The Advanced Tech Company has a project to design an integrated information database for a major bank. Data for the project are given in the Table. Indirect project costs amount to $300 per day. The company will incur a $150 per day penalty for each day the project lasts beyond day 14. What would be the least cost to achieve this desired result?
| 
 Activity  | 
 Normal Time (days)  | 
 Normal Cost ($)  | 
 Crash Time (days)  | 
 Crash Cost ($)  | 
 Immediate Predecessor(s)  | 
| 
 A  | 
 6  | 
 1,000  | 
 5  | 
 1,200  | 
 —  | 
| 
 B  | 
 4  | 
 800  | 
 2  | 
 2,000  | 
 —  | 
| 
 C  | 
 3  | 
 600  | 
 2  | 
 900  | 
 A, B  | 
| 
 D  | 
 2  | 
 1,500  | 
 1  | 
 2,000  | 
 B  | 
| 
 E  | 
 6  | 
 900  | 
 4  | 
 1,200  | 
 C, D  | 
| 
 F  | 
 2  | 
 1,300  | 
 1  | 
 1,400  | 
 E  | 
| 
 G  | 
 4  | 
 900  | 
 4  | 
 900  | 
 E  | 
| 
 H  | 
 4  | 
 500  | 
 2  | 
 900  | 
 G  | 
Please refer the images for the solutions:
Note: We crash
A by 1 day, C by 1 day, E by 2 days, G cannot be crashed, H by 2 days. So total reduced days are 6 days.
23 - 6 DAYS = 17 DAYS. (minimum)