In any given Project, risk form an
integral part. Certain risks are incidental to a Project which may
not be completely eliminated but can be taken in control while
there are few other risks that can be mitigated completely.
Therefore, it cannot be actually reasonable to assume that Project
risk will remain static throughout the Project life cycle. Few
risks that are out of our control may remain static because it can
impact the Project at any point of time while few other risks that
can be eliminated during the Project Life Cycle, shall not remain
static at all times owing to our power of control over it.
Hence the good practice when dealing
with risk throughout the Project Life Cycle would be to essentially
undertake the Risk plan in order to identify the risks associated
with the Project and how could it be best managed with.
Hence Risk plan helps in identifying the risks,
quantifying the same to understand the gravity and impact of such
risks associated in the Project and to undertake the measures to
overcome the same. Accordingly, it shall be necessary to understand
what is risk, how can it be identified, measured and mitigated.
Risk means deviations from
Expectations and is measured in terms of variability of returns.
The expected return reflects the benefits an investor anticipates
from investment and the Required return reflects the return an
investor demands for assuming risk. Hence, when expected return
matches required return in all scenarios, the project risk is
considered low. In order to deal with it, there are various methods
that could be aptly applied:
For example,
Quantitative theory
- Calculus , probability
distributions, mathematical statistics
- Econometrics , Business research
methods
- Financial engineering
techniques-numerical methods
- Process analysis
methods-operational risk
- Multivariate statistics
- Technical analysis
- Mathematical modeling
- MATLAB, MAPLE, SPPS, EVIEWS,
STATITICA
- PROWESS,CLINE, BLOOMBERG,
- KONDOR+,REUTERS, META STOCK
etc…
PROJECT MITIGATION
TECHNIQUES
- Supply/Inputs Risk Mitigation
- Proper due diligence
- Controlling the source, availability of alternatives
- Enforceable contracts
- Market Risk Mitigation
- Market study
- Good economics
- Sales contracts wherever “necessary”
- Industry/sector expertise
- Infrastructure Risk Mitigation
- Proper Feasibility study
- Ensure necessary infrastructure
- Environmental Risk Mitigation
- Proper Environmental Impact Assessment
- Address various issues
- Regulatory Issues
- Site Clearances
- Ministry of Environment & Forests Clearance Under
Environment Protection Act, 1986. Notification issued in 1994 and
modified from time to time
- CRZ clearances
- Environmental Norms used
- Issues with Local Population
- Long term effect issues
- Soil Contamination
- Health problems
- Fire / Explosion / Plant outage hazards
- Ensure compliances with norms
- Environmental Risk Mitigation
- Environmental Impact Assessment (EIA)
- Preliminary EIA done using standardized checklist & to
determine factors that would need detailed analysis during second
phase of assessment
- EIA in second phase consists of identification & evaluation
of environmental impacts resulting from the project
- EIA in 3rd phase consists of the preparation EI Statement. It
brings out mitigation measures that would make the project
environmentally acceptable
- The purpose of EIA statement is to bring out environmental
consequences of the project & its compliance with the statutory
requirements
- Political Risk
- War, insurrection, civil disturbance
- Nationalization
- Currency inconvertibility/transfer problems
- Contract frustration
- Change in Law, etc.
- Mitigation
- State Support Agreement
- Direct Agreement
- Good economics
- Force Majeure clause
- ECA/MIGA/World Bank (Partial Risk) Cover
- Force Majeure
- Natural - Insurable
- Political - Direct/Indirect - Relief from contractual
obligations, indemnity from the government
- Forex
- Syndication/Funding
- Select reputed financial advisor
- Select reputed financial advisor
- Attempt underwritten deal
- Have a reputed anchor lender
- Legal Risk
- Select reputed Legal Advisor
- Negotiate contract terms carefully
- Ensure compliances
- Select applicable law and venue of jurisdiction carefully