Question

In: Finance

9) A firm with a WACC of 10% is considering the following mutually exclusive projects: 0...

9)

A firm with a WACC of 10% is considering the following mutually exclusive projects:

0 1 2 3 4 5
Project 1 -$200 $70 $70 $70 $165 $165
Project 2 -$550 $300 $300 $130 $130 $130

Which project would you recommend?

Select the correct answer.

a. Neither Project 1 nor 2, since each project's NPV < 0.
b. Project 2, since the NPV2 > NPV1.
c. Both Projects 1 and 2, since both projects have IRR's > 0.
d. Project 1, since the NPV1 > NPV2.
e. Both Projects 1 and 2, since both projects have NPV's > 0.

Solutions

Expert Solution

Project 1
Discount rate 10.000%
Year 0 1 2 3 4 5
Cash flow stream -200 70 70 70 165 165
Discounting factor 1.000 1.100 1.210 1.331 1.464 1.611
Discounted cash flows project -200.000 63.636 57.851 52.592 112.697 102.452
NPV = Sum of discounted cash flows
NPV Project 1 = 189.23
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
IRR is the rate at which NPV =0
IRR 36.20%
Year 0 1 2 3 4 5
Cash flow stream -200.000 70.000 70.000 70.000 165.000 165.000
Discounting factor 1.000 1.362 1.855 2.526 3.441 4.686
Discounted cash flows project -200.000 51.396 37.737 27.707 47.952 35.208
NPV = Sum of discounted cash flows
NPV Project 1 = 0.000
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
IRR= 36.20%
Project 2
Discount rate 10.000%
Year 0 1 2 3 4 5
Cash flow stream -550 300 300 130 130 130
Discounting factor 1.000 1.100 1.210 1.331 1.464 1.611
Discounted cash flows project -550.000 272.727 247.934 97.671 88.792 80.720
NPV = Sum of discounted cash flows
NPV Project 2 = 237.84
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
Project 2
IRR is the rate at which NPV =0
IRR 29.77%
Year 0 1 2 3 4 5
Cash flow stream -550.000 300.000 300.000 130.000 130.000 130.000
Discounting factor 1.000 1.298 1.684 2.185 2.836 3.680
Discounted cash flows project -550.000 231.184 178.153 59.491 45.844 35.328
NPV = Sum of discounted cash flows
NPV Project 2 = 0.000
Where
Discounting factor = (1 + discount rate)^(Corresponding period in years)
Discounted Cashflow= Cash flow stream/discounting factor
IRR= 29.77%


Related Solutions

A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$250 $55 $55 $55 $190 $190 Project 2 -$650 $300 $300 $40 $40 $40 Which project would you recommend? Select the correct answer. a. Neither Project 1 nor 2, since each project's NPV < 0. b. Project 2, since the NPV2 > NPV1. c. Both Projects 1 and 2, since both projects have IRR's > 0. d. Both...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1...
A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project 1 -$200 $40 $40 $40 $235 $235 Project 2 -$450 $200 $200 $80 $80 $80 Which project would you recommend? Select the correct answer. a. Both Projects 1 and 2, since both projects have IRR's > 0. b. Neither Project 1 nor 2, since each project's NPV < 0. c. Both Projects 1 and 2, since both projects have...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 Project A -$250 $50 $50 $50 $200 $200 Project B -$600 $300 $300 $70 $70 $70 Which project would you recommend? Select the correct answer. I. Both Projects A and B, since both projects have IRR's > 0. II. Project A, since the NPVA > NPVB. III. Both Projects A and B, since both...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the...
Capital budgeting criteria: mutually exclusive projects A firm with a WACC of 10% is considering the following mutually exclusive projects: Project A -$300 $75 $75 $75 $220 $220 Project B -$550 $250 $250 $80 $80 $80 Which project would you recommend? Select the correct answer. I. Both Projects A and B, since both projects have IRR's > 0. II. Project A, since the NPVA > NPVB. III. Project B, since the NPVB > NPVA. IV. Neither A or B, since...
Problem 11-10 Capital Budgeting Criteria: Mutually Exclusive Projects. A firm with a WACC of 10% is...
Problem 11-10 Capital Budgeting Criteria: Mutually Exclusive Projects. A firm with a WACC of 10% is considering the following mutually exclusive projects: 0 1 2 3 4 5 |--------------|-----------------|-----------------|-----------------|-------------------| Project A -$200 $75 $75 $75 $190 $190 Project B -$650 $250 $250 $125 $125 $125 Which project would you recommend? Explain.
Your firm is considering the following mutually exclusive projects: Year Project A Project B 0 -$3,300,000...
Your firm is considering the following mutually exclusive projects: Year Project A Project B 0 -$3,300,000 -$3,300,000 1 1,940,000 866,000 2 1,350,000 1,250,000 3 850,000 2,325,000 The firm uses a discount rate of 12.628%. At that discount rate we find that A-Project A is clearly preferred B-Project B is clearly preferred C-the projects have roughly the same NPV's Given that finding, the firm should select ___________because it's NPV is the least sensitive to change A-Project A B-Project B
A firm is considering two mutually exclusive projects, A and B. The projects are different in...
A firm is considering two mutually exclusive projects, A and B. The projects are different in that they have different returns depending on general economic conditions. The firm forecasts that return on the market, and the returns on each project, along with their associated probabilities will be given by the following table. You can assume a 5% risk free rate and a 6% market risk premium. Assume the CAPM holds. Compare the expected returns to the cost of capital for...
Assume the projects below are mutually exclusive and the WACC is 10%. Which project should be...
Assume the projects below are mutually exclusive and the WACC is 10%. Which project should be chosen based on each of the following decision rules: NPV, IRR, MIRR, and Payback? Overall, which project should be chosen? Year Project A Project B 0 -$75,000.00 -$110,000.00 1 $46,000.00 $50,000.00 2 $24,000.00 $35,000.00 3 $10,000.00 $20,000.00 4 $10,000.00 $10,000.00 5 $6,000.00 $10,000.00 6 $4,000.00 $30,000.00
Braun Industries is considering the following mutually exclusive projects. Braun’s cost of capital is 9%.           ...
Braun Industries is considering the following mutually exclusive projects. Braun’s cost of capital is 9%.            Year        Project A                Project B             0             ($86,000)                ($86,000)             1             $42,000                  $63,000             2             $32,000                  $28,000 3             $12,900                  $8,000      4             $12,200                  $3,000 5             $12,000                  $2,000 a.   Calculate each project’s NPV and IRR. b.   Find the Payback Period for each project. c.   Find the MIRR for each project. d.   Which of these projects should Braun accept? Why?
9. Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown...
9. Suppose your firm is considering two mutually exclusive, required projects with the cash flows shown below. The required rate of return on projects of both of their risk class is 8 percent, and that the maximum allowable payback and discounted payback statistic for the projects are 2 and 3 years, respectively.   Time: 0 1 2 3   Project A Cash Flow -25,000 15,000 35,000 6,000   Project B Cash Flow -35,000 15,000 25,000 55,000 Use the NPV decision rule to evaluate...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT