A process makes two products. A and B. and operates 5 days per week. 8 hours...

A process makes two products. A and B. and operates 5 days per week. 8 hours per day. Demand for the two products for the next week is as follows:
Day 1: A: 20; B:26
Day 2: A: 10: B:15
Day 3: A: 20; B:19
Day 4: A: 18; B:20
Day 5: A: 12; B: 20
 
What is the takt time of the process? What would a level production schedule look like?

Solutions

Expert Solution

Takt time = Available time / Rate of Customer demand

Available time = 5 days per week * 8 hours per day

= 40 hours

Demand for A = 80 units

Demand for B = 100 units

Total demand = 180 units

Takt time = 40 / 180 = 0.22 hours/unit


Related Solutions

QUESTION 1 The Jubail Bicycle Shop operates 7 days per week, closing 5 days each for...
QUESTION 1 The Jubail Bicycle Shop operates 7 days per week, closing 5 days each for Eid-ul-Fitr and Eid- Ul -Adah (this gives 355 working days in a year). The shop pays SAR 600 for a particular bicycle purchased from the manufacturer. The annual holding cost per bicycle is estimated to be 25% of the SAR value of inventory. The shop sells an average of 25 bikes per week. Frequently, the dealer does not have a bike in stock when...
The Jubail Bicycle Shop operates 7 days per week, closing 5 days each for Eid-ul-Fitr and...
The Jubail Bicycle Shop operates 7 days per week, closing 5 days each for Eid-ul-Fitr and Eid- Ul -Adah (this gives 355 working days in a year). The shop pays SAR 600 for a particular bicycle purchased from the manufacturer. The annual holding cost per bicycle is estimated to be 25% of the SAR value of inventory. The shop sells an average of 25 bikes per week. Frequently, the dealer does not have a bike in stock when a customer...
Sam's Cat Hotel operates 52 weeks per? year, 5 days per? week, and uses a continuous...
Sam's Cat Hotel operates 52 weeks per? year, 5 days per? week, and uses a continuous review inventory system. It purchases kitty litter for ?$11.50 per bag. The following information is available about these bags. Refer to the standard normal table LOADING... for? z-values. Demand ?= 80 ?bags/week Order cost? = ?$58?/order Annual holding cost? = 30 percent of cost Desired ?cycle-service levelequals90 percent Lead time? = 2 ?week(s) ?(10 working? days) Standard deviation of weekly demand? = 16 bags...
A Company uses a 10-hp motor for 16 hours per day, 5 days per week, 50...
A Company uses a 10-hp motor for 16 hours per day, 5 days per week, 50 weeks per year in its flexible work cell. This motor is 85% efficient, and it is near the end of its useful life. The company is considering buying a new high efficiency motor (91% efficient) to replace the old one instead of buying a standard efficiency motor (86.4% efficient). The high efficiency motor cost $70 more than the standard model, and should have a...
Sam's Cat Hotel operates 52 weeks per year, 7 days per week
Sam's Cat Hotel operates 52 weeks per year, 7 days per week, and uses a continuous review inventory system. It purchases kitty litter for $10.75 per bag. The following information is available about these bags. Refer to the standard normal table for z-values. >Demand 95 bags/week >Order cost $56/order >Annual holding cost = 30 percent of cost >Desired cycle-service level = 99 percent >Lead time = 4 week(s) (28 working days) >Standard deviation of weekly demand = 20 bags >Current on-hand inventory is 325 bags, with no...
23 years old, makes $14 per hour (8hour), works for 5 days a week. Please use...
23 years old, makes $14 per hour (8hour), works for 5 days a week. Please use this information for the following questions. The answer to number 6 is $1,095,657.55 and The answer to number 5 is $80,620.37 7.How much do you need to save per month (at the end of each month) in an investment earning 7% per year now to reach the amount in Question 6 by age 65? Assume you have no money now in the investment. 8.Then...
Chapin Manufacturing Company operates 24 hours a day, five days a week. The workers rotate shifts...
Chapin Manufacturing Company operates 24 hours a day, five days a week. The workers rotate shifts each week. Management is interested in whether there is a difference in the number of units produced when the employees work on various shifts. A sample of five workers is selected and their output recorded on each shift. At the 0.05 significance level, can we conclude there is a difference in the mean production rate by shift or by employee? Units Produced Employee Day...
Chapin Manufacturing Company operates 24 hours a day, five days a week. The workers rotate shifts...
Chapin Manufacturing Company operates 24 hours a day, five days a week. The workers rotate shifts each week. Management is interested in whether there is a difference in the number of units produced when the employees work on various shifts. A sample of five workers is selected and their output recorded on each shift. At the 0.01 significance level, can we conclude there is a difference in the mean production rate by shift or by employee? Units Produced Employee Day...
Chapin Manufacturing Company operates 24 hours a day, five days a week. The workers rotate shifts...
Chapin Manufacturing Company operates 24 hours a day, five days a week. The workers rotate shifts each week. Management is interested in whether there is a difference in the number of units produced when the employees work on various shifts. A sample of five workers is selected and their output recorded on each shift. At the 0.05 significance level, can we conclude there is a difference in the mean production rate by shift or by employee? Units Produced Employee Day...
Chapin Manufacturing Company operates 24 hours a day, five days a week. The workers rotate shifts...
Chapin Manufacturing Company operates 24 hours a day, five days a week. The workers rotate shifts each week. Management is interested in whether there is a difference in the number of units produced when the employees work on various shifts. A sample of five workers is selected and their output recorded on each shift. At the 0.01 significance level, can we conclude there is a difference in the mean production rate by shift or by employee? Units Produced Employee Day...