In: Accounting
Material, Labor, and Variable Overhead Variances The following summarized manufacturing data relate to Kiosse Corporation’s May operations, during which 2,000 finished units of product were produced. Normal monthly capacity is 1,100 direct labor hours.
Standard Units Costs | Total Actual Costs | ||||||
---|---|---|---|---|---|---|---|
Direct material | |||||||
Standard (3 lb. @ $2.00/lb.) | $6 | ||||||
Actual (6,200 lb. @ $2.20/lb.) | $13,640 | ||||||
Direct labor | |||||||
Standard (0.5 hr. @ $14/hr.) | $7 | ||||||
Actual (980 hrs. @ $13.70/hr.) | 13,426 | ||||||
Variable overhead | |||||||
Standard (0.5 hr. @ $4/hr.) | $2 | ||||||
Actual | - | 4,200 | |||||
Total | $15 | $31,266 |
Assume that the 6,200 lb. of materials purchased were all used in producing the 2,000 completed units. Determine the materials price and efficiency variances, labor rate and efficiency variances, and variable overhead spending and efficiency variances.
Do not use negative signs with any of your answers. Next to each variance answer, select either "F" for Favorable or "U" for Unfavorable.
Materials Variances | ||
---|---|---|
Actual cost: | Answer | |
Split cost: | Answer | |
Standard cost: | Answer | |
Materials price | Answer | AnswerFU |
Materials efficiency | Answer | AnswerFU |
Labor Variances | ||
---|---|---|
Actual cost: | Answer | |
Split cost: | Answer | |
Standard cost: | Answer | |
Labor rate | Answer | AnswerFU |
Labor efficiency | Answer | AnswerFU |
Variable Overhead Variances | ||
---|---|---|
Actual cost: | Answer | |
Split cost: | Answer | |
Standard cost: | Answer | |
Variable overhead spending | Answer | AnswerFU |
Variable overhead efficiency | Answer | AnswerFU |
Material Variance |
||
Actual Cost |
$13,640 |
6200 lbs x $ 2.2 |
Split Cost |
$12,400 |
6200 lbs x $ 2 |
Standard Cost |
$12,000 |
2000 units x 3 lb x $ 2 |
Material Price Variance |
$1,240 |
Unfavourable |
Material Efficiency Variance |
$400 |
Unfavourable |
Labor Variance |
||
Actual Cost |
$13,426 |
980 x $ 13.70 |
Split Cost |
$13,720 |
980 x $ 14 |
Standard Cost |
$14,000 |
2000 units x 0.5 hr x $14 |
Labor rate Variance |
$294 |
Favourable, as Actual rate is LESS than Standard rate |
Labor Efficiency Variance |
$280 |
Favourable, as Actual hr is LESS than Standard hr |
Variable Overhead Variance |
||
Actual Cost |
$4,200 |
|
Split Cost |
$3,920 |
980 x $ 4 |
Standard Cost |
$4,000 |
2000 x 0.5hrs x $ 4 |
Variable Overhead rate Variance |
$280 |
Unfavourable |
Variable Overhead Efficiency Variance |
$80 |
Favourable |