In: Other
Develop a lot-for-lot solution and calculate total relevant costs for the gross requirements in the following table
Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 |
---|---|---|---|---|---|---|---|---|---|---|---|---|
Gross requirements | 30 | 30 | 30 | 60 | 20 | 20 | 70 | 50 |
Holding cost = $1.50/unitweek: setup cost = $200; lead time 1 week; beginning inventory 40
Develop a lot-for-lot solution (enter your responses as whole numbers).