In: Operations Management
The Advanced Tech Company has a project to design an integrated information database for a major bank. Data for the project are given in the Table. Indirect project costs amount to $300 per day. The company will incur a $150 per day penalty for each day the project lasts beyond day 14. What would be the least cost to achieve this desired result?
Activity |
Normal Time (days) |
Normal Cost ($) |
Crash Time (days) |
Crash Cost ($) |
Immediate Predecessor(s) |
A |
6 |
1,000 |
5 |
1,200 |
— |
B |
4 |
800 |
2 |
2,000 |
— |
C |
3 |
600 |
2 |
900 |
A, B |
D |
2 |
1,500 |
1 |
2,000 |
B |
E |
6 |
900 |
4 |
1,200 |
C, D |
F |
2 |
1,300 |
1 |
1,400 |
E |
G |
4 |
900 |
4 |
900 |
E |
H |
4 |
500 |
2 |
900 |
G |
Please refer the images for the solutions:
Note: We crash
A by 1 day, C by 1 day, E by 2 days, G cannot be crashed, H by 2 days. So total reduced days are 6 days.
23 - 6 DAYS = 17 DAYS. (minimum)