Which of the following statements is false regarding the Bluebeam software package?
It can be used to manage a digital document set. |
||
It can be used to create hyperlinks between documents to simplify navigation. |
||
It can be used to perform on-screen takeoffs of materials. |
||
It can be used to create project schedules. |
In the Activity Block, the number of working days needed to perform a specific activity is called:
Interval |
||
Length |
||
Duration |
||
Extent |
Which of the following best describes when the successor activity cannot start until the predecessor activity finishes (for example: Activity B starts after the end of Activity A)?
Start-to-start |
||
Finish-to-start |
||
Finish-to-finish |
||
None of the above |
In scheduling software, the least commonly used relationship is:
Finish -to-start |
||
Start-to-start |
||
Finish-to-finish |
||
Start-to-finish |
||
The duration assigned to a predecessor activity to delay its successor is called:
Lag |
||
Lead |
||
Successor |
||
First activity |
||
When adding or deleting doors and windows in Revit, the door and window schedule will automatically update.
True
False
1. Which of the following statements is false regarding the Bluebeam software package?
Answer:- It can be used to create project schedules. This is a false statement. Bluebeam is used to manage the informations and digital files not for creating files or schedules
2 In the Activity Block, the number of working days needed to perform a specific activity is called:
Answer Duration
3. Which of the following best describes when the successor activity cannot start until the predecessor activity finishes (for example: Activity B starts after the end of Activity A)?
Answer Finish-to-start
4. In scheduling software, the least commonly used relationship is:
Answer Start-to-finish
5. The duration assigned to a predecessor activity to delay its successor is called:
Answer is Lag. Lag is time period by which a predecessor activity is delayed due to which start of the successor is delayed.
6. When adding or deleting doors and windows in Revit, the door and window schedule will automatically update.
Yes true. In Revit if we update doors and windows or delete them then theri scheduled will be automatically update.
True