In: Civil Engineering
The Queensland Government proposes to develop a high-speed train to link Gold Coast and Brisbane. The Government would like the train to travel at speeds in the range of 150-225 km/hour. It is expected that the train will run from Coolangatta to South Bank stopping at Robina, Nerang, Helensvale, and Coomera before running express to South Bank. The Government would like the elapsed time for travel between the Coomera and South Bank station to be approximately 30 minutes.
Your company has been chosen as the consultant to prepare an EIA report on the proposed fast-train network. Develop a preliminary EIA report for this project such as identify requirement and extent of EIA, Significant issues, Impact and mitigation plan for each significant issues
1. PROJECT BACKGROUND
The Queensland Government proposes to develop a high-speed train to
link Gold Coast and Brisbane. The Government would like the train
to travel at speeds in the range of 150-225 km/hour. It is expected
that the train will run from Coolangatta to South Bank stopping at
Robina, Nerang, Helensvale, and Coomera before running express to
South Bank. The Government would like the elapsed time for travel
between the Coomera and South Bank station to be approximately 30
minutes.
2. PROJECT ALIGNMENT
The train will run from Coolangatta to South Bank stopping at
Robina, Nerang, Helensvale, and Coomera before running express to
South Bank.
3. PROJECT INFLUENCE AREA
The towns of Robina, Nerang, Helensvale, and Coomera alongwith Brisbane and Gold Coast will be influenced by this project.
4. ENVIRONMENTAL IMPACT ASSESSMENT (EIA) STUDY IN THE
PROJECT
The Environmental Impact Assessment study of the project has been
carried out as per terms of reference of Queensland Government. The
study methodology for the EIA employs a simplistic approach in
which the important environmental receptors were identified during
the Environmental Screening phase. Based on the identification
baseline data was generated and then analysed to predict the
impacts and quantify them. Avoidance, Mitigation and Enhancements
measures were then developed and these have been incorporated in
the Environmental Management Plan (EMP), design drawings and / or
Bills of Quantities as appropriate. Implementation arrangements
including responsibilities of all the actors have been streamlined
and documented for future guidance.
5. SIGNIFICANT ISSUES
5.11 POTENTIAL ENVIRONMENTAL IMPACTS
The environmental components are mainly impacted during the
construction and operational stages of the project and have to be
mitigated for and incorporated in the engineering design.
Environmental mitigation measures represent the project’s endeavour
to reduce its environmental footprint to the minimum possible.
These are conscious efforts from the project to reduce undesirable
environmental impacts of the proposed activities and offset these
to the degree practicable. Enhancement measures are project’s
efforts to gain acceptability in its area of influence. They
reflect the pro-active approach of the project towards
environmental management.
5.1.1 Impacts on Climate
Impact on the climate conditions from the proposed road fast train
network will not be significant as no major deforestation and / or
removal of vegetation is involved for the project.
5.1.2 Impact on Air Quality
There will be rise in PM10 & PM2.5 levels during the
construction activities, which shall again be within prescribed
limit after the construction activities are over.
5.1.3 Impact on Noise Levels
The impact of noise levels from the proposed project on the
neighbouring communities is addressed. It has been concluded that
both day and night times equivalent noise levels are within the
permissible limits right from start of project life. Noise
sensitive receptors have been identified along the project
alignment.
5.1.4 Impact on Water Resources and Quality
The construction and operation of the proposed project will not
have any major impacts on the surface water and the ground water
quality in the area. Contamination to water bodies may result due
to spilling of construction materials, oil, grease, fuel and paint
in the equipment yards and asphalt plants. This will be more
prominent in case of locations where the project alignment crosses
rivers, canals distributaries, etc. Mitigation measures have been
planned to avoid contamination of these water bodies.
5.1.5 Impact on Ecological Resources
There is no major loss of vegetation hence adverse impact in terms
of availability of nesting sites for the bird doesn’t arise.
Furthermore, there is no sensitive ecological area along the
project alignment, so the impact will be insignificant during
construction period. But on the long run the project shall have a
positive impact due to the compensatory forestation and avenue
plantation.
5.1.6 Impact on Land
During the construction of the proposed project, the topography
will change due to excavation of borrow areas, stone quarrying,
cuts and fills for project road and construction of project related
structures etc. Provision of construction yard for material
handling will also alter the existing topography. The change in
topography will also be due to the probable induced developments of
the project. Benefits in the form of land levelling and tree
plantations in the vicinity of the project alignment shall enhance
the local aesthetics.
5.1.7 Impact on Human Use Values
The PAPs shall be compensated as per the RAP. There shall also be
some impacts on cultural or religious properties along the
corridor.
6 MITIGATION MEASURES PROPOSED
The mitigation / avoidance / enhancement measures for the various
environmental components for the different project packages are
described below. The measures are described in the same order as
detailed out in the Assessment of Impacts.
6.1 Meteorological Parameters
Avoidance measures, such as the minimising of the number of trees
to be cut etc, have been worked out as part of the design
finalisation. However, there will be a significant tree felling due
to the project. Though no major change in the macro-climatic
setting (precipitation, temperature and wind) is envisaged due to
the project, the microclimate is likely to be temporarily modified
by vegetation removal, loss of roadside plantations and the
addition of increased pavement surface. Compensatory afforestation,
planting along the alignment and landscaping proposed shall help in
restoring the green cover along the corridor along with the
microclimate conditions that exist before the removal of trees,
within 2-3 years.
6.2 Land
Land Acquisition, soil erosion and contamination of soil have
emerged as major sources of land impact especially in urban areas
and nearby watercourses. Due to the proposed fast train network
aimed at enhancing the efficiency of transport system, which will
result in economic growth in the region over time.
6.2.1 Change in Geology - No blasting is envisaged. Quarry Development Plan need to be enforced.
6.2.2 Change in Seismology - Cross drainage structures are checked and complied with the seismological settings of the region (Zone).
6.2.3 Generation of Debris - Disposed properly to avoid contamination.
6.2.4 Soil Erosion - Embankment protection
through:
a) Stone pitching
b) Turfing
Residual spoil need to be disposed properly. Silt Fencing need to be provided. Quarries need to be reclaimed
Incorporating appropriate type of treatments of slopes has reduced the potential for erosion of high embankments and bridge fills. The soil is assumed to have an angle of repose corresponding to 1V: 2H. Slope protection is normally required only for slopes steeper than this.
6.3 Soil Quality Monitoring – Mitigation
The quality of the soil shall be monitored to find out the
effectiveness of the mitigation measures and further improvement in
designs if required. The monitoring plan shall be functional in
construction as well as in operation stages.
6.4 Air Quality – Mitigation
Dust Control
All precautions to reduce the level of dust emissions from the hot
mix plants, crushers and batching plants and other transportation
of materials will be taken up including:
a) Vehicles delivering loose and fine materials like sand and fine
aggregates shall be covered to reduce spills on existing
roads
b) Water will be sprayed on earthworks, temporary haulage and
detour roads on a regular basis. During and after compaction of the
sub-grade, water will be sprayed at regular intervals to prevent
dust generation.
Emission Control
To ensure the control of exhaust emissions from the various
construction activities, the contractor and the concessionaire
shall take up the following mitigation measures:
a) The asphalt plants and the batching plants will be sited at
least 1 km in the downwind direction from the nearest human
settlement.
b) An adequate cyclone / scrubber to control emissions from the
stack of hot mix plants will need to be provided in the event of
the emissions exceeding the pollution norms. Other potential
measures include plantation around periphery of the hot-mix
plants.
c) To ensure the efficacy of the mitigation measures suggested, air
quality monitoring shall be carried out at least once a month
during the period the plant is in operation.
d) All vehicles, equipment and machinery used for construction will
be regularly maintained to ensure that the pollution emission
levels conform to the pollution norms. A vehicle maintenance
schedule prepared by the contractor and the concessionaire and
approved by the Engineer shall be adhered to.
6.5 Water – Mitigation
Loss of Water Resources
Loss of water resources includes removal of private and community
water resources like hand pumps, water taps, OHTs, ponds, well etc.
The losses have been covered under the utility relocation process.
Compensatory water supply sources will be set up before the start
of construction with location of the new point as close to the
original as possible.
Drainage and Hydrological flow
Various streams and irrigation canals at different locations have
intersected the project corridor. To facilitate the cross-drainage
at these water crossings, 140 cross-drainage structures including
minor bridges, slab, box and pipe culverts are proposed. The
existing minor bridge has been retained with widening on LHS. The
proposed span arrangement and other particulars of the structures
are provided in the Design Report of the Draft DPR.
Mitigation measures will include contractual obligations for
relocation of sources of water supply at locations desired by the
host community, provision of balancing culverts of adequate
capacity where the level of the formation is being raised, and
provision for adequately sized drains to prevent flooding etc. All
these measures form a part of the good engineering practice and
should be part of the design drawings themselves.
a) To ensure efficient flow of surface water and to prevent water
logging along the side of the roads, adequate size and number of
cross-drainage structures have been provided.
b) Detailed drainage surveys and hydrological investigations have
been carried out and suitable design of bridges and culverts
proposed.
c) Provision of lined drains at settlement areas and unlined drains
at other areas.
Protecting Water Quality
To prevent any degradation of water quality of the various surface
and ground water resources due to the proposed project, the
contractor and the concessionaire shall work out the following
mitigative measures during the construction period:
a) Provision of necessary mitigation measures at the various
locations proposed in the design to prevent contamination and
degradation of water quality.
b) Construction work close to the streams or water bodies must be
avoided during monsoon.
c) The discharge standards promulgated under the Environmental
Protection Act, 1986 will be strictly adhered to.
d) Impact on the river / nallah system can be minimised if the
bridge construction is taken up during the lean flow season and
construction work close to the water bodies avoided during
monsoon.
e) The fuel storage and vehicle cleaning area shall be stationed at
least 500m away from the nearest drain / water body
f) The slope of the embankments leading to water bodies shall be
modified and re-channelled to prevent entry of contaminants into
the water body.
6.6 Noise - Mitigation
The contribution of project design towards mitigation of increased
noise levels would be the improved riding surface and geometry,
which will reduce vehicular noise generation, at least during the
initial years after construction. The mitigation measures for noise
are essentially aimed at protecting the receptor.
Noise and vibration during construction is a significant impact
especially around settlements and inhabited areas. During the
construction stage, the most vulnerable population is the
construction crew which is subjected to very high noise levels,
albeit intermittently. Provision of Personal Protective Equipment
(PPE) for the crew will be made a part of conditions of contract.
Specifying construction timings will prevent disturbance to the
local populations.