPV = Present Value of Cash Inflows - Initial Investment
NPV = $388,512.03 - $350,000
NPV = $38,512.03
Project B:
Present Value of Cash Inflows = $19,000/1.12 + $11,000/1.12^2 +
$19,000/1.12^3 + $11,000/1.12^4
Present Value of Cash Inflows = $46,247.94
NPV = Present Value of Cash Inflows - Initial Investment
NPV = $46,247.94 - $35,000
NPV = $11,247.94
Answer c.
Project A:
Let IRR be i%
NPV = -$350,000 + $25,000/(1+i) + $70,000/(1+i)^2 +
$70,000/(1+i)^3 + $410,000/(1+i)^4
0 = -$350,000 + $25,000/(1+i) + $70,000/(1+i)^2 + $70,000/(1+i)^3 +
$410,000/(1+i)^4
Using financial calculator, i = 15.49%
IRR of Project A = 15.49%
Project B:
Let IRR be i%
NPV = -$35,000 + $19,000/(1+i) + $11,000/(1+i)^2 +
$19,000/(1+i)^3 + $11,000/(1+i)^4
0 = -$35,000 + $19,000/(1+i) + $11,000/(1+i)^2 + $19,000/(1+i)^3 +
$11,000/(1+i)^4
Using financial calculator, i = 27.50%
IRR of Project A = 27.50%
Answer d.
Project A:
Profitability Index = Present Value of Cash Inflows / Initial
Investment
Profitability Index = $338,512.03 / $350,000
Profitability Index = 0.97
Project B:
Profitability Index = Present Value of Cash Inflows / Initial
Investment
Profitability Index = $46,247.94 / $35,000
Profitability Index = 1.32
Answer e.
Based on NPV, project A should be accepted. Based on IRR, project B should be selected. So, Project A should be selected.