Question

In: Finance

7. A firm is considering a mining project with the following cash flows (with the final...

7. A firm is considering a mining project with the following cash flows (with the final cash flow being negative, perhaps due to an extensive land reclamation in the project’s final year):

C0 = –$420, C1 = $420, C2 = $462, C3 = $546, C4 = $420, and C5 = –$1554. (a) From among the following multiple-choice answers, calculate this project’s internal rate(s) of return: 5.070%, 25.225%, 33.333%, 51.909%, 82.425%. (2 pts.) (b) If the required return is 30.000%, should the project be rejected or accepted? Briefly, clearly justify and explain your reasoning. (2 pts.)

Solutions

Expert Solution

IRR is calculated by solving for the follwing equation:

NPV will be 0 when we discount using the IRR as IRR is the rate at which the cash inflows = cash outflows

  • Now basically, we need to use either hit and trial method or the the goal seek function for finding out the IRR which satisfies the above equation.
  • But as this is a multiple choice question we can use the given values and substitute them in the above equation to find out the right value.
  • We also need to consider that there can be multiple IRRs as the cash flow series in unconventional.

Starting with the discount rate = 5.070%

As NPV is positive this is not the correct IRR,

If the discount rate = 25.225%

As NPV is positive this is not the correct IRR

If the discount rate = 33.333%

As NPV is positive this is not the correct IRR

If the discount rate = 51.909%

As NPV is positive this is not the correct IRR

If the discount rate = 82.425%

As NPV = 0 so this is the correct IRR

Now coming to the other part in the question, whether this project is worth investing in if the discount rate is 30%, if the cash flows are conventional then we actually dont need to solve the above equation again because there will only be one IRR and till the time the discount rate is less than the IRR, we will have a positive NPV and we should invest. But the CF are unconventional in this case so there is a chance of multiple IRR and so we will have to resolve the above equation to verify:

As NPV is positive, we should invest in this project, ie the project should be accepted.


Related Solutions

A firm is considering a mining project with the following cash flows (with the final cash...
A firm is considering a mining project with the following cash flows (with the final cash flow being negative, perhaps due to an extensive land reclamation in the project’s final year): C0 = –$280, C1 = $280, C2 = $308, C3 = $364, C4 = $280, and C5 = –$1036. (a) From among the following multiple-choice answers, calculate this project’s internal rate(s) of return: 5.070%, 25.225%, 33.333%, 51.909%, 82.425%. (2 pts.) (b) If the required return is 30.000%, should the...
7. Suppose your firm is considering investing in a project with the cash flows shown below,...
7. Suppose your firm is considering investing in a project with the cash flows shown below, that the required rate of return on projects of this risk class is 12 percent, and that the maximum allowable payback and discounted payback statistic for the project are 2 and 3 years, respectively.   Time 0 1 2 3 4 5 6   Cash Flow -1,100 80 520 720 720 320 720 Use the discounted payback decision rule to evaluate this project; should it be...
A firm is considering investing in a project with the following cash flows: Year 1 2...
A firm is considering investing in a project with the following cash flows: Year 1 2 3 4 5 6 7 8 Cash flow (OMR) 1,000 1,500 2,000 1,750 1,500 1,000 1,000 500 The initial investment is OMR 7,250. The firm has a required rate of return of 8 per cent. Calculate: The payback period;    The discounted payback; The net present value.   
A firm is considering an investment project with the following cash flows: Year 0 = -$110,000...
A firm is considering an investment project with the following cash flows: Year 0 = -$110,000 (initial costs); Year 1= $40,000; Year 2 =$90,000; and Year 3 = $30,000; and Year 4 = $60,000. The company has a 10% cost of capital. What is the project’s discounted payback? 1.67 years 1.86 years 1.99 years 2.08 years A firm is considering an investment project with the following cash flows: Year 0 = -$110,000 (initial costs); Year 1= $40,000; Year 2 =$90,000;...
firm is considering a project with the following expected cash flows: Year Cash Flow 0 -P350...
firm is considering a project with the following expected cash flows: Year Cash Flow 0 -P350 million 1 100 million 2 185 million 3 112.5 million 4 350 million The project’s WACC is 10 percent. What is the project’s discounted payback? a. 3.15 years b. 4.09 years c. 1.62 years d. 3.09 years The lolo Corporation has been presented with an investment opportunity that will yield end-of-year cash flows of $30,000 per year in Years 1 through 4, $35,000 per...
A firm is considering Projects S and L, with the following cash flows: Project L: −$2,150...
A firm is considering Projects S and L, with the following cash flows: Project L: −$2,150 in year 0, $765 in years 1, 2, 3, and 4 Project S: −$1,025 in year 0, $380 in years 1, 2, 3, and 4 These projects are mutually exclusive. The projects are also equally risky with WACC of 6%. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the...
Bohrer Mining, Inc., is trying to evaluate a project with the following cash flows: Year Cash...
Bohrer Mining, Inc., is trying to evaluate a project with the following cash flows: Year Cash Flow 0 –$ 38,500,000 1 62,500,000 2 – 11,500,000 a-1 What is the NPV for the project if the company requires a return of 12 percent? (Do not round intermediate calculations and round your answer to 2 decimal places, e.g., 32.16.) NPV $ a-2 Should the firm accept this project? Yes No b. This project has two IRRs, namely____ percent and ____ percent, in...
You are considering a project with the following cash​ flows: YEAR                      PROJECT CASH FLOW    ...
You are considering a project with the following cash​ flows: YEAR                      PROJECT CASH FLOW     0                         -60,000     1                         25,000     2                         25,000     3                         25,000     4                         25,000 If the appropriate discount rate is 11 ​percent, what is the​ project's discounted payback​ period in years?
.   Suppose your firm is considering investing in a project with the cash flows shown as...
.   Suppose your firm is considering investing in a project with the cash flows shown as follows, that the required rate of return on projects of this risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the project are three and three and a half years, respectively. Time 0 1 2 3 4 5 Cashflow -100,000 30,000 45,000 55,000 30,000 10,000 Calculate the payback and use the payback decision rule to evaluate this...
19) A firm is considering a project that is expected to generate annual cash flows of...
19) A firm is considering a project that is expected to generate annual cash flows of $24,000 for 15 years. The project requires an initial investment of $247,103.44. The cost of capital is 8.13%. What is the IRR of the project?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT