In: Finance
An electric utility is considering a new power plant in northern Arizona. Power from the plant would be sold in the Phoenix area, where it is badly needed. Because the firm has received a permit, the plant would be legal; but it would cause some air pollution. The company could spend an additional $40 million at Year 0 to mitigate the environmental problem, but it would not be required to do so. The plant without mitigation would cost $210.64 million, and the expected cash inflows would be $70 million per year for 5 years. If the firm does invest in mitigation, the annual inflows would be $76.08 million. Unemployment in the area where the plant would be built is high, and the plant would provide about 350 good jobs. The risk adjusted WACC is 19%.
Calculate the NPV and IRR with mitigation. Round your answers to
two decimal places. Enter your answer for NPV in millions. Do not
round your intermediate calculations. For example, an answer of
$10,550,000 should be entered as 10.55. Negative value should be
indicated by a minus sign.
NPV $ million
IRR %
Calculate the NPV and IRR without mitigation. Round your answers
to two decimal places. Enter your answer for NPV in millions. Do
not round your intermediate calculations. For example, an answer of
$10,550,000 should be entered as 10.55.
NPV $ million
IRR %
a: With Mitigation
NPV = $ 3.39 m
IRR = 19.72%
Without mitigation
NPV = -18.02 m
IRR = 15.74%
Year | Without Mitigation | With Mitigation | |
0 | -210.64 | -250.64 | |
1 | 70 | 76.08 | |
2 | 70 | 76.08 | |
3 | 70 | 76.08 | |
4 | 70 | 76.08 | |
5 | 70 | 76.08 | |
Without Mitigation | With Mitigation | ||
NPV | 3.39 | NPV | -18.02 |
IRR | 19.72% | IRR | 15.74% |
b: V
At the above analysis the project has negative NPV and is unprofitable. However, all costs such as penalties and cost of loss of goodwill must be considered before making the final decision.
The environmental effects cannot be ignored . This is not sunk cost but incremental cash outflowMoreover it is a certainty and not a remote possibility They are various benefits to undertaking the cost in the form of additional goodwill and fulfilment of social responsibility.
c: I
The project should be undertaken only under "no mitigation" .
Management should ensure that cost of negative goodwill and
penalties are considered.
If mitigation is undertaken there is negative NPV. The IRR is less
than the cost of capital and hence this option is
unprofitable. However if mitigation is not undertaken
the project is profitable and should be considered.
WORKINGS