Question

In: Other

A process makes two products. A and B. and operates 5 days per week. 8 hours...

A process makes two products. A and B. and operates 5 days per week. 8 hours per day. Demand for the two products for the next week is as follows:
Day 1: A: 20; B:26
Day 2: A: 10: B:15
Day 3: A: 20; B:19
Day 4: A: 18; B:20
Day 5: A: 12; B: 20
 
What is the takt time of the process? What would a level production schedule look like?

Solutions

Expert Solution

Takt time = Available time / Rate of Customer demand

Available time = 5 days per week * 8 hours per day

= 40 hours

Demand for A = 80 units

Demand for B = 100 units

Total demand = 180 units

Takt time = 40 / 180 = 0.22 hours/unit


Related Solutions

Sam's Cat Hotel operates 52 weeks per? year, 5 days per? week, and uses a continuous...
Sam's Cat Hotel operates 52 weeks per? year, 5 days per? week, and uses a continuous review inventory system. It purchases kitty litter for ?$11.50 per bag. The following information is available about these bags. Refer to the standard normal table LOADING... for? z-values. Demand ?= 80 ?bags/week Order cost? = ?$58?/order Annual holding cost? = 30 percent of cost Desired ?cycle-service levelequals90 percent Lead time? = 2 ?week(s) ?(10 working? days) Standard deviation of weekly demand? = 16 bags...
A Company uses a 10-hp motor for 16 hours per day, 5 days per week, 50...
A Company uses a 10-hp motor for 16 hours per day, 5 days per week, 50 weeks per year in its flexible work cell. This motor is 85% efficient, and it is near the end of its useful life. The company is considering buying a new high efficiency motor (91% efficient) to replace the old one instead of buying a standard efficiency motor (86.4% efficient). The high efficiency motor cost $70 more than the standard model, and should have a...
Sam's Cat Hotel operates 52 weeks per year, 7 days per week
Sam's Cat Hotel operates 52 weeks per year, 7 days per week, and uses a continuous review inventory system. It purchases kitty litter for $10.75 per bag. The following information is available about these bags. Refer to the standard normal table for z-values. >Demand 95 bags/week >Order cost $56/order >Annual holding cost = 30 percent of cost >Desired cycle-service level = 99 percent >Lead time = 4 week(s) (28 working days) >Standard deviation of weekly demand = 20 bags >Current on-hand inventory is 325 bags, with no...
Chapin Manufacturing Company operates 24 hours a day, five days a week. The workers rotate shifts...
Chapin Manufacturing Company operates 24 hours a day, five days a week. The workers rotate shifts each week. Management is interested in whether there is a difference in the number of units produced when the employees work on various shifts. A sample of five workers is selected and their output recorded on each shift. At the 0.05 significance level, can we conclude there is a difference in the mean production rate by shift or by employee? Units Produced Employee Day...
Chapin Manufacturing Company operates 24 hours a day, five days a week. The workers rotate shifts...
Chapin Manufacturing Company operates 24 hours a day, five days a week. The workers rotate shifts each week. Management is interested in whether there is a difference in the number of units produced when the employees work on various shifts. A sample of five workers is selected and their output recorded on each shift. At the 0.01 significance level, can we conclude there is a difference in the mean production rate by shift or by employee? Units Produced Employee Day...
Chapin Manufacturing Company operates 24 hours a day, five days a week. The workers rotate shifts...
Chapin Manufacturing Company operates 24 hours a day, five days a week. The workers rotate shifts each week. Management is interested in whether there is a difference in the number of units produced when the employees work on various shifts. A sample of five workers is selected and their output recorded on each shift. At the 0.05 significance level, can we conclude there is a difference in the mean production rate by shift or by employee? Units Produced Employee Day...
Chapin Manufacturing Company operates 24 hours a day, five days a week. The workers rotate shifts...
Chapin Manufacturing Company operates 24 hours a day, five days a week. The workers rotate shifts each week. Management is interested in whether there is a difference in the number of units produced when the employees work on various shifts. A sample of five workers is selected and their output recorded on each shift. At the 0.01 significance level, can we conclude there is a difference in the mean production rate by shift or by employee? Units Produced Employee Day...
MW is a large discount store that operates seven days per week. The store needs the...
MW is a large discount store that operates seven days per week. The store needs the following number of full-time employees working each day of the week. Sunday Monday Tuesday Wednesday Thursday Friday Saturday # of Employees 188 88 112 140 136 172 212 Each employee must work five consecutive days each week and then have two days off. For example, any employee who works Sunday through Thursday has Friday and Saturday off. The store currently has a total of...
Sam's Cat Hotel operates 5252 weeks per? year, 77 days per? week, and uses a continuous...
Sam's Cat Hotel operates 5252 weeks per? year, 77 days per? week, and uses a continuous review inventory system. It purchases kitty litter for ?$10.7510.75 per bag. The following information is available about these bags. Refer to the standard normal table LOADING... for? z-values. Demand = 100 bags/weeks Order cost = $56/order Annual Holding Cost = 30 percent of cost Desired cycle-service level =99 percent Lead time = 2 weeks (14 working days) Standard deviation of weekly demand = 10...
At Lummins Engine Corporation, production employees work 10 hours per day, four days per week. Each...
At Lummins Engine Corporation, production employees work 10 hours per day, four days per week. Each day of the week, at least the following number of employees must be working: Monday through Friday, seven employees; Saturday and Sunday, three employees. Lummins has set the following goals, listed in order ofpriority: ■ Goal 1: Meet employee requirements with 11 workers. ■ Goal 2: The average number of weekend days off per employee should be at least 1.5 days. ■ Goal 3:...