Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher...

Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine​ ES, EF,​ LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity​ times:

Activity   Time (weeks)   Immediate Predecessor(s)   Activity   Time (weeks)   Immediate Predecessor(s)
A 6 - E 3 B
B 7 - F 7 B
C 2 A G 9 C, E
D 1 A    H 6 D , F

Dave's earliest start​ (ES) and earliest finish​ (EF) are:

Activity ES EF

A ? 6

What is ES?

Solutions

Expert Solution

step 1 find early start, and early finish from the start of the project for each activity
step 2 Find Maximum EF and keep it as the LF of last activities. Max of EF's is 20
Activity Duration, D Early start, ES=Max of early finish of preceding activities Early finish, EF = ES + D Late finish, LF= Min of LS of successor activities Late start, LS= LF - D
A 6 0 6
B 7 0 7
C 2 6 8
D 1 6 7
E 3 7 10
F 7 7 14
G 9 10 19 20
H 6 14 20 20
step 3 calculate LS for each activity after calculating its EF
Activity Duration, D Early start, ES=Max of early finish of preceding activities Early finish, EF = ES + D Late finish, LF= Min of LS of successor activities Late start, LS= LF - D
A 6 0 6 9 3
B 7 0 7 7 0
C 2 6 8 11 9
D 1 6 7 14 13
E 3 7 10 11 8
F 7 7 14 14 7
G 9 10 19 20 11
H 6 14 20 20 14

Related Solutions

Progressive Discipline This activity is important because, as a manager, you must be able to determine...
Progressive Discipline This activity is important because, as a manager, you must be able to determine the most effective and legally defensible discipline process for your organization. While ideally all employees will always abide by all organizational policies and practices, in reality this is unlikely. Therefore, managers and supervisors must be prepared to implement a well-designed and formally communicated discipline policy The goal of this exercise is to demonstrate your understanding of the progressive discipline process and how it can...
  Supervisor Kenneth Peterson wants to determine the percent of time a machine in his area...
  Supervisor Kenneth Peterson wants to determine the percent of time a machine in his area is idle. He decides to use work sampling, and his initial estimate is that the machine is idle 18% of the time. (Round all intermediate calculations to at least two decimal places before proceeding with further calculations.)   The number of observations that need to be taken by Peterson to be 95.00% confident that the results will be less than 6% from the true...
Liam is struggling to determine which deprecation method he should use for his new silk-screening machine....
Liam is struggling to determine which deprecation method he should use for his new silk-screening machine. He expects sales to increase over the next five years. He also expects (hopes) that in two years he will need to buy a second silk-screening machine to keep up with the demand for products of his growing company. Discuss which depreciation method makes more sense for Liam: Higher expenses in the first few years, or keeping expenses consistent over time? Or would it...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT