Question

In: Civil Engineering

Consider a 2-acre detention basin with vertical walls. The triangular inflow hydrograph increases linearly from zero...

Consider a 2-acre detention basin with vertical walls. The triangular inflow hydrograph increases linearly from zero to a peak of 60 cfs at 60 min and then decreases linearly to a zero discharge at 180 min. Route the inflow hydrograph through the detention basin using the head discharge curve for the 5-ft pipe spillway in table below. The pipe is located at the bottom of the basin. Assuming the basin is initially empty, use the level pool routing procedure with 10-min time interval to determine the maximum depth in the detention basin.

Elevation Discharge

(ft) (cfs)

0.0    0

0.5    3

1.0    8

1.5 17

2.0 30

2.5 43

3.0 60

3.5 78

4.0 97

4.5 117

5.0 137

5.5 156

6.0 173

6.5 190

7.0 205

7.5 218

8.0 231

8.5 242

9.0 253

9.5 264

10.0 275

Solutions

Expert Solution

Inflow values are interpolated and values were obtained for each 10 min interval.

Time (min) Inflow (cfs)
0 0
10 10
20 20
30 30
40 40
50 50
60 60
70 55
80 50
90 45
100 40
110 35
120 30
130 25
140 20
150 15
160 10
170 5
180 0
H (ft) Discharge Q (cfs) Storage (ft3) 2S/t 2S/t + Q
0 0 0 0 0
0.5 3 43560 145.2 148.2
1 8 87120 290.4 298.4
1.5 17 130680 435.6 452.6
2 30 174240 580.8 610.8
2.5 43 217800 726 769
3 60 261360 871.2 931.2
3.5 78 304920 1016.4 1094.4
4 97 348480 1161.6 1258.6
4.5 117 392040 1306.8 1423.8
5 137 435600 1452 1589
5.5 156 479160 1597.2 1753.2
6 173 522720 1742.4 1915.4
6.5 190 566280 1887.6 2077.6
7 205 609840 2032.8 2237.8
7.5 218 653400 2178 2396
8 231 696960 2323.2 2554.2
8.5 242 740520 2468.4 2710.4
9 253 784080 2613.6 2866.6
9.5 264 827640 2758.8 3022.8
10 275 871200 2904 3179

S0 = 0 ft3/s; Q0 = ft3/s

2S1/t - Q1 = 2x0 -0 =0

2S2/t + Q2 = (I1+I2) + 2S1/t - Q1

Find Q1 by interpolating values from above table for corresponding 2S2/t + Q2 value

2S1/t - Q1 =  2S2/t + Q2 - 2Q1

Repeat this process

Time (min) I (ft3/s) Ii+Ii+1 (ft3/s) 2Si/t - Qi 2Si+1/t + Qi+1 Q (ft3/s)
0 0 0
10 10 10 0 10 0.2024
20 20 30 9.5952 39.5952 0.8015
30 30 50 37.9922 87.9922 1.7812
40 40 70 84.4298 154.4298 0.7074
50 50 90 153.015 243.015 3.6563
60 60 110 235.7024 345.7024 3.7608
70 55 115 338.1807 453.1807 1.5477
80 50 105 450.0853 555.0853 9.9217
90 45 95 535.2419 630.2419 3.5976
100 40 85 623.0466 708.0466 9.9912
110 35 75 688.0642 763.0642 14.5122
120 30 65 734.0397 799.0397 5.6484
130 25 55 787.7428 842.7428 10.2289
140 20 45 827.2849 872.2849 13.3252
150 15 35 845.6345 880.6345 14.2003
160 10 25 852.2339 877.2339 13.8439
170 5 15 849.5461 864.5461 12.5141
180 0 5 839.5179 844.5179 10.4149
190 0 823.6880 823.6880 8.2318
200 0 807.2244 807.2244 6.5063
210 0 794.2118 794.2118 5.1424
220 0 783.927 783.927 4.0645
230 0 775.7980 775.7980 3.2125

Maximum discharge = 14.5122 ft3/s. So depth of detention basin required = 1.5ft (corresponding to 17 ft3/s discharge from elevation discharge table). If exact value is required interpolation can be used.

So depth of basin = 1.33ft ~1.35 ft


Related Solutions

ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT