In: Accounting
The predetermined overhead rate is (
1,250,000 / 40,000) =
31.25 per machine hour.
In April, the recorded overhead would have been (4,780 x
31.25) =
149,375
This amount is larger than the actual overhead, so overhead was
over-applied by
(
149,375 -
141,800) =
7,575