In: Operations Management
Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times:
Activity Time (weeks) Immediate
Predecessor(s) Activity Time
(weeks) Immediate Predecessor(s)
A 6 - E 3 B
B 7 - F 7 B
C 2 A G 9 C, E
D 1 A H 6 D , F
Dave's earliest start (ES) and earliest finish (EF) are:
Activity ES EF
A ? 6
What is ES?
step 1 | find early start, and early finish from the start of the project for each activity | ||||
step 2 | Find Maximum EF and keep it as the LF of last activities. Max of EF's is 20 |
Activity | Duration, D | Early start, ES=Max of early finish of preceding activities | Early finish, EF = ES + D | Late finish, LF= Min of LS of successor activities | Late start, LS= LF - D |
A | 6 | 0 | 6 | ||
B | 7 | 0 | 7 | ||
C | 2 | 6 | 8 | ||
D | 1 | 6 | 7 | ||
E | 3 | 7 | 10 | ||
F | 7 | 7 | 14 | ||
G | 9 | 10 | 19 | 20 | |
H | 6 | 14 | 20 | 20 |
step 3 | calculate LS for each activity after calculating its EF |
Activity | Duration, D | Early start, ES=Max of early finish of preceding activities | Early finish, EF = ES + D | Late finish, LF= Min of LS of successor activities | Late start, LS= LF - D |
A | 6 | 0 | 6 | 9 | 3 |
B | 7 | 0 | 7 | 7 | 0 |
C | 2 | 6 | 8 | 11 | 9 |
D | 1 | 6 | 7 | 14 | 13 |
E | 3 | 7 | 10 | 11 | 8 |
F | 7 | 7 | 14 | 14 | 7 |
G | 9 | 10 | 19 | 20 | 11 |
H | 6 | 14 | 20 | 20 | 14 |