In: Finance
CAPITAL BUDGETING CRITERIA
A firm with a 13% WACC is evaluating two projects for this
year's...
CAPITAL BUDGETING CRITERIA
A firm with a 13% WACC is evaluating two projects for this
year's capital budget. After-tax cash flows, including
depreciation, are as follows:
Project M |
-$12,000 |
$4,000 |
$4,000 |
$4,000 |
$4,000 |
$4,000 |
Project N |
-$36,000 |
$11,200 |
$11,200 |
$11,200 |
$11,200 |
$11,200 |
NPV for each project:
Project M $ 2,068.93
Project N $3,392.99
IRR for each project:
Project M 19.86%
Project N 16.80%
MIRR for each project:
Project M 16.65 %
Project N 15.05%
Calculate payback for each project. Round your answers to two
decimal places. Do not round your intermediate calculations.
Project M 3.00 years
Project N 3.21 years
Discounted payback for each project:
Project M 4.05years
Project N 4.04 years
- Assuming the projects are independent, which one(s) would you
recommend?
-Select-Only Project M would be accepted because IRR(M) >
IRR(N).Both projects would be rejected since both of their NPV's
are negative.Only Project M would be accepted because NPV(M) >
NPV(N).Only Project N would be accepted because NPV(N) >
NPV(M).Both projects would be accepted since both of their NPV's
are positive.Item 11
- If the projects are mutually exclusive, which would you
recommend?
-Select-If the projects are mutually exclusive, the project with
the highest positive IRR is chosen. Accept Project N.If the
projects are mutually exclusive, the project with the highest
positive NPV is chosen. Accept Project N.If the projects are
mutually exclusive, the project with the highest positive IRR is
chosen. Accept Project M.If the projects are mutually exclusive,
the project with the highest positive MIRR is chosen. Accept
Project M.If the projects are mutually exclusive, the project with
the shortest Payback Period is chosen. Accept Project M.Item
12
-
Notice that the projects have the same cash flow timing pattern.
Why is there a conflict between NPV and IRR?
-Select-There is no conflict between NPV and IRR.The conflict
between NPV and IRR occurs due to the difference in the size of the
projects.The conflict between NPV and IRR is due to the relatively
high discount rate.The conflict between NPV and IRR is due to the
fact that the cash flows are in the form of an annuity.The conflict
between NPV and IRR is due to the difference in the timing of the
cash flows.Item 13
|